This table represents progress recorded since E8P02 Update No. 11.
Activity ID | Activity Description | Old Complete % | New Complete % | Change % |
---|---|---|---|---|
GC-GCN130 | PH MS - Start Phase IIA Construction | 0% | 100% | 100% |
GC-GCN140 | PH MS - Start Phase II B Construction | 0% | 100% | 100% |
GC-GCN150 | PH MS - Start Phase II C Construction | 0% | 100% | 100% |
GC-GCN160 | PH MS - Start Phase IV Construction | 0% | 100% | 100% |
GC-GCN170 | PH MS - Start Phase III B Construction | 0% | 100% | 100% |
GC-GCN180 | PH MS - Start Phase III C Construction | 0% | 100% | 100% |
GC-GCN190 | PH MS - Start Phase II D Construction | 0% | 100% | 100% |
GC-GCN200 | PH MS - Start Phase III A Construction | 0% | 100% | 100% |
GC-GCN220 | Written Suspend order - FOC related to pending change | 0% | 100% | 100% |
IAWBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 0% | 100% | 100% |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 0% | 100% | 100% |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 0% | 100% | 100% |
IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 50% | 100% | 50% |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 20% | 100% | 80% |
IBEBM-RW220 | PH IB - Grade (I4-International Drive) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW230 | PH IB - Grade (International Drive - Universal) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW250 | PH IB - Stabilization (I4-international Drive) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW260 | PH IB - Stabilization (International Drive - Universal) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW270 | PH IB - Stabilization (Universal - JYP) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | 70% | 100% | 30% |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | 90% | 100% | 10% |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0% | 100% | 100% |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0% | 100% | 100% |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 0% | 100% | 100% |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 0% | 100% | 100% |
IBEBM-ST550 | PH IB - Approach Slabs - EB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBEBM-ST580 | PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBEBM-ST590 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBEBM-ST600 | PH IB - Grind and Groove - EB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST730 | PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 0% | 100% | 100% |
IBEBM-ST770 | PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST780 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST790 | PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBEBM-ST840 | PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBEBM-ST860 | PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBEBM-ST870 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBEBM-ST880 | PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0% | 100% | 100% |
IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | 75% | 100% | 25% |
IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | 70% | 100% | 30% |
IBEBO-EW120 | PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside Widening | 0% | 100% | 100% |
IBEBO-EW130 | PH IB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 84% | 100% | 16% |
IBEBO-EW140 | PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside Widening | 84% | 100% | 16% |
IBEBO-EW150 | PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside Widening | 90% | 100% | 10% |
IBEBO-EW160 | PH IB - Pond Excav/Embank Universal to JYP - EB Outside Widening | 70% | 100% | 30% |
IBEBO-EW170 | PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside Widening | 45% | 100% | 55% |
IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | 10% | 100% | 90% |
IBR-AP120 | PH IB - Asphalt - Structural - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-EW100 | PH IB - Embankment - Ramp B/C Gore | 0% | 100% | 100% |
IBR-EW110 | PH IB - Embankment - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) | 0% | 100% | 100% |
IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | 75% | 100% | 25% |
IBR-RW100 | PH IB - Stabilization - Ramp B/C Gore | 0% | 100% | 100% |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 0% | 100% | 100% |
IBR-RW120 | PH IB - Stabilization - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-RW130 | PH IB - Base - Ramp C (Redundant) | 0% | 100% | 100% |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | 0% | 100% | 100% |
IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) | 0% | 100% | 100% |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 50% | 100% | 50% |
IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 20% | 100% | 80% |
IBWBM-RW130 | PH IB - Grade (JYP-Universal) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW140 | PH IB - Stabilization (JYP-Universal) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW150 | PH IB - Base (JYP-Universal) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW160 | PH IB - Grade (Universal-International Drv.) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW170 | PH IB - Stabilization (Universal-International Drv.) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW190 | PH IB - Grade (International Drive-I4) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW200 | PH IB - Stabilization (International Drv.-I4) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 0% | 100% | 100% |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 0% | 100% | 100% |
IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | 90% | 100% | 10% |
IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | 85% | 100% | 15% |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 0% | 100% | 100% |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 0% | 100% | 100% |
IBWBM-ST390 | PH IB - Approach Slabs - WB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBWBM-ST430 | PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBWBM-ST440 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBWBM-ST470 | PH IB - Grind and Groove - WB Median Widening (Bridge over International DR) | 0% | 100% | 100% |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 0% | 100% | 100% |
IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST630 | PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST640 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST650 | PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | 40% | 100% | 60% |
IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IBWBM-ST680 | PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBWBM-ST690 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBWBM-ST700 | PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | 0% | 100% | 100% |
IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | 60% | 100% | 40% |
IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | 90% | 100% | 10% |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 40% | 100% | 60% |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 0% | 100% | 100% |
IIAEBO-AP100 | PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 0% | 100% | 100% |
IIAR-EW100 | PH IIB - Embankment - Ramp O | 75% | 100% | 25% |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 0% | 100% | 100% |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 0% | 100% | 100% |
IIAR-RW110 | PH IIB - Base - Ramp O | 0% | 100% | 100% |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 0% | 100% | 100% |
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 90% | 100% | 10% |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 0% | 100% | 100% |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 0% | 100% | 100% |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0% | 100% | 100% |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0% | 100% | 100% |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0% | 100% | 100% |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0% | 100% | 100% |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 20% | 100% | 80% |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 0% | 100% | 100% |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 0% | 100% | 100% |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 0% | 100% | 100% |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 0% | 100% | 100% |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 0% | 100% | 100% |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 0% | 100% | 100% |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0% | 100% | 100% |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 0% | 100% | 100% |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 0% | 100% | 100% |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 0% | 100% | 100% |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 0% | 100% | 100% |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 0% | 100% | 100% |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 0% | 100% | 100% |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST11 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST120 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST130 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST150 | PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST16 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST17 | PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLV | 0% | 100% | 100% |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST18 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST200 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | 60% | 100% | 40% |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 0% | 100% | 100% |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST25 | PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST250 | PH IIB - Set Beams - EB Outside Widening (Bridge over International Drive) | 0% | 100% | 100% |
IIBEBO-ST26 | PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ov | 65.97% | 100% | 34.03% |
IIBEBO-ST260 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST270 | PH IIB - Superstructure Deck - EB Outside Widening (Bridge over International Drive) | 0% | 100% | 100% |
IIBEBO-ST280 | PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | 20% | 100% | 80% |
IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST320 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST360 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST380 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 55% | 100% | 45% |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST420 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST430 | PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST450 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST460 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST470 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST480 | PH IIB - Set Beams - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST500 | PH IIB - Superstructure Deck SIP / Overhangs / Edges - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST520 | PH IIB - Superstructure Deck Rebar - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST530 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST550 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST560 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST600 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST610 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST690 | PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 95% | 100% | 5% |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-ST710 | PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0% | 100% | 100% |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 0% | 100% | 100% |
IIBEBO-ST730 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 0% | 100% | 100% |
IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 0% | 100% | 100% |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 0% | 100% | 100% |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 0% | 100% | 100% |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 0% | 100% | 100% |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 0% | 100% | 100% |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 0% | 100% | 100% |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 0% | 100% | 100% |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0% | 100% | 100% |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 0% | 100% | 100% |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 0% | 100% | 100% |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 0% | 100% | 100% |
IIBR-AP160 | PH IIB - Asphalt - Structural - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-AP170 | PH IIB - Asphalt - Structural - Ramp L | 0% | 100% | 100% |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 0% | 100% | 100% |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 0% | 100% | 100% |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 0% | 100% | 100% |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 0% | 100% | 100% |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 0% | 100% | 100% |
IIBR-EW110 | PH IIB - Embankment - Ramp E | 50% | 100% | 50% |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 33% | 100% | 67% |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 0% | 100% | 100% |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 0% | 100% | 100% |
IIBR-EW150 | PH IIB - Embankment - Ramp I-1 | 0% | 100% | 100% |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 0% | 100% | 100% |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 0% | 100% | 100% |
IIBR-EW180 | PH IIB - Embankment - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-EW190 | PH IIB - Embankment - Ramp L | 0% | 100% | 100% |
IIBR-EW200 | PH IIB - Embankment - Ramp U | 33% | 100% | 67% |
IIBR-EW210 | PH IIB - Embankment - Ramp D | 0% | 100% | 100% |
IIBR-GC110 | PH IIB - Demo - Ramp E | 0% | 100% | 100% |
IIBR-GC130 | PH IIB - Demo - Ramp R-1 | 0% | 100% | 100% |
IIBR-GC140 | PH IIB - Demo - Ramp I-1 | 0% | 100% | 100% |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 0% | 100% | 100% |
IIBR-GC170 | PH IIB - Demo - Ramp C | 0% | 100% | 100% |
IIBR-GC220 | PH IIB - Guardrail (Roadway) - Ramp E | 0% | 100% | 100% |
IIBR-GC240 | PH IIB - Demo - Ramp H | 0% | 100% | 100% |
IIBR-GC260 | PH IIB - Guardrail (Roadway) - Ramp I-1 | 0% | 100% | 100% |
IIBR-GC290 | PH IIB - Demo - Ramp R-2 | 0% | 100% | 100% |
IIBR-GC300 | PH IIB - Demo - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-GC310 | PH IIB - Demo - Ramp L | 0% | 100% | 100% |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 0% | 100% | 100% |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-GC350 | PH IIB - Demo - Ramp U | 0% | 100% | 100% |
IIBR-GC390 | PH IIB - Guardrail (Roadway) - Ramp R | 0% | 100% | 100% |
IIBR-GC400 | PH IIB - Guardrail (Roadway) - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 0% | 100% | 100% |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 0% | 100% | 100% |
IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | 45% | 100% | 55% |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 0% | 100% | 100% |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 0% | 100% | 100% |
IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | 50% | 100% | 50% |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 25% | 100% | 75% |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 0% | 100% | 100% |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 0% | 100% | 100% |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 0% | 100% | 100% |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 0% | 100% | 100% |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 0% | 100% | 100% |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 0% | 100% | 100% |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 0% | 100% | 100% |
IIBR-RW130 | PH IIB - Base - Ramp E | 0% | 100% | 100% |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 0% | 100% | 100% |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 0% | 100% | 100% |
IIBR-RW160 | PH IIB - Base - Ramp C | 0% | 100% | 100% |
IIBR-RW170 | PH IIB - Base - Ramp I-1 | 0% | 100% | 100% |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 0% | 100% | 100% |
IIBR-RW190 | PH IIB - Base - Ramp H | 0% | 100% | 100% |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 0% | 100% | 100% |
IIBR-RW210 | PH IIB - Stabilization - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 0% | 100% | 100% |
IIBR-RW230 | PH IIB - Base - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 0% | 100% | 100% |
IIBR-RW250 | PH IIB - Base - Ramp L | 0% | 100% | 100% |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 0% | 100% | 100% |
IIBR-RW270 | PH IIB - Base - Ramp U | 0% | 100% | 100% |
IIBR-RW290 | PH IIB - Shoulder Gutter - Ramp C | 0% | 100% | 100% |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 0% | 100% | 100% |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 0% | 100% | 100% |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 0% | 100% | 100% |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 0% | 100% | 100% |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 0% | 100% | 100% |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 0% | 100% | 100% |
IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | 35% | 100% | 65% |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 0% | 100% | 100% |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 0% | 100% | 100% |
IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 40% | 100% | 60% |
IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 40% | 100% | 60% |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 0% | 100% | 100% |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 0% | 100% | 100% |
IIBR-SP120 | PH IIB - Drainage (Temp) - Ramp R-1 | 0% | 100% | 100% |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 0% | 100% | 100% |
IIBR-SP140 | PH IIB - Drainage (Temp) - Ramp S-1 | 0% | 100% | 100% |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 0% | 100% | 100% |
IIBR-SP160 | PH IIB - Drainage (Temp) - Ramp H | 0% | 100% | 100% |
IIBR-SP170 | PH IIB - Drainage (Temp) - Ramp R-2 | 0% | 100% | 100% |
IIBR-SP180 | PH IIB - Drainage (Temp) - Ramp I4 Interstate | 0% | 100% | 100% |
IIBR-SP190 | PH IIB - Drainage (Temp) - Ramp L | 0% | 100% | 100% |
IIBR-SP200 | PH IIB - Drainage (Temp) - Ramp U | 0% | 100% | 100% |
IIBR-SP210 | PH IIB - Drainage - Ramp D | 0% | 100% | 100% |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 0% | 100% | 100% |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 0% | 100% | 100% |
IIBR-TC170 | PH IIB - Temp Striping for New Ramp Alignment - Ramp B | 0% | 100% | 100% |
IIBR-TC220 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp E | 0% | 100% | 100% |
IIBR-TC230 | PH IIB - Temp Striping New Ramp Alignment - Ramp E | 0% | 100% | 100% |
IIBR-TC250 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp C | 0% | 100% | 100% |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 0% | 100% | 100% |
IIBR-TC280 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1 | 0% | 100% | 100% |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-TC300 | PH IIB - Temp Striping New Ramp Alignment - Ramp I-1 | 0% | 100% | 100% |
IIBR-TC310 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp H | 0% | 100% | 100% |
IIBR-TC320 | PH IIB - Temp Striping New Ramp Alignment - Ramp H | 0% | 100% | 100% |
IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | 0% | 100% | 100% |
IIBR-TC340 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2 | 0% | 100% | 100% |
IIBR-TC360 | PH IIB - Temp Striping New Ramp Alignment - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-TC370 | PH IIB - MOT Shift New Ramp Alignment - Ramp I4- Interstate | 0% | 100% | 100% |
IIBR-TC380 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp L | 0% | 100% | 100% |
IIBR-TC390 | PH IIB - Temp Striping New Ramp Alignment - Ramp L | 0% | 100% | 100% |
IIBR-TC400 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp U | 0% | 100% | 100% |
IIBR-TC410 | PH IIB - Temp Striping New Ramp Alignment - Ramp U | 0% | 100% | 100% |
IIBR-TC440 | PH IIB - Temp Striping New Ramp Alignment - Ramp D | 0% | 100% | 100% |
IIBR-TC450 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp D | 0% | 100% | 100% |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0% | 100% | 100% |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 0% | 100% | 100% |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0% | 100% | 100% |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0% | 100% | 100% |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0% | 100% | 100% |
IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | 90% | 100% | 10% |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 0% | 100% | 100% |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 0% | 100% | 100% |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 0% | 100% | 100% |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 0% | 100% | 100% |
IICR-EW120 | PH IIC - Embankment - Ramp M | 0% | 100% | 100% |
IICR-GC100 | PH IIC - Demo - Ramp S-2 | 0% | 100% | 100% |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 0% | 100% | 100% |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 0% | 100% | 100% |
IICR-GC170 | PH IIC - Demo - Ramp M | 0% | 100% | 100% |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 0% | 100% | 100% |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 0% | 100% | 100% |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 0% | 100% | 100% |
IICR-RW140 | PH IIC - Base - Ramp M | 0% | 100% | 100% |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 0% | 100% | 100% |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0% | 100% | 100% |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 0% | 100% | 100% |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 0% | 100% | 100% |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 0% | 100% | 100% |
IICR-SP120 | PH IIC - Drainage - Ramp M | 0% | 100% | 100% |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0% | 100% | 100% |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 0% | 100% | 100% |
IICR-TC1020 | PH IIC - Temp Striping New Ramp Alignment - Ramp M | 0% | 100% | 100% |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 0% | 100% | 100% |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 0% | 100% | 100% |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0% | 100% | 100% |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 0% | 100% | 100% |
IICR-TC160 | PH IIC - Temp Striping New Ramp Alignment - Ramp S-2 | 0% | 100% | 100% |
IICR-TC170 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp S-2 | 0% | 100% | 100% |
IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H | 0% | 100% | 100% |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0% | 100% | 100% |
IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L | 0% | 100% | 100% |
IICR-TC210 | PH IIC - MOT Shift New Ramp Alignment - Ramp U | 0% | 100% | 100% |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0% | 100% | 100% |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 0% | 100% | 100% |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 0% | 100% | 100% |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 75% | 100% | 25% |
IIDEBO-ST150 | PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST160 | PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP) | 32.99% | 100% | 67.01% |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST230 | PH IID - Set Beams - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST270 | PH IID - Lighting Conduit - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 0% | 100% | 100% |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST310 | PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 95% | 100% | 5% |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDEBO-ST340 | PH IID - Curing for End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 0% | 100% | 100% |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 0% | 100% | 100% |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 0% | 100% | 100% |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0% | 100% | 100% |
IIIAWBO-AP100 | PH IIIA - Mill & Resurface (sacrificial) - WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IIIAWBO-ST111 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST120 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST130 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST140 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST150 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST170 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST181 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 50% | 100% | 50% |
IIIAWBO-ST191 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST200 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST21 | PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST22 | PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T | 32.99% | 100% | 67.01% |
IIIAWBO-ST230 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIAWBO-ST290 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | 91% | 100% | 9% |
IIIAWBO-ST33 | PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIIAWBO-ST330 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST34 | PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John | 32.99% | 100% | 67.01% |
IIIAWBO-ST340 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST410 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST420 | PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST520 | PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST570 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST590 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST600 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0% | 100% | 100% |
IIIAWBO-ST690 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 95% | 100% | 5% |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIAWBO-ST710 | PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 95% | 100% | 5% |
IIIAWBO-TC100 | PH IIIA - Install Sign & Traffic Control Devices - WB Outside Widening Area | 0% | 100% | 100% |
IIIAWBO-TC110 | PH IIIA - Temp Striping for Phase - WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IIIAWBO-TC120 | PH IIIA - MOT Shift for Phase - WB Outside Widening Area | 0% | 100% | 100% |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 0% | 100% | 100% |
IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J | 0% | 100% | 100% |
IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V | 0% | 100% | 100% |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 0% | 100% | 100% |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 0% | 100% | 100% |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 0% | 100% | 100% |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 0% | 100% | 100% |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 0% | 100% | 100% |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 0% | 100% | 100% |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 0% | 100% | 100% |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 0% | 100% | 100% |
IIIBR-EW120 | PH IIIB - Embankment - Ramp V | 0% | 100% | 100% |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 0% | 100% | 100% |
IIIBR-EW140 | PH IIIB - Embankment - Ramp T | 75% | 100% | 25% |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 0% | 100% | 100% |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 0% | 100% | 100% |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 0% | 100% | 100% |
IIIBR-GC140 | PH IIIB - Demo - Ramp J | 0% | 100% | 100% |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 0% | 100% | 100% |
IIIBR-GC180 | PH IIIB - Demo - Ramp V | 0% | 100% | 100% |
IIIBR-GC190 | PH IIIB - Demo - Ramp K | 0% | 100% | 100% |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 0% | 100% | 100% |
IIIBR-GC250 | PH IIIB - Demo - Ramp P | 0% | 100% | 100% |
IIIBR-GC260 | PH IIIB - Guardrail (Roadway) - Ramp K | 0% | 100% | 100% |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 0% | 100% | 100% |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 0% | 100% | 100% |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 0% | 100% | 100% |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0% | 100% | 100% |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0% | 100% | 100% |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 0% | 100% | 100% |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 0% | 100% | 100% |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 0% | 100% | 100% |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 0% | 100% | 100% |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 50% | 100% | 50% |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 0% | 100% | 100% |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 0% | 100% | 100% |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 0% | 100% | 100% |
IIIBR-RW130 | PH IIIB - Base - Ramp J | 0% | 100% | 100% |
IIIBR-RW140 | PH IIIB - Stabilization - Ramp V | 0% | 100% | 100% |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 0% | 100% | 100% |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 0% | 100% | 100% |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 0% | 100% | 100% |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 0% | 100% | 100% |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 0% | 100% | 100% |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 0% | 100% | 100% |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 0% | 100% | 100% |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 0% | 100% | 100% |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0% | 100% | 100% |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0% | 100% | 100% |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 0% | 100% | 100% |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0% | 100% | 100% |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 0% | 100% | 100% |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0% | 100% | 100% |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 0% | 100% | 100% |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0% | 100% | 100% |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 0% | 100% | 100% |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 0% | 100% | 100% |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 0% | 100% | 100% |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 0% | 100% | 100% |
IIIBR-SP100 | PH IIIB - Drainage (Temp) - Ramp G | 0% | 100% | 100% |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 0% | 100% | 100% |
IIIBR-SP120 | PH IIIB - Drainage (Temp) - Ramp V | 0% | 100% | 100% |
IIIBR-SP130 | PH IIIB - Drainage (Temp) - Ramp K | 0% | 100% | 100% |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 0% | 100% | 100% |
IIIBR-SP150 | PH IIIB - Drainage - Ramp P | 0% | 100% | 100% |
IIIBR-SP160 | PH IIIB - Drainage (Temp) - Ramp Q | 0% | 100% | 100% |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 0% | 100% | 100% |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 0% | 100% | 100% |
IIIBR-TC120 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp G | 0% | 100% | 100% |
IIIBR-TC130 | PH IIIB - Temp Striping New Ramp Alignment - Ramp G | 0% | 100% | 100% |
IIIBR-TC160 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp J | 0% | 100% | 100% |
IIIBR-TC170 | PH IIIB - Temp Striping New Ramp Alignment - Ramp J | 0% | 100% | 100% |
IIIBR-TC180 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp V | 0% | 100% | 100% |
IIIBR-TC190 | PH IIIB - Temp Striping New Ramp Alignment - Ramp V | 0% | 100% | 100% |
IIIBR-TC200 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp K | 0% | 100% | 100% |
IIIBR-TC210 | PH IIIB - Temp Striping New Ramp Alignment - Ramp K | 0% | 100% | 100% |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 0% | 100% | 100% |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 0% | 100% | 100% |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 0% | 100% | 100% |
IIIBR-TC270 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp Q | 0% | 100% | 100% |
IIIBR-TC280 | PH IIIB - Temp Striping New Ramp Alignment - Ramp Q | 0% | 100% | 100% |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0% | 100% | 100% |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0% | 100% | 100% |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 0% | 100% | 100% |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0% | 100% | 100% |
IIIBR120 | PH IIIB - Construct Ramp V Diversion - Ramp V | 0% | 100% | 100% |
IIIBR130 | PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp K | 0% | 100% | 100% |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0% | 100% | 100% |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0% | 100% | 100% |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 0% | 100% | 100% |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0% | 100% | 100% |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0% | 100% | 100% |
IIIBWBO-EW100 | PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 90% | 100% | 10% |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 70% | 100% | 30% |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 0% | 100% | 100% |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 0% | 100% | 100% |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0% | 100% | 100% |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 80% | 100% | 20% |
IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 0% | 100% | 100% |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 0% | 100% | 100% |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 0% | 100% | 100% |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 0% | 100% | 100% |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 0% | 100% | 100% |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 0% | 100% | 100% |
IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | 40% | 100% | 60% |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST12 | PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST13 | PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Uni | 0% | 100% | 100% |
IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST14 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 0% | 100% | 100% |
IIIBWBO-ST220 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST240 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST260 | PH IIIB - Wall Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST300 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST320 | PH IIIB - Curing for Pier 2, 3, (Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST330 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST340 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 0% | 100% | 100% |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 0% | 100% | 100% |
IIIBWBO-ST390 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over International Drive) | 0% | 100% | 100% |
IIIBWBO-ST4 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR) | 41% | 100% | 59% |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST460 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST470 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST5 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR) | 80% | 100% | 20% |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST530 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST540 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-ST640 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST690 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over International Drive) | 0% | 100% | 100% |
IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | 30% | 100% | 70% |
IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 0% | 100% | 100% |
IIIBWBO-ST8 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD) | 0% | 100% | 100% |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 0% | 100% | 100% |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 0% | 100% | 100% |
IIIBWBO-W101 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over Universal BLVD) | 0% | 100% | 100% |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0% | 100% | 100% |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0% | 100% | 100% |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 0% | 100% | 100% |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 0% | 100% | 100% |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 0% | 100% | 100% |
IIIC-CP10 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 0% | 100% | 100% |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 0% | 100% | 100% |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 0% | 100% | 100% |
IIICR-EW100 | PH IIIC - Embankment - Ramp F | 10% | 100% | 90% |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 0% | 100% | 100% |
IIICR-GC110 | PH IIIC - Demo - Ramp N | 0% | 100% | 100% |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 0% | 100% | 100% |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 0% | 100% | 100% |
IIICR-RW110 | PH IIIC - Base - Ramp F | 0% | 100% | 100% |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 0% | 100% | 100% |
IIICR-RW130 | PH IIIC - Base - Ramp N | 0% | 100% | 100% |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 0% | 100% | 100% |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 0% | 100% | 100% |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 0% | 100% | 100% |
IIICR-TC140 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp N | 0% | 100% | 100% |
IIICR-TC150 | PH IIIC - Temp Striping New Ramp Alignment - Ramp N | 0% | 100% | 100% |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 0% | 100% | 100% |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 0% | 100% | 100% |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 0% | 100% | 100% |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0% | 100% | 100% |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 0% | 100% | 100% |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0% | 100% | 100% |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
IIICWBO-ST220 | PH IIIA - Demo Bridge Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 0% | 100% | 100% |
ITS10-1000 | Issue Identification | 0% | 100% | 100% |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 0% | 100% | 100% |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0% | 100% | 100% |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0% | 100% | 100% |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 0% | 100% | 100% |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 0% | 100% | 100% |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 0% | 100% | 100% |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 0% | 100% | 100% |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 0% | 100% | 100% |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0% | 100% | 100% |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0% | 100% | 100% |
IVEBM-W180 | PH IV - Median Wall - FFP Stem - Station 259+50 to 311 | 0% | 100% | 100% |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 0% | 100% | 100% |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0% | 100% | 100% |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 0% | 100% | 100% |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0% | 100% | 100% |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 0% | 100% | 100% |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 0% | 100% | 100% |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 0% | 100% | 100% |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 0% | 100% | 100% |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 0% | 100% | 100% |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 0% | 100% | 100% |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 0% | 100% | 100% |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 0% | 100% | 100% |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 0% | 100% | 100% |
IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express | 0% | 100% | 100% |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 0% | 100% | 100% |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 0% | 100% | 100% |
PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | 0% | 100% | 100% |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 95% | 100% | 5% |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 95% | 100% | 5% |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 95% | 100% | 5% |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 95% | 100% | 5% |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 95% | 100% | 5% |
PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | 50% | 100% | 50% |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 0% | 100% | 100% |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 0% | 100% | 100% |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 0% | 100% | 100% |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 0% | 100% | 100% |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 0% | 100% | 100% |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 0% | 100% | 100% |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 0% | 100% | 100% |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 50% | 100% | 50% |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 75% | 100% | 25% |
PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals | 0% | 100% | 100% |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 0% | 100% | 100% |
PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector | 0% | 100% | 100% |
PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | 0% | 100% | 100% |
PRE-FA-030 | Fabricate and Deliver 042200 Masonry | 0% | 100% | 100% |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 0% | 100% | 100% |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 0% | 100% | 100% |
PRE-FA-033 | Fabricate and Deliver 101400 Signage | 0% | 100% | 100% |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 0% | 100% | 100% |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 0% | 100% | 100% |
PRE-FA-036 | Fabricate and Deliver 232000 Piping and Specialties | 0% | 100% | 100% |
PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 0% | 100% | 100% |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 0% | 100% | 100% |
PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | 50% | 100% | 50% |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 0% | 100% | 100% |
PRE-FA-044 | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable | 50% | 100% | 50% |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 50% | 100% | 50% |
PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | 50% | 100% | 50% |
PRE-FA-047 | Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS) | 50% | 100% | 50% |
PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | 50% | 100% | 50% |
PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | 75% | 100% | 25% |
PRE-PS-006 | Prepare and Submit Precast Erection | 75% | 100% | 25% |
PRE-PS-017 | Prepare and Submit 646 Aluminum Pedestal Poles | 0% | 100% | 100% |
PRE-PS-018 | Prepare and Submit 650 Traffic Signals | 50% | 100% | 50% |
PRE-PS-019 | Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead) | 85% | 100% | 15% |
PRE-PS-020 | Prepare and Submit 992 Under deck Lighting | 0% | 100% | 100% |
PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | 75% | 100% | 25% |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 0% | 100% | 100% |
PRE-PS-026 | Prepare and Submit 653 Pedestrian Signals | 0% | 100% | 100% |
PRE-PS-027 | Prepare and Submit 663 Signal Priority and Preemption Systems | 85% | 100% | 15% |
PRE-PS-028 | Prepare and Submit 665 Pedestrian Detector | 0% | 100% | 100% |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 0% | 100% | 100% |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 0% | 100% | 100% |
PRE-PS-031 | Prepare and Submit 081100 Metal Doors and Frames | 0% | 100% | 100% |
PRE-PS-032 | Prepare and Submit 099100 Painting Product Data and Sample | 0% | 100% | 100% |
PRE-PS-033 | Prepare and Submit 101400 Signage | 0% | 100% | 100% |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 0% | 100% | 100% |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 0% | 100% | 100% |
PRE-PS-036 | Prepare and Submit 232000 Piping and Specialties | 0% | 100% | 100% |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-PS-038 | Prepare and Submit 238119 Packaged Air Conditioners | 0% | 100% | 100% |
PRE-PS-039 | Prepare and Submit 260536 Cable Trays | 0% | 100% | 100% |
PRE-PS-040 | Prepare and Submit 264113 Lighting Protection System Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-RA-001 | Review and Approve 506 Bridge Drainage System | 0% | 100% | 100% |
PRE-RA-017 | Review and Approve 646 Aluminum Pedestal Poles | 0% | 100% | 100% |
PRE-RA-018 | Review and Approve 650 Traffic Signals | 0% | 100% | 100% |
PRE-RA-019 | Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead) | 90% | 100% | 10% |
PRE-RA-020 | Review and Approve 992 Under deck Lighting | 0% | 100% | 100% |
PRE-RA-021 | Review and Approve 05500 Metal Fabrications | 90% | 100% | 10% |
PRE-RA-022 | Review and Approve 133420 Pre-Engineered Precast Concrete Structure | 0% | 100% | 100% |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 0% | 100% | 100% |
PRE-RA-026 | Review and Approve 653 Pedestrian Signals | 0% | 100% | 100% |
PRE-RA-027 | Review and Approve 663 Signal Priority and Preemption Systems | 40% | 100% | 60% |
PRE-RA-028 | Review and Approve 665 Pedestrian Detector | 0% | 100% | 100% |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 0% | 100% | 100% |
PRE-RA-030 | Review and Approve 042200 Masonry | 0% | 100% | 100% |
PRE-RA-031 | Review and Approve 081100 Metal Doors and Frames | 0% | 100% | 100% |
PRE-RA-032 | Review and Approve 099100 Painting Product Data and Sample | 0% | 100% | 100% |
PRE-RA-033 | Review and Approve 101400 Signage | 0% | 100% | 100% |
PRE-RA-034 | Review and Approve 231113 Fuel Oil Piping | 0% | 100% | 100% |
PRE-RA-035 | Review and Approve 231323 Aboveground Diesel Storage Tank and Piping | 0% | 100% | 100% |
PRE-RA-036 | Review and Approve 232000 Piping and Specialties | 0% | 100% | 100% |
PRE-RA-037 | Review and Approve 233113 Ductwork Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-RA-038 | Review and Approve 238119 Packaged Air Conditioners | 0% | 100% | 100% |
PRE-RA-039 | Review and Approve 260536 Cable Trays | 0% | 100% | 100% |
PRE-RA-040 | Review and Approve 264113 Lighting Protection System Product Data and Shop Drawing | 0% | 100% | 100% |
PRE-RA-042 | Review and Approve 781 DMS | 90% | 100% | 10% |
TF-CO-001 | Foundation (FRP SOG) | 0% | 100% | 100% |
TF-CO-002 | Install Upright 1 D.S. | 0% | 100% | 100% |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 0% | 100% | 100% |
TF-CO-004 | Precast Erection | 0% | 100% | 100% |
TF-CO-005 | Install Upright 2 D.S. | 0% | 100% | 100% |
TF-CO-006 | FRP Conc. Roof Dec/c | 0% | 100% | 100% |
TF-CO-007 | Install Upright 3 D.S. | 0% | 100% | 100% |
TF-CO-008 | Constr. Pedestal | 0% | 100% | 100% |
TF-CO-009 | Const. Roof System | 0% | 100% | 100% |
TF-CO-010 | FRP Conc. Pad (Generator) | 0% | 100% | 100% |
TF-CO-011 | AS Build D.S. | 0% | 100% | 100% |
TF-CO-012 | Install Frames & Doors | 0% | 100% | 100% |
TF-CO-013 | Const. Screen Wall (Con.) | 0% | 100% | 100% |
TF-CO-014 | Pull Wire & Install Light Fixtures | 0% | 100% | 100% |
TF-CO-015 | Install HVAC | 0% | 100% | 100% |
TF-CO-016 | F+1 Generator | 0% | 100% | 100% |
TF-CO-017 | F+1 Fuel Tank | 0% | 100% | 100% |
TF-CO-018 | Install Lighting | 0% | 100% | 100% |
TF-CO-019 | Install Security System | 0% | 100% | 100% |
TF-CO-020 | Install Lightning Protection | 0% | 100% | 100% |
TF-CO-022 | Construct Sidewalk | 0% | 100% | 100% |
TF-CO-023 | Erect Truss | 0% | 100% | 100% |
TF-CO-024 | Wall Treatments (Ply) | 0% | 100% | 100% |
TF-CO-025 | Install Equip. Arm Supports | 0% | 100% | 100% |
TF-CO-027 | Cont. HVAC | 0% | 100% | 100% |
TF-FA-001 | Fabricate and Deliver Precast Erection | 0% | 100% | 100% |
TF-RA-001 | Review and Approve Precast Erection | 0% | 100% | 100% |
USDED-CO-002 | Duke Energy Distribution (B) | 50% | 100% | 50% |
IAWBO-EW100 | PH IA - Pond EXCAVATION (Shape 4A & 5A) - WB Outside Widening Area | 100% | 99% | -1% |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 0% | 98.02% | 98.02% |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 0% | 97.92% | 97.92% |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 0% | 96% | 96% |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 0% | 96% | 96% |
IBWBO-EW100 | PH IB - Pond Excav/Embank JYP to TPK - WB Outside Widening | 92% | 95% | 3% |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 0% | 95% | 95% |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 0% | 95% | 95% |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 0% | 95% | 95% |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 0% | 90% | 90% |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 0% | 90% | 90% |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 0% | 90% | 90% |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0% | 90% | 90% |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0% | 90% | 90% |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 0% | 90% | 90% |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 0% | 90% | 90% |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 0% | 88.01% | 88.01% |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 0% | 85% | 85% |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0% | 85% | 85% |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 0% | 83.33% | 83.33% |
IIBR-RW320 | PH IIB - Stabilization - Ramp D | 0% | 80% | 80% |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0% | 80% | 80% |
IVR-EC30 | PH IV - Erect Cantilevers (10-15) | 0% | 80% | 80% |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 0% | 75% | 75% |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 0% | 75% | 75% |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 0% | 75% | 75% |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 0% | 75% | 75% |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0% | 75% | 75% |
TF-CO-026 | Cont. Lightning | 0% | 75% | 75% |
TF-CO-029 | Install Conduit/Raceways | 0% | 75% | 75% |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 0% | 70% | 70% |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 0% | 70% | 70% |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0% | 60% | 60% |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 0% | 60% | 60% |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 0% | 60% | 60% |
IIBR-SP100 | PH IIB - Drainage - Ramp B | 0% | 50% | 50% |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 0% | 50% | 50% |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 0% | 50% | 50% |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0% | 50% | 50% |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | 0% | 50% | 50% |
TF-CO-031 | Toll Facility Finishes and Punchlist | 0% | 50% | 50% |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 0% | 30% | 30% |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 0% | 25% | 25% |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 0% | 25% | 25% |
TF-CO-030 | Pull Wire | 0% | 25% | 25% |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 0% | 20% | 20% |
This table represents activities added since E8P02 Update No. 11
Activity ID | Activity Description | Original Duration |
---|---|---|
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 5 |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 15 |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 12 |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 12 |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 15 |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 12 |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 15 |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 2 |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 12 |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 12 |
GC-GCN220 | Written Suspend order - FOC related to pending change | 50 |
IVR-SM710 | PH IV - Allow for TEC Install and Test | 21 |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 7 |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 4 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 10 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 8 |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 8 |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 8 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 8 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 15 |
ITS10-1000 | Issue Identification | 0 |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 0 |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 14 |
ITS10-1040 | Fabrication and Delivery - Conduits | 40 |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 7 |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 45 |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | 55 |
ITS10-1080 | Furnish & Install ITS Standby Generators | 19 |
ITS10-1090 | Furnish & Install - Conduit | 40 |
ITS10-1100 | ITS Generator Stand AloneTesting | 19 |
ITS10-1110 | Fabrication and Delivery - Conductors | 20 |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 3 |
ITS10-1130 | Furnish & Install - Conductors | 26 |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | 15 |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 12 |
ITS10-1160 | Furnish & Install - FOC Drops | 26 |
ITS10-1170 | Splice / Terminate FOC Drops | 12 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 2 |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 10 |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 5 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 4 |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 12 |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 5 |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 8 |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 3 |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 2 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 1 |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 10 |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 2 |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 10 |
IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 | 2 |
IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T | 2 |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 25 |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 20 |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 6 |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 8 |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 5 |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 15 |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 15 |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 15 |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 1 |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 1 |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | 2 |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 4 |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 4 |
IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider | 8 |
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | 5 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 8 |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 6 |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 6 |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | 4 |
IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider | 8 |
IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening | 5 |
IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express | 2 |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | 2 |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | 5 |
IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express | 2 |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | 2 |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | 5 |
IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express | 2 |
IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express | 5 |
IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express | 2 |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | 2 |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | 5 |
IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express | 2 |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 5 |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 8 |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 4 |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 4 |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 3 |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 8 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 8 |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 10 |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 3 |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 8 |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 6 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 22 |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 2 |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 10 |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | 10 |
IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) | 10 |
IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) | 10 |
IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) | 10 |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 6 |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 2 |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 15 |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 4 |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 4 |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 10 |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 3 |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 4 |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 5 |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 5 |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 5 |
This table represents activities deleted since E8P02 Update No. 11
Activity ID | Activity Description |
---|---|
IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F |
IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) |
PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera |
PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure |
PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure |
PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera |
PRE-RA-048 | Review and Approve 785 ITS Infrastructure |
PRE-RA-043 | Review and Approve 782 ITS CCTV Camera |
IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT |
The following predecessor relationships were added since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Predecessor Activity ID |
---|---|---|---|---|
GC-GCN220 | Written Suspend order - FOC related to pending change | 0 | FS | ITS10-1000 |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 0 | FS | IBEBM-RW290 |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 0 | FS | IBEBM-RW300 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 0 | FS | IIBEBO-AP110 |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0 | FS | IIBEBO-RW150 IIBEBO-ST580 |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0 | FS | IIBEBO-RW140 IIBEBO-RW160 IIBEBO-SP120 |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IIBEBO-RW180 |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIBEB-TC110 IIBEBO-AP110 IIBEBO-GC110 |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 0 | FS | IBEBM-AP120 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 0 | FS | IIBEBO-RW170 |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 0 | FS | IIBEBO-EW100 |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 0 | FS | IIBEBO-EW101 |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 0 | FS | IIBEBO-EW101 |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 0 | FS | GC-GCN140 |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 0 | FS | IIIBWBO-W110 |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 0 | FS | IIBR-EW130 |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 0 | FS | IIBR-EW170 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 0 | FS | IICR-GC100 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0 | FS | IIBR-AP110 IICR-TC120 |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 0 | FS | IIBR-AP140 IICR-TC180 |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 0 | FS | IICR-TC150 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 0 | FS | IICR-TC200 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0 | FS | IIBEBO-AP140 IIBEBO-ST620 IICR-TC130 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 0 | FS | IIBEBO-W150 |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IBEBM-RW330 IBEBM-TC220 IBWBM-RW230 IIIAR100 |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIBEBO-AP145 IIBR-AP120 IIBR-TC430 |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW240 IIIBR-RW250 |
IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 | 0 | FS | IIIBWBO-AP110 |
IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-AP140 |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 0 | SS | IVEBO-SS100 |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | 0 | FS | GC-GCN220 IIIBR-ITS90 |
IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) | 0 | FS | IIIBR-ITS1030 |
IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) | 0 | FS | IIIBR-ITS1040 |
IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) | 0 | FS | IIIBR-ITS1050 |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW250 |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC370 |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-RW270 IIIBWBO-SP170 |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-GC210 IIICR170 |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 0 | FS | IIIAWBO-SP100 |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 0 | FS | IIIBR-SP170 |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 0 | FS | IIIBR-SP180 |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIAWBO-ST211 IIIBR-GC300 IIIBR-GC320 IIIBWBO-AP100 IIIBWBO-ST150 |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IIIBR-GC400 IIIBR-TC230 |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIBEBO-AP145 IIBR-SM460 IIIBR-SM550 |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC380 |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0 | FS | IIIBWBO-RW150 IIIBWBO-RW180 |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 0 | FS | GC-GCN170 |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0 | FS | IIBEBO-W160 IIIBWBO-W110 IIIBWBO-W140 |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW170 |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 0 | FS | IIIBWBO-EW110 |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 0 | FS | IIIBWBO-EW110 IIIBWBO-RW100 |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 0 | FS | IIIBWBO-EW120 |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 0 | FS | IIIBWBO-RW110 |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 0 | FS | IIBR-EHM370 IIIBR-RW270 |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 0 | FS | IIIBWBO-W130 |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | 0 | FS | IIICR-TC130 |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 0 | FS | IIICR-AP100 IIICR-AP120 |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 0 | FS | IIIBR-AP100 |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 0 | FS | IIIBR-AP110 |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0 | FS | IIICR-AP110 |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 0 | FS | IIIBR-AP130 |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IIIBR-AP150 IIIBR-TC290 IIIBWBO-ST150 |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 0 | FS | IIIBR-TC230 IIIBR-TC300 |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IIIBR-AP160 IIIBR-GC350 IIIBR-GC360 |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 0 | FS | IIIBR-AP120 |
ITS10-1000 | Issue Identification | 0 | FS | GC-DP100 |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 0 | FS | ITS10-1000 |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 | FS | GC-GCN220 ITS10-1010 |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0 | FS | ITS10-1020 |
ITS10-1040 | Fabrication and Delivery - Conduits | 0 | FS | ITS10-1030 |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1020 |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1050 |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | 0 | FS | ITS10-1060 |
ITS10-1080 | Furnish & Install ITS Standby Generators | 0 | FS | ITS10-1070 |
ITS10-1090 | Furnish & Install - Conduit | 0 | FS | ITS10-1040 |
ITS10-1100 | ITS Generator Stand AloneTesting | 0 | FS | ITS10-1080 |
ITS10-1110 | Fabrication and Delivery - Conductors | 0 | FS | ITS10-1030 |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 0 | FS | ITS10-1090 |
ITS10-1130 | Furnish & Install - Conductors | 0 | FS | ITS10-1110 ITS10-1120 |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | 0 | FS | ITS10-1030 |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 0 | FS | ITS10-1130 ITS10-1140 |
ITS10-1160 | Furnish & Install - FOC Drops | 0 | FS | ITS10-1090 |
ITS10-1170 | Splice / Terminate FOC Drops | 0 | FS | ITS10-1160 |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 0 | FS | IVWBM-RW250 |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 0 | FS | IVWBM-RW300 IVWBM-RW320 |
IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider | 0 | FS | IVEBO-AP120 |
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | 0 | FS | IVEBM-PM110 IVEBO-AP120 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0 | FS | IVEBM-TC120 IVWBM-RW290 |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 0 | FS | IVEBM-W230 |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 0 | FS | IVEBM-W240 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IIIBR-TC300 IVEBM-TC120 IVEBM-W230 IVWBM-RW310 IVWBM-RW360 |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 0 | FS | IVEBM-W260 |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 0 | FS | IVEBM-W270 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIAR-GC100 IIBR-GC210 IIBR-GC320 IIBR-GC330 IIBR-GC370 IIBR-GC470 IICR-GC180 IICR-RW350 IIIBR-CP10 IIIBR-CP170 IIIBR-GC110 IIIBR-GC150 IIIBR-GC220 IIIBR-GC350 IIIBR-GC390 IIICR-GC100 IIICR-GC120 IIICR-GC130 IIICR120 IIICR150 IIICR170 IIICR180 IIICR190 IVR-IPM100 |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 3 | FF | IIBEBM-GC110 IIIBWBM-GC110 IVEBM-AP100 IVEBM-AP110 IVEBM-AP120 IVEBM-TC110 IVR-ET50 IVR-ET60 IVWBO-AP100 |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIBR-GC460 IICR-GC110 IIIAWBO-ST211 IIIBR-GC200 IIIBR-GC280 IIIBR-SM640 IIICR180 IIICR200 IVEBO-SS100 |
IVR-SM710 | PH IV - Allow for TEC Install and Test | 0 | FS | IVEBM-AP110 IVWBM-AP110 |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 0 | FS | IVWBM-RW170 |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | 0 | FS | IVWBM-RW340 IVWBM-RW370 |
IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider | 0 | FS | IVWBO-AP110 |
IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening | 10 | FS | IVWBO-AP110 |
IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express | 0 | FS | IVEBM-TC120 |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | 0 | FS | IVWBM-RW285 |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | 0 | FS | IVEBM-W250 IVWBM-RW290 |
IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express | 0 | FS | IVEBM-TC120 |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | 0 | FS | IVWBM-RW305 |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | 0 | FS | IVEBM-W280 IVWBM-RW310 |
IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW350 |
IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW330 |
IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express | 0 | FS | IIIBR-TC300 |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | 0 | FS | IVWBM-RW380 |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | 0 | FS | IVEBM-W280 IVWBM-RW360 |
IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express | 0 | FS | IIIBR-TC300 |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | IVWBM-AP100 IVWBM-AP110 IVWBM-AP130 IVWBM-TC110 |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IVEBM-PM120 IVR-SM710 IVWBM-PM130 NA-GC100 |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IBEBM-AP100 |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IBWBO-SP160 IBWBO-SP190 IICR-RW340 IICR-RW360 IICR-TC140 |
GC-GCN170 | PH MS - Start Phase III B Construction | 0 | FS | IIBEBO-SP160 |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVEBO-AP100 IVEBO-AP110 IVEBO-AP120 IVML-AP130 IVWBM-PM110 IVWBO-AP100 IVWBO-AP110 NA-GC110 |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 0 | FS | IBEBM-RW310 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0 | FS | IBEBM-TC110 |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC130 IBEBM-TC210 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IIBEBO-AP140 IIBEBO-ST620 IICR-SP130 |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 0 | FS | IIBR-EW140 |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 0 | FS | IIAR-TC120 IIBR-TC160 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 0 | FS | IVEBM-AP120 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 0 | FS | IIBEBO-RW120 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 0 | FS | IIBEBO-AP120 IIBEBO-AP140 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 0 | FS | IBEBM-AP100 IIBEBO-SP100 IIBEBO-SP130 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IBEBM-AP110 IIBEBO-SP140 IIBEBO-SP150 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 0 | FS | IBEBM-AP120 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-RW112 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 0 | FS | GC-GCN120 |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | GC-GCN120 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST240 IIBEBO-ST300 |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST4 IIBEBO-W120 |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST4 IIBEBO-W110 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-W120 |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST32 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IIBEBO-W130 |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST160 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 0 | FS | IIBEBO-W100 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-EW101 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-ST510 IICR-GC120 PRE-FA-015 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0 | FS | IIIBWBO-RW160 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 0 | FS | USDED-CO-001 |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 0 | FS | GC-GCN110 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 0 | FF | IICR-RW350 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 0 | FS | IIBR-GC450 |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 0 | FS | GC-GCN140 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 0 | FS | IIIBR-ITS1010 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 0 | FS | IIBR-SP240 IIBR-SP250 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0 | FS | IIBEBO-W150 IIDEBO-ST280 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0 | FS | GC-GCN120 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 0 | FS | GC-GCN120 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0 | FS | GC-GCN120 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | GC-GCN120 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | GC-GCN120 |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 0 | FS | IICR-GC190 |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 0 | FS | IIBEBO-AP140 IIBEBO-ST620 |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | IIBR-AP120 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | GC-GCN120 IICR-TC190 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST100 |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | GC-GCN140 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST200 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST220 |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST130 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST320 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IICR-GC120 |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 IIDEBO-ST210 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 0 | FS | GC-GCN120 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | GC-GCN120 |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IIIBWBO-ST150 |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 0 | FS | IIBR-GC340 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-RW260 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 0 | FS | IIIBR-GC250 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 0 | FS | IIIBR-GC280 IIIBR-TC290 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIBR-ITS40 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | GC-GCN220 IIIBR-ITS1020 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 0 | FS | IIIBR-ITS90 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 0 | FS | IIIBR-ITS90 IIIBR-ITS1020 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 0 | FS | IIIBR-ITS140 IIIBR-ITS150 IIIBR-ITS1060 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0 | FS | GC-GCN120 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS1000 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 0 | FS | IIIBR-SP150 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 0 | FS | IIIBWBO-RW140 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | SS | IIIBR-SM570 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 0 | FS | IIIBWBO-EW110 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBR-SM620 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IIIBWBO-EW110 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 0 | SS | IIIBWBO-EW110 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IIIBR-SM570 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 0 | FS | IIIBWBO-EW110 |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-AP140 |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 0 | FS | GC-GCN120 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0 | FS | GC-GCN120 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0 | FS | GC-GCN140 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 0 | FS | IIIBWBO-RW140 |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 4 | FF | IIIBWBO-SP100 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 0 | FS | IBWBM-TC150 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IIIBWBO-EW140 |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 0 | FS | IIIBWBO-AP120 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0 | FS | GC-GCN170 IIBEBO-AP130 IIBEBO-AP140 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FF | GC-GCN170 IIBEBO-AP120 IIIBWBO-SP150 IIIBWBO-ST490 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-EW130 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 1 | FF | IIIBWBO-SP140 |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 0 | FF | IIIBWBO-RW110 IIIBWBO-SP160 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 0 | FS | GC-GCN120 |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-SP130 |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIBEBO-ST390 IICR-RW330 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IBEBM-TC220 IIIAR120 |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 0 | FS | IIIBWBO-ST250 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST2 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 0 | FS | IIIBWBO-ST211 IIIBWBO-ST280 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST250 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 IIIBWBO-ST750 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 0 | FS | IBWBM-AP100 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IICR-RW330 IIIBR-RES130 IIIBWB-TC100 IIIBWBO-SP120 IIIBWBO-W100 IIIBWBO-W111 IIIBWBO-W130 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-W130 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 0 | FS | IIIBWB-TC100 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 0 | FS | IICR-AP120 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 0 | FS | IVWBO-TC100 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | IIICR-AP100 |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 0 | FS | GC-GCN120 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 0 | FS | IIIBR-SP190 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 0 | FS | IVWBM-GC100 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IIBR-SM500 IIDEBO-RW150 IIIBR-IDS50 IVEBO-TC100 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 0 | FS | IVWBM-RW180 IVWBM-RW210 |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0 | FS | IVEBM-GC100 IVEBM-SP100 IVWBM-RW160 IVWBM-RW240 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 3 | SS | IVEBM-GC100 IVEBM-SP100 IVWBM-RW270 IVWBO-TC100 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IIBR-EHM370 IIDEBO-ST290 IIIBWBO-GC110 IVEBO-AP110 IVR-SM670 IVR-SM680 IVR-SM690 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 0 | FS | IIBR-IB10 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 0 | FS | IIIBR-IDS50 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 0 | FS | PRE-FA-020 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0 | FS | PRE-FA-020 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 0 | FS | PRE-FA-020 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 0 | FS | PRE-FA-020 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 3 | SS | IVWBM-SP100 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 0 | FS | IVWBM-GC100 |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 0 | FS | IVEBM-W190 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 0 | FS | IVEBM-W160 |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-GC100 |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-W190 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 0 | FS | IVEBM-GC100 IVWBO-TC100 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 0 | FS | IVEBM-W220 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IBR-AP110 IBR-GC110 IIAR-TC120 IIAR-TC130 IIBR-AP120 IIBR-GC200 IIBR-TC420 IIIAWBO-ST211 IIIAWBO-ST620 IIIBWBO-ST150 IIIBWBO-ST510 IIIBWBO-ST550 IIICR120 IIICR130 IIICR140 IIICR150 IIICR160 IIICR190 IIICR200 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM510 IIIBR-SM520 IIIBR-SM540 IIIBR-SM560 IIIBR-SM590 IIIBWBO-AP120 IIIBWBO-GC110 IIIBWBO-GC120 IIICR-AP120 IIICR-GC140 IIICR-TC130 IIICR150 |
NA-GC100 | TEC Install and Test | 0 | FS | IVEBM-AP100 IVWBM-AP100 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | ITS10-1100 ITS10-1150 ITS10-1170 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 0 | FS | IIBEBO-EW112 |
TF-CO-017 | F+1 Fuel Tank | 0 | FS | PRE-FA-034 |
The following predecessor relationships were deleted since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Predecessor Activity ID |
---|---|---|---|---|
IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) | 0 | FS | IIIBR-SM570 |
IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT | 0 | FS | GC-GCN170 |
IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 0 | FS | IIIBR-AP100 IIICR-AP100 |
PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera | 0 | FS | PRE-RA-043 |
PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure | 0 | FS | PRE-RA-048 |
PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera | 0 | FS | GC-GC100 |
PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure | 0 | FS | GC-GC100 |
PRE-RA-043 | Review and Approve 782 ITS CCTV Camera | 0 | FS | PRE-PS-043 |
PRE-RA-048 | Review and Approve 785 ITS Infrastructure | 0 | FS | PRE-PS-048 |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IIIBWBO-RW140 |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IBEBM-TC130 IBWBM-RW230 IBWBO-SP160 IBWBO-SP190 USDED-CO-001 |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIAR-GC100 IIBEBM-GC110 IIBEBO-GC110 IIBR-SM500 IIDEBO-ST290 IIIAWBO-ST211 IIIAWBO-ST620 IIIBR-AP130 IIIBR-AP160 IIIBR-CP10 IIIBR-CP170 IIIBR-GC110 IIIBR-GC150 IIIBR-GC200 IIIBR-GC220 IIIBR-GC350 IIIBR-IHM330 IIIBWBM-GC110 IIIBWBO-GC110 IIIBWBO-ST150 IIIBWBO-ST510 IIIBWBO-ST550 IIIC-AP170 IIICR-GC120 IIICR-GC130 IIICR-TC130 |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | GC-GCN200 IIBR-AP100 IIBR-EHM370 IIBR-GC210 IIBR-GC320 IIBR-GC330 IIBR-GC340 IIBR-GC370 IIBR-GC450 IIBR-GC470 IIBR-TC420 IIBR-TC430 |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | GC-GCN170 IBEBM-TC220 IIIBR-GC110 IIIBR-GC150 IIIBR-GC280 IIIBR-GC300 IIIBWBO-ST510 IIIBWBO-ST550 |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IBEBM-RW330 IIBR-GC191 IICR-GC110 IICR-TC120 IICR-TC140 IICR-TC150 IICR-TC190 |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IBR-GC110 IIAR-TC130 IIBEBO-ST390 IIBEBO-ST580 |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IIIBWBO-GC110 IVEBM-AP100 IVWBM-AP100 |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening | 0 | FS | IBEBM-RW111 |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 0 | FS | IBEBM-RW290 |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-AP100 |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 0 | FS | IBEBM-AP100 IBEBM-TC110 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | GC-GCN170 |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B | 0 | FS | IBR-AP110 |
IIAR-TC120 | PH IIA - Construction 12' Widening on I-4 (NEBound) - Ramp I4- Interstate | 0 | FS | GC-GCN140 |
IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate | 0 | FS | GC-GCN140 |
IIBEBM-GC110 | PH IIB - Rumble Strip (Widening) - EB Median Widening | 0 | FS | IIBEBO-AP110 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening | 0 | FS | IIBEBO-RW140 IIBEBO-RW160 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-SP120 IIBEBO-W130 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-EW101 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening | 0 | FS | IIBEBO-EW102 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 0 | FS | IIBEBO-RW120 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR | 0 | FS | IIBEBO-RW150 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-RW140 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-SP100 |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | GC-GCN140 IBEBM-ST120 IBWBM-ST230 IBWBM-ST610 IBWBM-ST670 IIBR-EW120 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST410 |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST2 IIBEBO-ST7 |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST2 IIBEBO-ST140 IIBEBO-ST160 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST230 |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST230 |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IICR-AP120 IICR-GC180 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.3) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W110 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W120 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) | 0 | FS | GC-GCN140 GC-GCN150 IIBEBO-W130 |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 0 | FS | GC-GCN140 |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 0 | FS | IIBR-GC460 |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 0 | FS | IIBR-AP150 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 0 | FS | PRE-FA-043 |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 0 | FS | IIAR-TC120 IIAR-TC130 IIBR-TC270 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0 | FS | IIBEBO-AP100 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 0 | FS | IIBEBO-AP100 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0 | FS | IIBEBO-AP100 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | IIBEBO-AP100 IIBR-EW130 IIBR-TC330 IIBR120 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | IIBEBO-AP100 IIBR-RW130 IIBR100 |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 0 | FS | IIBEBO-AP100 |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 0 | FS | IIBR-IB10 |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | IIBR-TC270 |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-017 PRE-FA-018 PRE-FA-024 PRE-FA-025 PRE-FA-026 PRE-FA-027 PRE-FA-028 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | GC-GCN150 IIBR-EW120 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST320 |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST100 |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-W150 IIDEBO-ST190 |
IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 IIDEBO-ST200 |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST240 |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 0 | FS | IIDEBO-ST290 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P | 0 | FS | GC-GCN170 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IAI-TC110 IIBEBO-ST30 IIBEBO-ST590 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST680 |
IIIBR-AP140 | PH IIIB - Asphalt - Structural - Ramp T | 0 | FS | IIIBR-RW190 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P | 0 | FS | IIIBR-SP150 |
IIIBR-GC210 | PH IIIB - Demo - Ramp T | 0 | FS | GC-GCN200 IIIBR-TC230 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 0 | FS | IIIBR-AP140 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P | 0 | FS | IIIBR-RW210 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 0 | FS | IIIBR-RW210 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIIBR-ITS1020 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | IIIBR-ITS140 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0 | FS | IIBR-ITS40 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS1010 |
IIIBR-SM520 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | FS | IIIBR-SM510 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 0 | FS | IIIBR-SM520 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBR-SM540 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IIIBR-SM550 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (A) | 0 | FS | IIIBR-SM560 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IIIBR-SM580 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 0 | FS | IIIBR-SM590 |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 0 | FS | IIIBR-GC210 |
IIIBR-TC230 | PH IIIB - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-TC220 |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 0 | FS | GC-GCN170 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0 | FS | GC-GCN170 IIIBR-RW110 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0 | FS | GC-GCN170 IIIBR-RW210 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside Widening Area | 0 | FS | IIIBWBO-RW160 |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP120 IIIBWBO-W130 PRE-FA-015 |
IIIBWBO-EW130 | PH IIIB - Embankment (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-EW120 IIIBWBO-W110 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IIIBWBO-GC120 |
IIIBWBO-RW120 | PH IIIB - Stabilization (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW110 |
IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 |
IIIBWBO-RW150 | PH IIIB - Base (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW140 |
IIIBWBO-RW160 | PH IIIB - Base (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW150 |
IIIBWBO-SP100 | PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528) | 0 | FS | GC-GCN170 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST211 |
IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST211 IIIBWBO-ST250 |
IIIBWBO-ST310 | PH IIIB - End Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST360 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST370 IIIBWBO-ST400 |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-008 PRE-FA-009 PRE-FA-010 PRE-FA-011 PRE-FA-012 PRE-FA-050 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-008 PRE-FA-009 PRE-FA-010 PRE-FA-011 PRE-FA-012 PRE-FA-050 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 0 | FS | GC-GCN170 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 |
IIIC-CP10 | PH IIIC - Construct Ped Signalization at Ramps G&F | 0 | FS | IIICR-AP100 |
IIICR-GC100 | PH IIIC - Demo - Ramp F | 0 | FS | IIICR-TC130 |
IIICR-SP100 | PH IIIC - Drainage (Temp) - Ramp F | 0 | FS | IIICR-GC100 |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 0 | FS | GC-GCN180 |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 0 | FS | GC-GCN180 |
IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | 0 | FS | IVEBM-W220 IVWBM-RW130 IVWBM-RW250 |
IVEBM-SP100 | PH IV - Drainage - EB Median Widening (entire Project) | 0 | SS | IVEBM-GC100 |
IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening | 1 | SS | IVEBM-TC110 |
IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) | 0 | FS | IVEBM-W160 |
IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W190 |
IVEBO-SS100 | PH IV - Install Overhead Signs Structures - EB Outside Widening | 0 | FS | IVEBO-TC100 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0 | FS | IVR-SM670 |
IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 0 | FS | IVEBM-W220 IVWBM-RW130 |
IVWBM-RW110 | PH IV - Grade for road for Station 1 (I4 to International Drive) (B) | 0 | FS | IVEBM-W160 |
IVWBM-RW120 | PH IV - Grade for road for Station 2 (International Drive to Universal) (B) | 0 | FS | IVEBM-W190 |
IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 0 | FS | IVEBM-W220 |
IVWBM-RW200 | PH IV - Grade for road for Station 1 (I4 to International Drive) (A) | 0 | FS | IVEBM-SP100 IVEBM-W160 |
IVWBM-RW230 | PH IV - Grade for road for Station 2 (International Drive to Universal) (A) | 0 | FS | IVEBM-W190 |
IVWBM-RW260 | PH IV - Grade for Station 3 (Universal to JYP) (A) | 0 | FS | IVEBM-W220 |
IVWBM-RW280 | PH IV - Base for Station 3 (Universal to JYP) | 0 | FS | IVWBM-RW270 |
IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area | 0 | FS | IVR-ET50 IVR-ET60 |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 0 | FS | IVWBO-TC100 |
IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area | 0 | FS | IIIAWBO-ST211 IIIBWBO-ST150 IIIBWBO-ST510 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | NA-GC100 PRE-FA-043 PRE-FA-048 PRE-RA-043 |
TF-CO-002 | Install Upright 1 D.S. | 0 | SS | TF-CO-001 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 0 | FS | TF-CO-001 |
TF-CO-004 | Precast Erection | 0 | FS | PRE-FA-034 PRE-FA-035 |
TF-CO-019 | Install Security System | 0 | FS | TF-CO-018 |
The following predecessor relationships were added since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Predecessor Activity ID | Predecessor Activity Description |
---|---|---|---|---|---|
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening |
GC-GC110 | PH MS - Substantial Completion | 10 | FF | IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IVR-SM710 | PH IV - Allow for TEC Install and Test |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | NA-GC100 | TEC Install and Test |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IICR-RW340 | PH IIC - Complete Widening - Ramp H |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IICR-RW360 | PH IIC - Complete Widening - Ramp L |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C |
GC-GCN170 | PH MS - Start Phase III B Construction | 0 | FS | IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
GC-GCN220 | Written Suspend order - FOC related to pending change | 0 | FS | ITS10-1000 | Issue Identification |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 0 | FS | IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 0 | FS | IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 0 | FS | IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0 | FS | IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 0 | FS | IIBR-EW140 | PH IIB - Embankment - Ramp C |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 0 | FS | IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 0 | FS | IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 0 | FS | IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 0 | FS | IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0 | FS | IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0 | FS | IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0 | FS | IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0 | FS | IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0 | FS | IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 0 | FS | IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 0 | FS | IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 0 | FS | IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 0 | FS | IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 0 | FS | IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 0 | FS | IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 0 | FS | IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 0 | FS | IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 0 | FS | GC-GCN140 | PH MS - Start Phase II B Construction |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 0 | FS | IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 0 | FS | IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 0 | FS | PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0 | FS | IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 0 | FS | USDED-CO-001 | Duke Energy Distribution (A) |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 0 | FS | GC-GCN110 | PH MS - Start Phase IA Construction |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 0 | FF | IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 0 | FS | IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 0 | FS | GC-GCN140 | PH MS - Start Phase II B Construction |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 0 | FS | IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 0 | FS | IIBR-SP240 | PH IIB - Drainage - Ramp R-1 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 0 | FS | IIBR-SP250 | PH IIB - Drainage - Ramp R-2 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0 | FS | IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0 | FS | IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 0 | FS | IIBR-EW130 | PH IIB - Embankment - Ramp R-1 |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 0 | FS | IIBR-EW170 | PH IIB - Embankment - Ramp R-2 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 0 | FS | IICR-GC100 | PH IIC - Demo - Ramp S-2 |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 0 | FS | IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0 | FS | IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0 | FS | IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 0 | FS | IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 0 | FS | IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 0 | FS | IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 0 | FS | IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0 | FS | IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0 | FS | IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 0 | FS | IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 0 | FS | IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | GC-GCN140 | PH MS - Start Phase II B Construction |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 1 | FF | IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 0 | FF | IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 0 | FS | IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 0 | FS | IIIBR-GC250 | PH IIIB - Demo - Ramp P |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 0 | FS | IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 | 0 | FS | IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 0 | SS | IVEBO-SS100 | PH IV - Install OT Structures - East of JYP |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | GC-GCN220 | Written Suspend order - FOC related to pending change |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 0 | FS | IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 0 | FS | IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 0 | FS | IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 0 | FS | IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 0 | FS | IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 0 | FS | IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | 0 | FS | GC-GCN220 | Written Suspend order - FOC related to pending change |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | 0 | FS | IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware |
IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) | 0 | FS | IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) |
IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) | 0 | FS | IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) |
IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) | 0 | FS | IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 0 | FS | IIIBR-SP150 | PH IIIB - Drainage - Ramp P |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 0 | FS | IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 0 | FS | IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0 | FS | IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | SS | IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 0 | SS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 0 | FS | IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 0 | FS | IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 0 | FS | IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0 | FS | GC-GCN140 | PH MS - Start Phase II B Construction |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 0 | FS | IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0 | FS | IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0 | FS | IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 4 | FF | IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 0 | FS | IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 0 | FS | GC-GCN170 | PH MS - Start Phase III B Construction |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 0 | FS | IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0 | FS | GC-GCN170 | PH MS - Start Phase III B Construction |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0 | FS | IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FS | GC-GCN170 | PH MS - Start Phase III B Construction |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FS | IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FF | IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 1 | FF | IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 3 | FF | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 0 | FF | IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0 | FS | IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0 | FS | IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 0 | FS | IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 0 | FS | IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 0 | FS | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 0 | FS | IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 0 | FS | IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IICR-RW330 | PH IIC - Complete Widening - Ramp E |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 0 | FS | IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 0 | FS | IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 0 | FS | IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IICR-RW330 | PH IIC - Complete Widening - Ramp E |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FF | IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 5 | SS | IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 0 | FS | IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 2 | SS | IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 0 | FS | IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 0 | FS | IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | 0 | FS | IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 0 | FS | GC-GCN120 | PH MS - Start Phase IB Construction |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 0 | FS | IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 0 | FS | IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 0 | FS | IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 0 | FS | IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0 | FS | IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 0 | FS | IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 0 | FS | IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 0 | FS | IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V |
ITS10-1000 | Issue Identification | 0 | FS | GC-DP100 | PH MS - NTP |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 0 | FS | ITS10-1000 | Issue Identification |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 | FS | GC-GCN220 | Written Suspend order - FOC related to pending change |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 | FS | ITS10-1010 | NOI submitted - Potential Delay to Project Schedule |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0 | FS | ITS10-1020 | Plan Revision 10 Officially transmitted |
ITS10-1040 | Fabrication and Delivery - Conduits | 0 | FS | ITS10-1030 | Plan Revision 10 - Review and Procurement |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1020 | Plan Revision 10 Officially transmitted |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | 0 | FS | ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings |
ITS10-1080 | Furnish & Install ITS Standby Generators | 0 | FS | ITS10-1070 | Fabrication & Delivery - ITS Standby Generators |
ITS10-1090 | Furnish & Install - Conduit | 0 | FS | ITS10-1040 | Fabrication and Delivery - Conduits |
ITS10-1100 | ITS Generator Stand AloneTesting | 0 | FS | ITS10-1080 | Furnish & Install ITS Standby Generators |
ITS10-1110 | Fabrication and Delivery - Conductors | 0 | FS | ITS10-1030 | Plan Revision 10 - Review and Procurement |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 0 | FS | ITS10-1090 | Furnish & Install - Conduit |
ITS10-1130 | Furnish & Install - Conductors | 0 | FS | ITS10-1110 | Fabrication and Delivery - Conductors |
ITS10-1130 | Furnish & Install - Conductors | 0 | FS | ITS10-1120 | Modify existing cabinets to incorporate additional conduit |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | 0 | FS | ITS10-1030 | Plan Revision 10 - Review and Procurement |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 0 | FS | ITS10-1130 | Furnish & Install - Conductors |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 0 | FS | ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers |
ITS10-1160 | Furnish & Install - FOC Drops | 0 | FS | ITS10-1090 | Furnish & Install - Conduit |
ITS10-1170 | Splice / Terminate FOC Drops | 0 | FS | ITS10-1160 | Furnish & Install - FOC Drops |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 0 | FS | IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 0 | FS | IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 0 | FS | IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 0 | FS | IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express |
IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | 0 | FS | IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider |
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | 10 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 0 | FS | IVWBM-GC100 | PH IV - Demo Temporary - WB Express |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 0 | FS | IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 0 | FS | IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0 | FS | IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0 | FS | IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0 | FS | IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 0 | FS | IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 0 | FS | IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 0 | FS | IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 3 | SS | IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 3 | SS | IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 5 | SS | IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0 | FS | IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 0 | FS | IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 0 | FS | IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 0 | FS | IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR-GC100 | PH IIIC - Demo - Old Ramp F |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR180 | PH IIIC - Remove Diversion - Ramp T |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 3 | FF | IIBEBM-GC110 | PH IV - Rumble Strips - EB Median |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVR-ET50 | PH IV - Erect Trusses (9-17) |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVR-ET60 | PH IV - Erect Trusses (18-24) |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 0 | FS | IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIICR180 | PH IIIC - Remove Diversion - Ramp T |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | IVEBO-SS100 | PH IV - Install OT Structures - East of JYP |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 0 | FS | IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 0 | FS | PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0 | FS | PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 0 | FS | PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 0 | FS | PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting |
IVR-SM710 | PH IV - Allow for TEC Install and Test | 0 | FS | IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express |
IVR-SM710 | PH IV - Allow for TEC Install and Test | 0 | FS | IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 0 | FS | IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | 0 | FS | IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | 0 | FS | IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express |
IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider | 0 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening | 10 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 3 | SS | IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 0 | FS | IVWBM-GC100 | PH IV - Demo Temporary - WB Express |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | 2 | SS | IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 0 | FS | IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 0 | FS | IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 0 | FS | IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 |
IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | 0 | FS | IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | 0 | FS | IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | 0 | FS | IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express |
IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | 0 | FS | IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | 0 | FS | IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | 0 | FS | IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express |
IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express |
IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express |
IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | 0 | FS | IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | 0 | FS | IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | 0 | FS | IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express |
IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FF | IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N |
NA-GC100 | TEC Install and Test | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express |
NA-GC100 | TEC Install and Test | 0 | FS | IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | ITS10-1100 | ITS Generator Stand AloneTesting |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | ITS10-1170 | Splice / Terminate FOC Drops |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 0 | FS | IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility |
TF-CO-017 | F+1 Fuel Tank | 0 | FS | PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping |
The following predecessor relationships were deleted since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Predecessor Activity ID | Predecessor Activity Description |
---|---|---|---|---|---|
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area |
GC-GC110 | PH MS - Substantial Completion | 0 | FS | IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | USDED-CO-001 | Duke Energy Distribution (A) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIBEBM-GC110 | PH IIB - Rumble Strip (Widening) - EB Median Widening |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N |
GC-GCN160 | PH MS - Start Phase IV Construction | 0 | FS | IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R-2 |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IIBR-GC191 | PH IIB - Performance Turf, SOD - Ramp A |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 |
GC-GCN190 | PH MS - Start Phase IID Construction | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening |
GC-GCN210 | PH MS - Punch List/Acceptance | 0 | FS | IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening | 0 | FS | IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 0 | FS | IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 0 | FS | IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B | 0 | FS | IBR-AP110 | PH IB - Asphalt - Structural - Ramp B |
IIAR-TC120 | PH IIA - Construction 12' Widening on I-4 (NEBound) - Ramp I4- Interstate | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIBEBM-GC110 | PH IIB - Rumble Strip (Widening) - EB Median Widening | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening | 0 | FS | IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening | 0 | FS | IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 0 | FF | IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening | 0 | FS | IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 0 | FS | IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR | 0 | FS | IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IBEBM-ST120 | PH IB - Construct Crane Access - EB Median Widening (Bridge over John Young PKWY) |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IBWBM-ST230 | PH IB - Construct Crane Access - WB Median Widening (Bridge over John Young PKWY) |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) |
IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IIBR-EW120 | PH IIB - Embankment - Ramp S-1 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST7 | PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Internatio |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.3) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.2) - EB Outside Widening (SR528) |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.3) - EB Outside Widening (SR528) |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) | 0 | FS | GC-GCN150 | PH MS - Start Phase IIC Construction |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 0 | FS | IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 0 | FS | IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 0 | FS | PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 0 | FS | IIAR-TC120 | PH IIA - Construction 12' Widening on I-4 (NEBound) - Ramp I4- Interstate |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 0 | FS | IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 0 | FS | IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | IIBR-EW130 | PH IIB - Embankment - Ramp R-1 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 0 | FS | IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | IIBR-RW130 | PH IIB - Base - Ramp E |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 0 | FS | IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 0 | FS | IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 0 | FS | IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-024 | Fabricate and Deliver 633 Communication Cable |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | GC-GCN150 | PH MS - Start Phase IIC Construction |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 0 | FS | IIBR-EW120 | PH IIB - Embankment - Ramp S-1 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-W150 | PH IIB - MSE Wall RW5(Continue Panels\set coping) - EB Outside Widening (SR528) |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 | PH IID - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 | PH IID - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST240 | PH IID - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST300 | PH IID - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 0 | FS | IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IAI-TC110 | PH IA - Set Temp Traffic Barriers - Interchanges Roads Universal Avn |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBR-AP140 | PH IIIB - Asphalt - Structural - Ramp T | 0 | FS | IIIBR-RW190 | PH IIIB - Base - Ramp T |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P | 0 | FS | IIIBR-SP150 | PH IIIB - Drainage (Temp) - Ramp P |
IIIBR-GC210 | PH IIIB - Demo - Ramp T | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
IIIBR-GC210 | PH IIIB - Demo - Ramp T | 0 | FS | IIIBR-TC230 | PH IIIB - Temp Striping New Ramp Alignment - Ramp T |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 0 | FS | IIIBR-AP140 | PH IIIB - Asphalt - Structural - Ramp T |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P | 0 | FS | IIIBR-RW210 | PH IIIB - Base - Ramp P |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 0 | FS | IIIBR-RW210 | PH IIIB - Base - Ramp P |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0 | FS | IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) |
IIIBR-SM520 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | FS | IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 0 | FS | IIIBR-SM520 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (9) |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (A) | 0 | FS | IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) |
IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) | 0 | FS | IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (A) |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 0 | FS | IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 0 | FS | IIIBR-GC210 | PH IIIB - Demo - Ramp T |
IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBR-TC230 | PH IIIB - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 0 | FS | IIIBR-RW110 | PH IIIB - Base - Ramp G |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 0 | FS | IIIBR-RW210 | PH IIIB - Base - Ramp P |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside Widening Area | 0 | FS | IIIBWBO-RW160 | PH IIIB - Base (International - I4) - WB Outside Widening Area |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-W130 | PH IIIB - Concrete FACED SHEET Pile Wall 3 - WB Outside Widening Area (SR528) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems |
IIIBWBO-EW130 | PH IIIB - Embankment (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area |
IIIBWBO-EW130 | PH IIIB - Embankment (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 - WB Outside Widening Area (SR528) |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening Area |
IIIBWBO-RW120 | PH IIIB - Stabilization (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW110 | PH IIIB - Stabilization (Universal - International) - WB Outside Widening Area |
IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 | PH IIIB - Stabilization (International - I4) - WB Outside Widening Area |
IIIBWBO-RW150 | PH IIIB - Base (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area |
IIIBWBO-RW160 | PH IIIB - Base (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW150 | PH IIIB - Base (Universal - International) - WB Outside Widening Area |
IIIBWBO-SP100 | PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528) | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST211 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST211 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST310 | PH IIIB - End Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-W130 | PH IIIB - Concrete FACED SHEET Pile Wall 3 - WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall 2 - WB Outside Widening Area (SR528) |
IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 0 | FS | IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G |
IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 0 | FS | IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F |
IIIC-CP10 | PH IIIC - Construct Ped Signalization at Ramps G&F | 0 | FS | IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F |
IIICR-GC100 | PH IIIC - Demo - Ramp F | 0 | FS | IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F |
IIICR-SP100 | PH IIIC - Drainage (Temp) - Ramp F | 0 | FS | IIICR-GC100 | PH IIIC - Demo - Ramp F |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) |
IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | 0 | FS | IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) |
IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | 0 | FS | IVWBM-RW250 | PH IV - Base for road for Station 2 (International Drive to Universal) (A) |
IVEBM-SP100 | PH IV - Drainage - EB Median Widening (entire Project) | 0 | SS | IVEBM-GC100 | PH IV - Demo Temporary - EB Median Widening |
IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening | 0 | FF | IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening |
IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening | 1 | SS | IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening |
IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) | 0 | FS | IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) |
IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) |
IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) |
IVEBO-SS100 | PH IV - Install Overhead Signs Structures - EB Outside Widening | 0 | FS | IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0 | FS | IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) |
IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) |
IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 0 | FS | IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) |
IVWBM-RW110 | PH IV - Grade for road for Station 1 (I4 to International Drive) (B) | 0 | FS | IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) |
IVWBM-RW120 | PH IV - Grade for road for Station 2 (International Drive to Universal) (B) | 0 | FS | IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) |
IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) |
IVWBM-RW150 | PH IV - Base for Station 3 (Universal to JYP) (B) | 0 | FS | IVWBM-RW140 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) |
IVWBM-RW200 | PH IV - Grade for road for Station 1 (I4 to International Drive) (A) | 0 | FS | IVEBM-SP100 | PH IV - Drainage - EB Median Widening (entire Project) |
IVWBM-RW200 | PH IV - Grade for road for Station 1 (I4 to International Drive) (A) | 0 | FS | IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) |
IVWBM-RW230 | PH IV - Grade for road for Station 2 (International Drive to Universal) (A) | 0 | FS | IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) |
IVWBM-RW260 | PH IV - Grade for Station 3 (Universal to JYP) (A) | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) |
IVWBM-RW280 | PH IV - Base for Station 3 (Universal to JYP) | 0 | FS | IVWBM-RW270 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | 0 | SS | IVWBM-TC110 | PH IV - Temp Striping for Phase - WB Median Widening |
IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area | 0 | FS | IVR-ET50 | PH IV - Erect Trusses (9-17) |
IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area | 0 | FS | IVR-ET60 | PH IV - Erect Trusses (18-24) |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 0 | FS | IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area |
IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area | 0 | FS | IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) |
IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area | 0 | FS | IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | NA-GC100 | TEC Install and Test |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | PRE-RA-043 | Review and Approve 782 ITS CCTV Camera |
PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera | 0 | FS | PRE-RA-043 | Review and Approve 782 ITS CCTV Camera |
PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure | 0 | FS | PRE-RA-048 | Review and Approve 785 ITS Infrastructure |
PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera | 0 | FS | GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) |
PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure | 0 | FS | GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) |
PRE-RA-043 | Review and Approve 782 ITS CCTV Camera | 0 | FS | PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera |
PRE-RA-048 | Review and Approve 785 ITS Infrastructure | 0 | FS | PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure |
TF-CO-002 | Install Upright 1 D.S. | 0 | FS | TF-CO-001 | Foundation (FRP SOG) |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 0 | FS | TF-CO-001 | Foundation (FRP SOG) |
TF-CO-004 | Precast Erection | 0 | FS | PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping |
TF-CO-004 | Precast Erection | 0 | FS | PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping |
TF-CO-019 | Install Security System | 0 | FS | TF-CO-018 | Install Lighting |
TF-CO-020 | Install Lightning Protection | 0 | FF | PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing |
The following successor relationships were added since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Successor Activity ID | Successor Activity Description |
---|---|---|---|---|---|
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 10 | FF | GC-GC110 | PH MS - Substantial Completion |
IVR-SM710 | PH IV - Allow for TEC Install and Test | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
NA-GC100 | TEC Install and Test | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 0 | FS | GC-GCN140 | PH MS - Start Phase II B Construction |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 0 | FS | GC-GCN170 | PH MS - Start Phase III B Construction |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
ITS10-1000 | Issue Identification | 0 | FS | GC-GCN220 | Written Suspend order - FOC related to pending change |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 0 | FS | IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) |
IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | 0 | FS | IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) |
IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | 0 | FS | IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening |
IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening | 0 | FS | IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 0 | FS | IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 0 | FS | IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 0 | FS | IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 0 | FS | IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 0 | FS | IIBEBM-GC110 | PH IV - Rumble Strips - EB Median |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 0 | FS | IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 0 | FS | IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 0 | FS | IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 0 | FS | IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 0 | FS | IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 0 | FS | IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0 | FS | IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 0 | FS | IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 0 | FS | IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 0 | FS | IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 0 | FS | IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 0 | FS | IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 0 | FS | IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 0 | FS | IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 0 | FS | IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 0 | FS | IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 0 | FS | IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 0 | FS | IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 0 | FS | IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 0 | FS | IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C |
USDED-CO-001 | Duke Energy Distribution (A) | 0 | FS | IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I |
GC-GCN110 | PH MS - Start Phase IA Construction | 0 | FS | IIBR-GC150 | PH IIB - Demo - Ramp S-1 |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 0 | FF | IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 0 | FS | IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 0 | FS | IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 0 | FS | IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 0 | FS | IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 0 | FS | IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 0 | FS | IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 0 | FS | IIBR-SP240 | PH IIB - Drainage - Ramp R-1 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 0 | FS | IIBR-SP250 | PH IIB - Drainage - Ramp R-2 |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H |
IICR-GC100 | PH IIC - Demo - Ramp S-2 | 0 | FS | IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 0 | FS | IICR-RW110 | PH IIC - Base - Ramp S-2 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 0 | FS | IICR-RW330 | PH IIC - Complete Widening - Ramp E |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 0 | FS | IICR-RW330 | PH IIC - Complete Widening - Ramp E |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 0 | FS | IICR-RW340 | PH IIC - Complete Widening - Ramp H |
IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H | 0 | FS | IICR-RW340 | PH IIC - Complete Widening - Ramp H |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 0 | FS | IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 |
IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L | 0 | FS | IICR-RW360 | PH IIC - Complete Widening - Ramp L |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 0 | FS | IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0 | FS | IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 0 | FS | IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 |
IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 1 | FF | IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 0 | FS | IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FF | IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0 | FS | IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 0 | FS | IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 0 | FS | IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 0 | FS | IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T |
IIIBR-GC250 | PH IIIB - Demo - Ramp P | 0 | FS | IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 0 | FS | IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0 | FS | IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 0 | FS | IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 0 | SS | IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) |
GC-GCN220 | Written Suspend order - FOC related to pending change | 0 | FS | IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 0 | FS | IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 0 | FS | IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 0 | FS | IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 0 | FS | IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC |
IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) | 0 | FS | IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 0 | FS | IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) |
GC-GCN220 | Written Suspend order - FOC related to pending change | 0 | FS | IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 0 | FS | IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | 0 | FS | IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) |
IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) | 0 | FS | IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) |
IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) | 0 | FS | IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) |
IIIBR-SP150 | PH IIIB - Drainage - Ramp P | 0 | FS | IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 0 | FS | IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 0 | FS | IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 0 | FS | IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 0 | SS | IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 0 | FS | IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | SS | IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 0 | FS | IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 0 | FS | IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 0 | FS | IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 0 | FS | IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P |
IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J |
GC-GCN140 | PH MS - Start Phase II B Construction | 0 | FS | IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 0 | FS | IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 0 | FS | IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 0 | FS | IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 0 | FS | IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 4 | FF | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | 0 | FS | IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area |
GC-GCN170 | PH MS - Start Phase III B Construction | 0 | FS | IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0 | FS | IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge |
GC-GCN170 | PH MS - Start Phase III B Construction | 0 | FS | IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 0 | FS | IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 0 | FS | IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area |
GC-GCN170 | PH MS - Start Phase III B Construction | 0 | FS | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 0 | FS | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 0 | FS | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) | 0 | FF | IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 1 | FF | IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 3 | FF | IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 0 | FF | IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 0 | FS | IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 0 | FS | IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 0 | FS | IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 0 | FS | IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 0 | FS | IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 0 | FS | IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 0 | FS | IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 0 | FS | IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0 | FS | IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 0 | FS | IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 0 | FS | IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 0 | FS | IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 0 | FS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 0 | FF | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 5 | SS | IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 0 | FS | IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 0 | FS | IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 2 | SS | IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 0 | FS | IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 0 | FS | IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IIICR-GC100 | PH IIIC - Demo - Old Ramp F |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 0 | FS | IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F |
GC-GCN120 | PH MS - Start Phase IB Construction | 0 | FS | IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 0 | FS | IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | 0 | FS | IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 0 | FS | IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G |
IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J | 0 | FS | IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 0 | FS | IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 0 | FS | IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 0 | FS | IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 0 | FS | IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIICR180 | PH IIIC - Remove Diversion - Ramp T |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IIICR180 | PH IIIC - Remove Diversion - Ramp T |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 0 | FS | IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 0 | FS | IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q |
IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q | 0 | FS | IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q |
IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V | 0 | FS | IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V |
GC-DP100 | PH MS - NTP | 0 | FS | ITS10-1000 | Issue Identification |
ITS10-1000 | Issue Identification | 0 | FS | ITS10-1010 | NOI submitted - Potential Delay to Project Schedule |
GC-GCN220 | Written Suspend order - FOC related to pending change | 0 | FS | ITS10-1020 | Plan Revision 10 Officially transmitted |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 0 | FS | ITS10-1020 | Plan Revision 10 Officially transmitted |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 | FS | ITS10-1030 | Plan Revision 10 - Review and Procurement |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0 | FS | ITS10-1040 | Fabrication and Delivery - Conduits |
ITS10-1020 | Plan Revision 10 Officially transmitted | 0 | FS | ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 0 | FS | ITS10-1070 | Fabrication & Delivery - ITS Standby Generators |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | 0 | FS | ITS10-1080 | Furnish & Install ITS Standby Generators |
ITS10-1040 | Fabrication and Delivery - Conduits | 0 | FS | ITS10-1090 | Furnish & Install - Conduit |
ITS10-1080 | Furnish & Install ITS Standby Generators | 0 | FS | ITS10-1100 | ITS Generator Stand AloneTesting |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0 | FS | ITS10-1110 | Fabrication and Delivery - Conductors |
ITS10-1090 | Furnish & Install - Conduit | 0 | FS | ITS10-1120 | Modify existing cabinets to incorporate additional conduit |
ITS10-1110 | Fabrication and Delivery - Conductors | 0 | FS | ITS10-1130 | Furnish & Install - Conductors |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 0 | FS | ITS10-1130 | Furnish & Install - Conductors |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 0 | FS | ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers |
ITS10-1130 | Furnish & Install - Conductors | 0 | FS | ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | 0 | FS | ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers |
ITS10-1090 | Furnish & Install - Conduit | 0 | FS | ITS10-1160 | Furnish & Install - FOC Drops |
ITS10-1160 | Furnish & Install - FOC Drops | 0 | FS | ITS10-1170 | Splice / Terminate FOC Drops |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | 0 | FS | IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | 0 | FS | IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 0 | FS | IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider |
IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider | 0 | FS | IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | 10 | FS | IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 0 | FS | IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 0 | FS | IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 0 | FS | IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 0 | FS | IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 0 | FS | IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 0 | FS | IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 0 | FS | IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 |
IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express | 0 | FS | IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 0 | FS | IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 0 | FS | IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | 3 | SS | IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 3 | SS | IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 5 | SS | IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | 0 | FS | IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0 | FS | IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 0 | FS | IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | 0 | FS | IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 0 | FS | IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 0 | FS | IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 0 | FS | IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIIBR-GC390 | PH IIIB - Guardrail - Median Widening STA 2030+00 to STA 217+00 | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 0 | FS | IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 3 | FF | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 0 | FS | IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 0 | FS | IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 0 | FS | IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 0 | FS | IVR-ET60 | PH IV - Erect Trusses (18-24) |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 0 | FS | IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 0 | FS | IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 0 | FS | IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 0 | FS | IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 0 | FS | IVR-SM710 | PH IV - Allow for TEC Install and Test |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 0 | FS | IVR-SM710 | PH IV - Allow for TEC Install and Test |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 0 | FS | IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express |
IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express | 0 | FS | IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | 0 | FS | IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 0 | FS | IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | 10 | FS | IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 3 | SS | IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 0 | FS | IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | 2 | SS | IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 0 | FS | IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | 0 | FS | IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 0 | FS | IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 0 | FS | IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 0 | FS | IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 0 | FS | IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 0 | FS | IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express |
IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express | 0 | FS | IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 0 | FS | IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | 0 | FS | IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 0 | FS | IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express |
IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express | 0 | FS | IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 0 | FS | IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | 0 | FS | IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express |
IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express |
IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express | 0 | FS | IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express |
IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express | 0 | FS | IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 0 | FS | IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | 0 | FS | IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 0 | FS | IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 0 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 0 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | 0 | FS | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | 0 | FF | IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 0 | FS | IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 0 | FS | NA-GC100 | TEC Install and Test |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 0 | FS | NA-GC100 | TEC Install and Test |
ITS10-1100 | ITS Generator Stand AloneTesting | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
ITS10-1170 | Splice / Terminate FOC Drops | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 0 | FS | TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 0 | FS | TF-CO-017 | F+1 Fuel Tank |
The following successor relationships were deleted since E8P02 Update No. 11.
Activity ID | Activity Description | Lag | Relationship Type | Predecessor Activity ID | Predecessor Activity Description |
---|---|---|---|---|---|
IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 0 | FS | GC-GC110 | PH MS - Substantial Completion |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
USDED-CO-001 | Duke Energy Distribution (A) | 0 | FS | GC-GCN140 | PH MS - Start Phase IIB Construction |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIBEBM-GC110 | PH IIB - Rumble Strip (Widening) - EB Median Widening | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | GC-GCN160 | PH MS - Start Phase IV Construction |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R-2 | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 0 | FS | GC-GCN170 | PH MS - Start Phase IIIB Construction |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 0 | FS | GC-GCN180 | PH MS - Start Phase IIIC Construction |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IIBR-GC191 | PH IIB - Performance Turf, SOD - Ramp A | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 0 | FS | GC-GCN190 | PH MS - Start Phase IID Construction |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 0 | FS | GC-GCN200 | PH MS - Start Phase IIIA Construction |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 0 | FS | GC-GCN210 | PH MS - Punch List/Acceptance |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 0 | FS | IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 0 | FS | IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening | 0 | FS | IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening | 0 | FS | IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 0 | FS | IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B | 0 | FS | IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IIAR-TC120 | PH IIA - Construction 12' Widening on I-4 (NEBound) - Ramp I4- Interstate |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening | 0 | FS | IIBEBM-GC110 | PH IIB - Rumble Strip (Widening) - EB Median Widening |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 0 | FS | IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FF | IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 0 | FS | IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 0 | FS | IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 0 | FS | IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 0 | FS | IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR | 0 | FS | IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IBEBM-ST120 | PH IB - Construct Crane Access - EB Median Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IBWBM-ST230 | PH IB - Construct Crane Access - WB Median Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 0 | FS | IIBEBO-ST19 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge 750629 Ramp S over JYP) |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST7 | PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Internatio | 0 | FS | IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 0 | FS | IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 0 | FS | IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 0 | FS | IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 0 | FS | IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 0 | FS | IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.2) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.3) - EB Outside Widening (SR528) |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (International Dr.3) - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) |
GC-GCN150 | PH MS - Start Phase IIC Construction | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 0 | FS | IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads\Begin Panels) - EB Outside Widening (SR528) |
GC-GCN140 | PH MS - Start Phase IIB Construction | 0 | FS | IIBR-GC150 | PH IIB - Demo - Ramp S-1 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 0 | FS | IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 0 | FS | IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R |
PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera | 0 | FS | IIBR-ITS70 | PH IIB - Install CCTV's (1-8) |
IIAR-TC120 | PH IIA - Construction 12' Widening on I-4 (NEBound) - Ramp I4- Interstate | 0 | FS | IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate |
IIAR-TC130 | PH IIA - Construction 12' Widening on I-4 (SWBound) - Ramp I4- Interstate | 0 | FS | IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 0 | FS | IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 0 | FS | IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 |
IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | 0 | FS | IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 0 | FS | IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H |
IIBR-RW130 | PH IIB - Base - Ramp E | 0 | FS | IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 0 | FS | IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 0 | FS | IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 0 | FS | IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 0 | FS | IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector | 0 | FS | IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 |
GC-GCN150 | PH MS - Start Phase IIC Construction | 0 | FS | IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 0 | FS | IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) |
IIBEBO-W150 | PH IIB - MSE Wall RW5(Continue Panels\set coping) - EB Outside Widening (SR528) | 0 | FS | IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST190 | PH IID - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST190 | PH IID - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH IID - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST240 | PH IID - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST300 | PH IID - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 0 | FS | IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P |
IAI-TC110 | PH IA - Set Temp Traffic Barriers - Interchanges Roads Universal Avn | 0 | FS | IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 0 | FS | IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 0 | FS | IIIBR-AP140 | PH IIIB - Asphalt - Structural - Ramp T |
IIIBR-SP150 | PH IIIB - Drainage (Temp) - Ramp P | 0 | FS | IIIBR-EW150 | PH IIIB - Embankment - Ramp P |
GC-GCN200 | PH MS - Start Phase IIIA Construction | 0 | FS | IIIBR-GC210 | PH IIIB - Demo - Ramp T |
IIIBR-TC230 | PH IIIB - Temp Striping New Ramp Alignment - Ramp T | 0 | FS | IIIBR-GC210 | PH IIIB - Demo - Ramp T |
IIIBR-AP140 | PH IIIB - Asphalt - Structural - Ramp T | 0 | FS | IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T |
IIIBR-RW210 | PH IIIB - Base - Ramp P | 0 | FS | IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P |
IIIBR-RW210 | PH IIIB - Base - Ramp P | 0 | FS | IIIBR-GC340 | PH IIIB - Demo - Ramp Q |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 0 | FS | IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 0 | FS | IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 0 | FS | IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 0 | FS | IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 0 | FS | IIIBR-SM520 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (9) |
IIIBR-SM520 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (9) | 0 | FS | IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 0 | FS | IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 0 | FS | IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 0 | FS | IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (A) |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (A) | 0 | FS | IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) |
IIIBR-SM580 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) (B) | 0 | FS | IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 0 | FS | IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) |
IIIBR-GC210 | PH IIIB - Demo - Ramp T | 0 | FS | IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT |
IIIBR-TC220 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - RampT | 0 | FS | IIIBR-TC230 | PH IIIB - Temp Striping New Ramp Alignment - Ramp T |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 0 | FS | IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q |
IIIBR-RW210 | PH IIIB - Base - Ramp P | 0 | FS | IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q |
IIIBWBO-RW160 | PH IIIB - Base (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside Widening Area |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBWBO-W130 | PH IIIB - Concrete FACED SHEET Pile Wall 3 - WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 0 | FS | IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-EW130 | PH IIIB - Embankment (International - I4) - WB Outside Widening Area |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 - WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-EW130 | PH IIIB - Embankment (International - I4) - WB Outside Widening Area |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening Area | 0 | FS | IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area |
IIIBWBO-RW110 | PH IIIB - Stabilization (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW120 | PH IIIB - Stabilization (International - I4) - WB Outside Widening Area |
IIIBWBO-RW120 | PH IIIB - Stabilization (International - I4) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area |
IIIBWBO-RW140 | PH IIIB - Base (JYP - Universal) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW150 | PH IIIB - Base (Universal - International) - WB Outside Widening Area |
IIIBWBO-RW150 | PH IIIB - Base (Universal - International) - WB Outside Widening Area | 0 | FS | IIIBWBO-RW160 | PH IIIB - Base (International - I4) - WB Outside Widening Area |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBWBO-SP100 | PH IIIB - Drainage (JYP-Universal) - WB Outside Widening Area (SR528) |
IIIBWBO-ST211 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST211 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-ST310 | PH IIIB - End Bent 5 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 0 | FS | IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) | 0 | FS | IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) | 0 | FS | IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) |
GC-GCN170 | PH MS - Start Phase IIIB Construction | 0 | FS | IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area |
IIIBWBO-ST280 | PH IIIB - Wall Bent 5 - WB Outside Widening Area (Bridge over International DR) | 0 | FS | IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall 2 - WB Outside Widening Area (SR528) | 0 | FS | IIIBWBO-W130 | PH IIIB - Concrete FACED SHEET Pile Wall 3 - WB Outside Widening Area (SR528) |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 0 | FS | IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 0 | FS | IIIC-AP170 | PH IIIC - Construct Ped. Signalization at Ramps G&F |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 0 | FS | IIIC-CP10 | PH IIIC - Construct Ped Signalization at Ramps G&F |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 0 | FS | IIICR-GC100 | PH IIIC - Demo - Ramp F |
IIICR-GC100 | PH IIIC - Demo - Ramp F | 0 | FS | IIICR-SP100 | PH IIIC - Drainage (Temp) - Ramp F |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F |
GC-GCN180 | PH MS - Start Phase IIIC Construction | 0 | FS | IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening |
IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening |
IVWBM-RW250 | PH IV - Base for road for Station 2 (International Drive to Universal) (A) | 0 | FS | IVEBM-AP100 | PH IV - Asphalt - Structural - EB Median Widening |
IVEBM-GC100 | PH IV - Demo Temporary - EB Median Widening | 0 | SS | IVEBM-SP100 | PH IV - Drainage - EB Median Widening (entire Project) |
IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening | 0 | FF | IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening |
IVEBM-TC110 | PH IV - Temp Striping for Phase - EB Median Widening | 1 | SS | IVEBM-TC120 | PH IV - MOT Shift for Phase - EB Median Widening |
IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | 0 | FS | IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) |
IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | 0 | FS | IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) |
IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) |
IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) | 0 | FS | IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 0 | FS | IVEBO-SS100 | PH IV - Install Overhead Signs Structures - EB Outside Widening |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 0 | FS | IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 0 | FS | IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening |
IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 0 | FS | IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening |
IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | 0 | FS | IVWBM-RW110 | PH IV - Grade for road for Station 1 (I4 to International Drive) (B) |
IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | 0 | FS | IVWBM-RW120 | PH IV - Grade for road for Station 2 (International Drive to Universal) (B) |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 0 | FS | IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) |
IVWBM-RW140 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | 0 | FS | IVWBM-RW150 | PH IV - Base for Station 3 (Universal to JYP) (B) |
IVEBM-SP100 | PH IV - Drainage - EB Median Widening (entire Project) | 0 | FS | IVWBM-RW200 | PH IV - Grade for road for Station 1 (I4 to International Drive) (A) |
IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | 0 | FS | IVWBM-RW200 | PH IV - Grade for road for Station 1 (I4 to International Drive) (A) |
IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | 0 | FS | IVWBM-RW230 | PH IV - Grade for road for Station 2 (International Drive to Universal) (A) |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 0 | FS | IVWBM-RW260 | PH IV - Grade for Station 3 (Universal to JYP) (A) |
IVWBM-RW270 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | 0 | FS | IVWBM-RW280 | PH IV - Base for Station 3 (Universal to JYP) |
IVWBM-TC110 | PH IV - Temp Striping for Phase - WB Median Widening | 0 | SS | IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 0 | FS | IVWBO-AP100 | PH IV - Asphalt - Overbuild & Friction - WB Outside Widening Area |
IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area | 0 | FS | IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 0 | FS | IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 0 | FS | IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 0 | FS | IVWBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - WB Outside Widening Area |
NA-GC100 | TEC Install and Test | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
PRE-RA-043 | Review and Approve 782 ITS CCTV Camera | 0 | FS | NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas |
PRE-RA-043 | Review and Approve 782 ITS CCTV Camera | 0 | FS | PRE-FA-043 | Fabricate and Deliver 782 ITS CCTV Camera |
PRE-RA-048 | Review and Approve 785 ITS Infrastructure | 0 | FS | PRE-FA-048 | Fabricate and Deliver 785 ITS Infrastructure |
GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) | 0 | FS | PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera |
GC-GC100 | PH MS - NTP2 - Start Construction (35 days from NTP 1= Contract date ) | 0 | FS | PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure |
PRE-PS-043 | Prepare and Submit 782 ITS CCTV Camera | 0 | FS | PRE-RA-043 | Review and Approve 782 ITS CCTV Camera |
PRE-PS-048 | Prepare and Submit 785 ITS Infrastructure | 0 | FS | PRE-RA-048 | Review and Approve 785 ITS Infrastructure |
TF-CO-001 | Foundation (FRP SOG) | 0 | FS | TF-CO-002 | Install Upright 1 D.S. |
TF-CO-001 | Foundation (FRP SOG) | 0 | FS | TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 0 | FS | TF-CO-004 | Precast Erection |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 0 | FS | TF-CO-004 | Precast Erection |
TF-CO-018 | Install Lighting | 0 | FS | TF-CO-019 | Install Security System |
PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | 0 | FF | TF-CO-020 | Install Lightning Protection |
The following activity descriptions were changed since E8P02 Update No. 11
Activity ID | Old Activity Description | New Activity Description |
---|---|---|
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) |
GC-GCN140 | PH MS - Start Phase II | PH MS - Start Phase II B Construction |
GC-GCN150 | PH MS - Start Phase II | PH MS - Start Phase II C Construction |
GC-GCN170 | PH MS - Start Phase III | PH MS - Start Phase III B Construction |
GC-GCN180 | PH MS - Start Phase III | PH MS - Start Phase III C Construction |
GC-GCN190 | PH MS - Start Phase II | PH MS - Start Phase II D Construction |
GC-GCN200 | PH MS - Start Phase III | PH MS - Start Phase III A Construction |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B | PH IB - Asphalt - Structural - Ramp B/C Gore |
IBR-AP120 | PH IB - Asphalt - Structural - Ramp C | PH IB - Asphalt - Structural - Ramp C (Redundant) |
IBR-EW100 | PH IB - Embankment - Ramp B | PH IB - Embankment - Ramp B/C Gore |
IBR-EW110 | PH IB - Embankment - Ramp C | PH IB - Embankment - Ramp C (Redundant) |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B | PH IB - Clear & Grub/Demo - Ramp B/C Gore |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B | PH IB - Performance Turf, SOD - Ramp B/C Gore |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) |
IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C | PH IB - Clear & Grub/Demo - Ramp C (Redundant) |
IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C | PH IB - Performance Turf, SOD - Ramp C (Redundant) |
IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C | PH IB - Guardrail (Roadway) - Ramp C (Redundant) |
IBR-RW100 | PH IB - Stabilization - Ramp B | PH IB - Stabilization - Ramp B/C Gore |
IBR-RW110 | PH IB - Base - Ramp B | PH IB - Base - Ramp B/C Gore |
IBR-RW120 | PH IB - Stabilization - Ramp C | PH IB - Stabilization - Ramp C (Redundant) |
IBR-RW130 | PH IB - Base - Ramp C | PH IB - Base - Ramp C (Redundant) |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore |
IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) |
IIIC-CP10 | PH IIIC - Construct Ped | PH IIIC - Construct Ped. Signalization at Ramps G&F |
IIAR-TC120 | PH II | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) |
IIAR-TC130 | PH II | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) |
IIBR-GC200 | PH IIB - | PH IIB - Grade ditch and SOD - Ramp C |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | PH IIB - Performance Turf, SOD - Ramp R |
IIBR-GC390 | PH IIB - Guardrail (Roadway) - Ramp R | PH IIB - Guardrail (Roadway) - Ramp R |
IIBR-ITS90 | PH IIB - Install CCTV's (17-2 | PH IIB - Install CCTV's (17-22) |
IIBR-SP110 | PH IIB - Drainage | PH IIB - Drainage - Ramp E |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | PH IIC - Guardrail (Roadway) - Ramp S |
IVEBM-W140 | PH IV - Median Wall - | PH IV - Median Wall - Excavate - Station 207 to 217 |
IVEBM-W150 | PH IV - Median Wall - FFP | PH IV - Median Wall - FFP Stem Station 207 to 217 |
IVEBM-W160 | PH IV - Median Wall - | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 |
IVEBM-W170 | PH IV - Median Wall - | PH IV - Median Wall - Excavate - Station 259+50 to 311 |
IVEBM-W180 | PH IV - Median Wall - FFP | PH IV - Median Wall - FFP Stem - Station 259+50 to 311 |
IVEBM-W190 | PH IV - Median Wall - | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 |
IVEBM-W200 | PH IV - Median Wall - | PH IV - Median Wall - Excavate - Station 217 to 259+50 |
IVEBM-W210 | PH IV - Median Wall - FFP | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 |
IVEBM-W220 | PH IV - Median Wall - | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 |
PRE-FA-044 | Fabricate and | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable |
PRE-FA-047 | Fabricate and Deliver | Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS) |
PRE-PS-045 | Prepare and Submit | Prepare and Submit 660 ITS Vehicle Detection System |
PRE-PS-046 | Prepare and Submit | Prepare and Submit 684 ITS Managed Ethernet Hub Switch |
PRE-PS-049 | Prepare and Submit | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing |
PRE-RA-044 | Review and Approve | Review and Approve 633 ITS Fiber Optic Cable |
PRE-RA-045 | Review and Approve | Review and Approve 660 ITS Vehicle Detection System |
PRE-RA-046 | Review and Approve | Review and Approve 684 ITS Managed Ethernet Hub Switch |
PRE-RA-047 | Review and Approve | Review and Approve 685 ITS Uninterruptible Power Source (UPS) |
PRE-RA-049 | Review and Approve | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) |
IIBEBO-ST31 | PH IIB - Gravity Wall @ S | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall ( | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall ( | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) |
IIBEBO-W150 | PH IIB - MSE Wall RW5 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening |
IIIBR-AP140 | PH III | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P | PH IIIB - Asphalt - Structural - Ramp P to Shingle |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P | PH IIIB - Embankment - Ramp P to Shingle |
IIIBR-GC210 | PH III | PH III C - Demo - old temp Ramp T gore |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P | PH IIIB - Stabilization - Ramp P to Shingle |
IIIBR-RW210 | PH IIIB - Base - Ramp P | PH IIIB - Base - Ramp P to Shingle |
IIIBR-SM520 | PH IIIB - | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service ( | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) |
IIIBR-SP150 | PH IIIB - Drainage | PH IIIB - Drainage - Ramp P |
IIIBR-TC230 | PH III | PH III C - Temp Striping New Ramp Alignment - Ramp T |
IIICR-GC100 | PH IIIC - Demo - | PH IIIC - Demo - Old Ramp F |
IIICR-SP100 | PH IIIC - Drainage | PH IIIC - Drainage - Ramp F |
IIICR-SP110 | PH IIIC - Drainage | PH IIIC - Drainage - Ramp N |
IVEBM-AP100 | PH IV - Asphalt - Structural | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express |
IVEBM-GC100 | PH IV - Demo Temporary | PH IV - Demo Temporary pavement - EB Express |
IVEBM-SP100 | PH IV - Drainage - | PH IV - Drainage - Median Widening (West of 311) |
IVEBM-TC100 | PH IV - S | PH IV - Shift EB traffic to outside I-Drive through Station 312 |
IVEBM-TC110 | PH IV - | PH IV - Remove Temp Barrier - EB Median Widening |
IVEBM-TC120 | PH IV - | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP |
IVEBO-AP100 | PH IV - Asphalt - | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D |
IVEBO-SS100 | PH IV - Install O | PH IV - Install OT Structures - East of JYP |
IVWBM-AP100 | PH IV - Asphalt - Structural - | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express |
IVWBM-GC100 | PH IV - Demo Temporary - WB | PH IV - Demo Temporary - WB Express |
IVWBM-RW110 | PH IV - Grade for road | PH IV - Grade for road - Station 207 to 217 WB Express |
IVWBM-RW120 | PH IV - Grade for road | PH IV - Grade for road - Station 259+50 to 311 WB Express |
IVWBM-RW130 | PH IV - Grade for | PH IV - Grade for road Station 217 to 259+50 WB Express |
IVWBM-RW140 | PH IV - Stabilization | PH IV - Stabilization - Station 217 to 259+50 WB Express |
IVWBM-RW150 | PH IV - Base | PH IV - Base - Station 217 to 259+50 WB Express |
IVWBM-RW160 | PH IV - Stabilization | PH IV - Stabilization - Station 259+50 to 311 WB Express |
IVWBM-RW170 | PH IV - Base | PH IV - Base - Station 259+50 to 311 WB Express |
IVWBM-RW180 | PH IV - Stabilization for road | PH IV - Stabilization for road - Station 207 to 217 WB Express |
IVWBM-RW190 | PH IV - Base for road | PH IV - Base for road - Station 207 to 217 WB Express |
IVWBM-RW200 | PH IV - Grade for road | PH IV - Grade for road - Station 207 to 217 EB Express |
IVWBM-RW210 | PH IV - Stabilization | PH IV - Stabilization - Station 207 to 217 EB Express |
IVWBM-RW220 | PH IV - Base | PH IV - Base - Station 207 to 217 EB Express |
IVWBM-RW230 | PH IV - Grade for road | PH IV - Grade for road - Station 259+50 to 311 EB Express |
IVWBM-RW240 | PH IV - Stabilization | PH IV - Stabilization - Station 259+50 to 311 EB Express |
IVWBM-RW250 | PH IV - Base | PH IV - Base - Station 259+50 to 311 EB Express |
IVWBM-RW260 | PH IV - | PH IV - Subgrade Station 217 to 259+50 EB Express |
IVWBM-RW270 | PH IV - Stabilization for Station | PH IV - Stabilization for Station 217 to 259+50 EB Express |
IVWBM-RW280 | PH IV - Base | PH IV - Base - Station 217 to 259+50 EB Express |
IVWBM-SP100 | PH IV - Drainage - | PH IV - Drainage - Median Widening (East of 311) |
IVWBM-TC110 | PH IV - | PH IV - Remove Temp barrier - WB Median Widening |
IVWBO-AP100 | PH IV - Asphalt - | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C |
IVWBO-TC100 | PH IV - | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge |
IIBEBM-GC110 | PH I | PH IV - Rumble Strips - EB Median |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) |
IIBEBO-ST720 | PH IIB - Curing for End Bent | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) |
IIBEBO-ST730 | PH IIB - Curing for End Bent | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over universal BLVD) |
IIDEBO-ST190 | PH II | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST210 | PH II | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST240 | PH II | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over J | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) |
IIDEBO-ST300 | PH II | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) |
IIIBR-ITS160 | PH IIIB - Pull FOC ( | PH IIIB - Pull FOC (International to Univ) |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal |
IIIBWBO-W100 | PH IIIB - Concrete | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive |
IIIBWBO-W130 | PH IIIB - | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive |
IIIBWBO-EW130 | PH IIIB - Embankment (I | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge |
IIIBWBO-RW100 | PH IIIB - Stabilization ( | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area |
IIIBWBO-RW110 | PH IIIB - Stabilization ( | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-RW120 | PH IIIB - Stabilization ( | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area |
IIIBWBO-RW140 | PH IIIB - Base ( | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area |
IIIBWBO-RW150 | PH IIIB - Base ( | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area |
IIIBWBO-RW160 | PH IIIB - Base (I | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area |
IIIBWBO-SP100 | PH IIIB - Drainage ( | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) |
IIIBWBO-ST211 | PH IIIB - | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) |
IIIBWBO-ST260 | PH IIIB - Wall Bent | PH IIIB - Wall Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) |
IIIBWBO-ST280 | PH IIIB - | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST300 | PH IIIB - End Bent | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) |
IIIBWBO-ST310 | PH IIIB - End Bent | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
IIIBWBO-ST330 | PH IIIB - Curing for End Bent | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) |
The following original durations (OD) were changed since E8P02 Update No. 11
Activity ID | Activity Description | Critical | Old OD | New OD |
---|---|---|---|---|
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | Yes | 20 | 15 |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | No | 5 | 2 |
IBR-EW100 | PH IB - Embankment - Ramp B/C Gore | Yes | 22 | 5 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | Yes | 15 | 5 |
IBR-RW100 | PH IB - Stabilization - Ramp B/C Gore | Yes | 12 | 2 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | Yes | 22 | 4 |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | Yes | 5 | 2 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | Yes | 2 | 4 |
IIAR-EW100 | PH IIB - Embankment - Ramp O | Yes | 5 | 20 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | Yes | 2 | 4 |
IIAR-SP110 | PH IIB - Drainage - Ramp O | Yes | 3 | 20 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | Yes | 22 | 2 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | Yes | 20 | 4 |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | No | 1 | 10 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | Yes | 20 | 16 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | Yes | 20 | 14 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | Yes | 20 | 10 |
IIBR-RW110 | PH IIB - Base - Ramp B | Yes | 20 | 10 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | Yes | 10 | 1 |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | Yes | 5 | 10 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | Yes | 10 | 15 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | Yes | 6 | 10 |
PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | Yes | 14 | 5 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | Yes | 42 | 30 |
PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | Yes | 42 | 21 |
PRE-FA-030 | Fabricate and Deliver 042200 Masonry | Yes | 42 | 21 |
PRE-FA-033 | Fabricate and Deliver 101400 Signage | Yes | 42 | 21 |
PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | Yes | 42 | 21 |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | Yes | 7 | 2 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | Yes | 20 | 15 |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | Yes | 15 | 10 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | Yes | 15 | 10 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | Yes | 2 | 3 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | Yes | 1 | 4 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | Yes | 2 | 5 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | Yes | 8 | 10 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | Yes | 8 | 6 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | Yes | 4 | 6 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | Yes | 9 | 12 |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | Yes | 4 | 10 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | Yes | 5 | 10 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | Yes | 5 | 10 |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | Yes | 4 | 10 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | Yes | 8 | 12 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | Yes | 20 | 4 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | Yes | 22 | 14 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | Yes | 16 | 8 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | Yes | 15 | 10 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | Yes | 22 | 10 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | Yes | 20 | 10 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | Yes | 20 | 10 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | Yes | 20 | 10 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 8 | 6 |
IIIBWBO-ST390 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over International Drive) | Yes | 20 | 10 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 12 | 4 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 8 | 6 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 5 | 2 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 5 | 3 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | Yes | 15 | 3 |
IIIBWBO-ST690 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over International Drive) | Yes | 15 | 12 |
The following activities became critical since E8P02 Update No. 11
Activity ID | Activity Description | Old TF | New TF |
---|---|---|---|
NA-GC100 | TEC Install and Test | 14 | -34 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 7 | -130 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 15 | 0 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 15 | 0 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 81 | -3 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | 25 | -36 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | 25 | -36 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | 25 | -36 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | 91 | -9 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 91 | -9 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 91 | -35 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 91 | -35 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 91 | -35 |
TF-CO-021 | Install Bollards | 22 | -26 |
TF-CO-026 | Cont. Lightning | 17 | -23 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | 36 | -26 |
TF-CO-029 | Install Conduit/Raceways | 30 | -18 |
TF-CO-030 | Pull Wire | 14 | -23 |
TF-CO-031 | Toll Facility Finishes and Punchlist | 14 | -26 |
TF-CO-032 | Toll Facility CO | 14 | -26 |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 38 | -13 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 42 | -36 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 32 | -3 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 7 | -73 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 7 | -73 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 114 | -11 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 9 | -3 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 25 | -36 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 72 | -16 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 88 | -16 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 44 | -36 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 63 | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 63 | -22 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 63 | -22 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 7 | -73 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 63 | -22 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 75 | -41 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 75 | -34 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 75 | -32 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 75 | -32 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 75 | -3 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 75 | -3 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 14 | -32 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 48 | -12 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 34 | -30 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | 22 | -30 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 22 | -30 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | 22 | -21 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | 22 | -29 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 22 | -29 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 22 | -30 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 50 | -41 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 51 | -15 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 45 | -34 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | 25 | -36 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 96 | -16 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 7 | -53 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 7 | -53 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 7 | -53 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 7 | -53 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 7 | -73 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 7 | -73 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 7 | -73 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | 7 | -73 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 7 | -73 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 7 | -72 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 7 | -72 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 21 | -33 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | 67 | -34 |
The following relationship lags were changed since E8P02 Update No. 11
Activity ID | Activity Description | Relationship Type | Predecessor Activity ID | Predecessor Activity Description | Old Lag | New Lag |
---|---|---|---|---|---|---|
GC-GC110 | PH MS - Substantial Completion | FS | IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | 0 | 10 |
This table represents the longest path of E8P02 Update No 36.
Activity ID | Activity Description | Start Date | Finish Date | Total Float |
---|---|---|---|---|
ITS10-1040 | Fabrication and Delivery - Conduits | 05-Oct-18 | 19-Dec-18 | -130 |
ITS10-1090 | Furnish & Install - Conduit | 20-Dec-18 | 18-Feb-19 | -130 |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 19-Feb-19 | 21-Feb-19 | -130 |
ITS10-1130 | Furnish & Install - Conductors | 22-Feb-19 | 29-Mar-19 | -130 |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 01-Apr-19 | 16-Apr-19 | -130 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 17-Apr-19 | 29-May-19 | -130 |
GC-GCN210 | PH MS - Punch List/Acceptance | 30-May-19 | 28-Jun-19 | -190 |
GC-DP110 | PH MS - Project Completion | 28-Jun-19 | -190 |
This table compares the longest paths from both updates.
Activity ID | Activity Description | Start Date | Finish Date | Total Float |
---|---|---|---|---|
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 07-Sep-16 | 19-Sep-16 | -41 |
IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | 19-Sep-16 | 29-Sep-16 | -41 |
IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | 29-Sep-16 | 11-Oct-16 | -41 |
IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 | 18-Oct-16 | -41 |
IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 | 18-Oct-16 | -41 |
IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | 18-Oct-16 | 08-Nov-16 | -41 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 08-Nov-16 | 13-Dec-16 | -41 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 13-Dec-16 | 12-Jan-17 | -39 |
IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 12-Jan-17 | 18-Jan-17 | -61 |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 18-Jan-17 | 20-Jan-17 | -37 |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 20-Jan-17 | 25-Jan-17 | -38 |
IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 26-Jan-17 | 15-Feb-17 | -38 |
IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 16-Feb-17 | 22-Feb-17 | -57 |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 22-Feb-17 | 10-Mar-17 | -39 |
IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | 10-Mar-17 | 07-Apr-17 | -39 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 07-Apr-17 | 28-Apr-17 | -39 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 28-Apr-17 | 11-May-17 | -39 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 12-May-17 | 15-May-17 | -39 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 16-May-17 | 25-May-17 | -39 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 26-May-17 | 07-Jun-17 | -39 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 08-Jun-17 | 14-Jun-17 | -39 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 15-Jun-17 | 21-Jun-17 | -39 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Jun-17 | 13-Jul-17 | -39 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 14-Jul-17 | 20-Jul-17 | -39 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 21-Jul-17 | 03-Aug-17 | -39 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Aug-17 | 24-Aug-17 | -38 |
IIIBWBO-ST320 | PH IIIB - Curing for Pier 2, 3, (Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 24-Aug-17 | 30-Aug-17 | -56 |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 30-Aug-17 | 31-Aug-17 | -40 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 31-Aug-17 | 12-Sep-17 | -40 |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 13-Sep-17 | 03-Oct-17 | -40 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Oct-17 | 13-Oct-17 | -40 |
IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 16-Oct-17 | 06-Nov-17 | -40 |
IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 07-Nov-17 | 13-Nov-17 | -56 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 13-Nov-17 | 04-Dec-17 | -38 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Dec-17 | 03-Jan-18 | -38 |
IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 | 25-Jan-18 | -38 |
IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 25-Jan-18 | 09-Feb-18 | -38 |
IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 12-Feb-18 | 12-Feb-18 | -38 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 13-Feb-18 | 15-Feb-18 | -38 |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 16-Feb-18 | 21-Feb-18 | -38 |
GC-GCN160 | PH MS - Start Phase IV Construction | 22-Feb-18 | -38 | |
IVEBM-TC100 | PH IV - Set Temp Traffic Barriers - EB Median Widening | 22-Feb-18 | 27-Feb-18 | -38 |
IVEBM-GC100 | PH IV - Demo Temporary - EB Median Widening | 28-Feb-18 | 06-Mar-18 | -38 |
IVEBM-W140 | PH IV - Median Wall - Grading for Station 1 (I4 to International Drive) | 07-Mar-18 | 08-Mar-18 | -38 |
IVEBM-W150 | PH IV - Median Wall - FFP Footing/Stem for Station 1 (I4 to International Drive) | 09-Mar-18 | 22-Mar-18 | -38 |
IVEBM-W160 | PH IV - Median Wall - Construct/ slip Top for Station 1 (I4 to International Drive) | 23-Mar-18 | 29-Mar-18 | -38 |
IVEBM-W170 | PH IV - Median Wall - Grading for Station 2 (International Drive to Universal) | 30-Mar-18 | 06-Apr-18 | -38 |
IVEBM-W180 | PH IV - Median Wall - FFP Footing/Stem for Station 2 (International Drive to Universal) | 09-Apr-18 | 27-Apr-18 | -38 |
IVEBM-W190 | PH IV - Median Wall - Construct/ slip Top for Station 2 (International Drive to Universal) | 30-Apr-18 | 04-May-18 | -38 |
IVEBM-W200 | PH IV - Median Wall - Grading for Station 3 (Universal to JYP) | 07-May-18 | 18-May-18 | -38 |
IVEBM-W210 | PH IV - Median Wall - FFP Footing/Stem for Station 3 (Universal to JYP) | 21-May-18 | 04-Jun-18 | -38 |
IVEBM-W220 | PH IV - Median Wall - Construct/ slip Top for Station 3 (Universal to JYP) | 05-Jun-18 | 12-Jun-18 | -38 |
IVWBM-RW130 | PH IV - Grade for Station 3 (Universal to JYP) (B) | 13-Jun-18 | 19-Jun-18 | -38 |
IVWBM-RW140 | PH IV - Stabilization for Station 3 (Universal to JYP) (A) | 20-Jun-18 | 25-Jun-18 | -38 |
IVWBM-RW150 | PH IV - Base for Station 3 (Universal to JYP) (B) | 26-Jun-18 | 09-Jul-18 | -38 |
IVWBM-AP100 | PH IV - Asphalt - Structural - WB Median Widening | 10-Jul-18 | 13-Jul-18 | -38 |
ITS10-1040 | Fabrication and Delivery - Conduits | 05-Oct-18 | 19-Dec-18 | -130 |
ITS10-1090 | Furnish & Install - Conduit | 20-Dec-18 | 18-Feb-19 | -130 |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | 19-Feb-19 | 21-Feb-19 | -130 |
ITS10-1130 | Furnish & Install - Conductors | 22-Feb-19 | 29-Mar-19 | -130 |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | 01-Apr-19 | 16-Apr-19 | -130 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 17-Apr-19 | 29-May-19 | -130 |
GC-GCN210 | PH MS - Punch List/Acceptance | 30-May-19 | 28-Jun-19 | -190 |
GC-DP110 | PH MS - Project Completion | 28-Jun-19 | -190 |
Activity ID | Activity Description | Total Float |
---|---|---|
GC-DP110 | PH MS - Project Completion | -190 |
GC-GC110 | PH MS - Substantial Completion | -160 |
IIICR120 | PH IIIC - Shift traffic to new Ramp F / Remove Diversion/Construct Ramp Shoulder/Gore - Ramp F | -11 |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | -30 |
IIICR180 | PH IIIC - Remove Diversion - Ramp T | -7 |
NA-GC100 | TEC Install and Test | -34 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | -130 |
GC-GCN210 | PH MS - Punch List/Acceptance | -190 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 0 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 0 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | -3 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | -36 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | -36 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | -36 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | -9 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | -9 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | -35 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | -35 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | -35 |
TF-CO-021 | Install Bollards | -26 |
TF-CO-026 | Cont. Lightning | -23 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | -26 |
TF-CO-029 | Install Conduit/Raceways | -18 |
TF-CO-030 | Pull Wire | -23 |
TF-CO-031 | Toll Facility Finishes and Punchlist | -26 |
TF-CO-032 | Toll Facility CO | -26 |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | -13 |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | -39 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | -39 |
IIBR-GC100 | PH IIB - Demo - Ramp B | -39 |
IIBR-GC120 | PH IIB - Performance Turf, SOD - Ramp B | -39 |
IIBR-GC160 | PH IIB - Guardrail (Roadway) - Ramp B | -39 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | -36 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | -3 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | -73 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | -73 |
IIBR-RW100 | PH IIB - Stabilization - Ramp B | -39 |
IIBR-RW110 | PH IIB - Base - Ramp B | -39 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | -39 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | -11 |
IIBR-SP100 | PH IIB - Drainage - Ramp B | -39 |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | -39 |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | -39 |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | -3 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | -3 |
ITS10-1040 | Fabrication and Delivery - Conduits | -130 |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | -102 |
ITS10-1080 | Furnish & Install ITS Standby Generators | -102 |
ITS10-1090 | Furnish & Install - Conduit | -130 |
ITS10-1100 | ITS Generator Stand AloneTesting | -102 |
ITS10-1110 | Fabrication and Delivery - Conductors | -67 |
ITS10-1120 | Modify existing cabinets to incorporate additional conduit | -130 |
ITS10-1130 | Furnish & Install - Conductors | -130 |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | -36 |
ITS10-1150 | Furnish & Install - Step Up / Step Down Transformers | -130 |
ITS10-1160 | Furnish & Install - FOC Drops | -127 |
ITS10-1170 | Splice / Terminate FOC Drops | -127 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | -30 |
IVEBM-W150 | PH IV - Median Wall - FFP Stem Station 207 to 217 | -30 |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | -30 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | -41 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | -41 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | -41 |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | -4 |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | -22 |
IVML-AP130 | PH IV - Asphalt - Friction - from Consulate to JYP incl Ramps Q to V | -1 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | -36 |
IAWBO-EW100 | PH IA - Pond EXCAVATION (Shape 4A & 5A) - WB Outside Widening Area | -35 |
IBWBO-EW100 | PH IB - Pond Excav/Embank JYP to TPK - WB Outside Widening | -36 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | -16 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | -16 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | -36 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | -22 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | -22 |
IIIBR-GC400 | PH IIIB - Guardrail (Roadway) - WB outside 337-340 + old Ramp T | -22 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | -73 |
IIIBR-RW110 | PH IIIB - Base - Ramp G | -36 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | -22 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | -41 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | -34 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | -32 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | -32 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | -3 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | -3 |
IIICR-AP120 | PH IIIC - Mill and Resurface - Ramp F/G at I-Drive | -33 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | -7 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | -32 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | -33 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | -41 |
IVEBM-AP120 | PH IV - Asphalt - Structural - Station 311 to 352 EB Express | -15 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | -35 |
IVEBM-PM110 | PH IV - Tubular Delineators - EB Express Divider | -35 |
IVEBM-PM120 | PH IV - Pavement Markings (Final) - EB Express Widening | -37 |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | -41 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | -36 |
IVEBO-AP110 | PH IV - Asphalt - Friction - All ramps E thru P | -34 |
IVEBO-AP120 | PH IV - Asphalt - Friction - EB Express lanes to JYP | -42 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | -31 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | -12 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | -25 |
IVWBM-AP130 | PH IV - Asphalt - Structural - Station 311 to 352 WB Express | -22 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | -30 |
IVWBM-PM110 | PH IV - Tubular Delineators - WB Express Divider | -24 |
IVWBM-PM130 | PH IV - Pavement Markings (Final) - WB Express Widening | -11 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | -30 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | -25 |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | -25 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | -25 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | -30 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | -21 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | -29 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | -29 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | -30 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | -41 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | -41 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | -41 |
IVWBM-RW285 | PH IV - Grade for road - Station 311 to 332 EB Express | -12 |
IVWBM-RW290 | PH IV - Stabilization - Station 311 to 332 EB Express | -12 |
IVWBM-RW300 | PH IV - Base - Station 311 to 332 EB Express | -4 |
IVWBM-RW305 | PH IV - Grade for road - Station 335 to 352 EB Express | -12 |
IVWBM-RW310 | PH IV - Stabilization - Station 335 to 352 EB Express | -12 |
IVWBM-RW320 | PH IV - Base - Station 335 to 352 EB Express | -15 |
IVWBM-RW330 | PH IV - Stabilization - Station 311 to 332 WB Express | -17 |
IVWBM-RW340 | PH IV - Base - Station 311 to 332 WB Express | -17 |
IVWBM-RW350 | PH IV - Grade for road - Station 311 to 332 WB Express | -17 |
IVWBM-RW360 | PH IV - Stabilization - Station 335 to 352 WB Express | -22 |
IVWBM-RW370 | PH IV - Base - Station 335 to 352 WB Express | -22 |
IVWBM-RW380 | PH IV - Grade for road - Station 335 to 352 WB Express | -22 |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | -30 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | -25 |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | -25 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | -42 |
IVWBO-AP110 | PH IV - Asphalt - Friction - WB Express lanes from JYP to I-4 | -24 |
IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | -31 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | -41 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | -15 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | -34 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | -36 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | -16 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | -53 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | -53 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | -53 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | -53 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | -73 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | -73 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | -73 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | -73 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | -73 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | -72 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | -72 |
IIIBR-ITS1030 | PH IIIB - Pull Conductors (I-4 to International) | -73 |
IIIBR-ITS1040 | PH IIIB - Pull Conductors (International to Univ) | -73 |
IIIBR-ITS1050 | PH IIIB - Pull Conductors (UNIV to JYP) | -73 |
IIIBR-ITS1060 | PH IIIB - Pull Conductors (JYP to TPK) | -73 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | -33 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | -34 |
The following actual start dates were added in E8P02 Update No 36
Activity ID | Activity Description | Actual Start |
---|---|---|
GC-GCN100 | PH MS - Construction Mobilization | 19-Aug-15 |
PRE-PS-002 | Prepare and Submit 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood) | 20-Sep-15 |
PRE-PS-003 | Prepare and Submit 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway) | 20-Sep-15 |
PRE-PS-004 | Prepare and Submit 455 Pile Installation Plan (Structure 750629- Ramp S JYP) | 20-Sep-15 |
PRE-PS-005 | Prepare and Submit 455 Pile Installation Plan (Structure 750630- Ramp T JYP) | 20-Sep-15 |
IAR-TC140 | PH IA - Set Temp Traffic Barriers for Phase IB - EB Median Widening | 29-Oct-15 |
IBEBM-ST100 | PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek) | 05-Nov-15 |
GC-GCN120 | PH MS - Start Phase IB Construction | 20-Nov-15 |
PRE-FA-00147 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 12X53 (Structure 750629-Ramp S JYP) | 17-Jan-16 |
IBWBM-SP110 | PH IB - Drainage for JYP to STA 390 | 18-Feb-16 |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 21-Feb-16 |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 21-Feb-16 |
PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | 21-Feb-16 |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 21-Feb-16 |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 21-Feb-16 |
IAEBO-W130 | PH IA - Noise/Sound Wall Prep Work (W-2) - EB Outside Widening | 22-Feb-16 |
IAEBO-GC130 | PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H) | 22-Feb-16 |
IBEBM-ST390 | PH IB - Curing for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | 24-Feb-16 |
IBEBM-ST260 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD) | 29-Feb-16 |
IBEBM-ST900 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD) | 29-Feb-16 |
IBWBM-ST180 | PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD) | 29-Feb-16 |
IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) | 29-Feb-16 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 01-Mar-16 |
PRE-RA-007 | Review and Approve 400 Concrete Structures (Bearing Pads) | 02-Mar-16 |
IBR-IDS10 | PH IB - Install Drilled Shafts (1-13) | 04-Mar-16 |
IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | 07-Mar-16 |
PRE-FA-007 | Fabricate and Deliver 400 Concrete Structures (Bearing Pads) | 09-Mar-16 |
IBEBM-ST270 | PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD) | 10-Mar-16 |
IBEBM-ST290 | PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD) | 10-Mar-16 |
IBWBM-ST210 | PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 10-Mar-16 |
IBEBM-ST150 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR) | 14-Mar-16 |
IBEBM-ST890 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR) | 14-Mar-16 |
IBWBM-ST120 | PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR) | 14-Mar-16 |
IBWBM-ST730 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR) | 14-Mar-16 |
IBEBM-ST140 | PH IB - Construct Crane Access - EB Median Widening (Bridge over International DR) | 17-Mar-16 |
IBWBM-ST110 | PH IB - Construct Crane Access - WB Median Widening (Bridge over International DR) | 17-Mar-16 |
IBWBO-SP140 | PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50) | 17-Mar-16 |
IIBEBO-ST21 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-Mar-16 |
IIDEBO-ST120 | PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY) | 18-Mar-16 |
PRE-PS-049 | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing | 21-Mar-16 |
IBWBM-ST710 | PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD) | 22-Mar-16 |
IBEBM-ST230 | PH IB - Production Pile - EB Median Widening (Bridge over International DR) | 28-Mar-16 |
IBWBM-ST130 | PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR) | 28-Mar-16 |
IBWBM-ST150 | PH IB - Production Pile - WB Median Widening (Bridge over International DR) | 28-Mar-16 |
PRE-RA-049 | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing | 30-Mar-16 |
IIIAWBO-ST18 | PH IIIA - Production Pile (H Piles) (1-32) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 04-Apr-16 |
IIICR-EW100 | PH IIIC - Embankment - Ramp F | 05-Apr-16 |
IIIAWBO-ST27 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over John Young PKWY) | 05-Apr-16 |
IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | 07-Apr-16 |
IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | 11-Apr-16 |
IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | 12-Apr-16 |
IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | 12-Apr-16 |
IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Apr-16 |
PRE-PS-015 | Prepare and Submit 548 Retaining/MSE Wall Systems | 17-Apr-16 |
IBEBM-ST330 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR) | 18-Apr-16 |
IBEBM-ST370 | PH IB - End Bent 1 - EB Median Widening (Bridge over International DR) | 18-Apr-16 |
IBWBM-ST280 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR) | 18-Apr-16 |
IBWBM-ST290 | PH IB - End Bent 1 - WB Median Widening (Bridge over International DR) | 18-Apr-16 |
IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | 18-Apr-16 |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 18-Apr-16 |
IBEBM-ST710 | PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD) | 20-Apr-16 |
IBWBM-ST570 | PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD) | 20-Apr-16 |
IBEBM-ST430 | PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek) | 28-Apr-16 |
IAEBO-W110 | PH IA - Install Posts (1-101)- EB Outside Widening | 29-Apr-16 |
PRE-RA-015 | Review and Approve 548 Retaining/MSE Wall Systems | 29-Apr-16 |
PRE-PS-020 | Prepare and Submit 992 Under deck Lighting | 02-May-16 |
IBEBM-ST480 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY) | 05-May-16 |
IBEBM-ST530 | PH IB - End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | 05-May-16 |
IBWBM-ST330 | PH IB - End Bent 3 - WB Median Widening (Bridge over International DR) | 05-May-16 |
IBWBM-ST450 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY) | 05-May-16 |
IIDEBO-ST170 | PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY) | 05-May-16 |
IIIAWBO-ST17 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 05-May-16 |
IBEBM-ST360 | PH IB - Pier 2, 3, 4(F/R/P) ( Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | 06-May-16 |
IBEBM-ST700 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over universal BLVD) | 06-May-16 |
IBWBM-ST550 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over universal BLVD) | 06-May-16 |
IAEBO-W120 | PH IA - Install Posts (102- 203) - EB Outside Widening | 09-May-16 |
IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 09-May-16 |
IBEBM-ST380 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR) | 09-May-16 |
IBEBM-ST410 | PH IB - End Bent 3 - EB Median Widening (Bridge over International DR) | 09-May-16 |
IBWBM-ST320 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR) | 09-May-16 |
IBEBM-ST970 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over universal BLVD) | 10-May-16 |
IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | 11-May-16 |
IBEBM-ST420 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over International DR) | 12-May-16 |
PRE-RA-020 | Review and Approve 992 Under deck Lighting | 13-May-16 |
IBWBM-ST750 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over International DR) | 13-May-16 |
PRE-PS-021 | Prepare and Submit 05500 Metal Fabrications | 16-May-16 |
IBEBM-ST200 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over International DR) | 16-May-16 |
IBWBM-ST140 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over International DR) | 16-May-16 |
IBWBM-ST760 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over universal BLVD) | 16-May-16 |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | 16-May-16 |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 16-May-16 |
IAEBO-W140 | PH IA - Install Posts (204-305) - EB Outside Widening | 18-May-16 |
IIBR-EW122 | PH IIB - Embankment - Ramp A | 18-May-16 |
IBEBM-ST250 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | 18-May-16 |
IBEBM-ST980 | PH IB - Curing for End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | 18-May-16 |
IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | 20-May-16 |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 23-May-16 |
IIIAWBO-ST30 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY) | 25-May-16 |
IAEBO-W150 | PH IA - Install Posts (306- 409) - EB Outside Widening | 26-May-16 |
PRE-PS-006 | Prepare and Submit Precast Erection | 03-Jun-16 |
PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | 03-Jun-16 |
IBEBM-W130 | PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528) | 06-Jun-16 |
IBEBM-W140 | PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528) | 06-Jun-16 |
IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | 06-Jun-16 |
IBWBM-W120 | PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528) | 06-Jun-16 |
IBWBM-W140 | PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528) | 06-Jun-16 |
IBEBM-ST850 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD) | 06-Jun-16 |
IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 06-Jun-16 |
PRE-RA-021 | Review and Approve 05500 Metal Fabrications | 08-Jun-16 |
IBEBM-ST280 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD) | 08-Jun-16 |
IBWBM-ST200 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD) | 08-Jun-16 |
IAEBO-IL100 | PH IA - Temp. ITS Relocate Existing - EB Outside Widening (SR528) | 09-Jun-16 |
IIBEBO-ST3 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over International DR) | 13-Jun-16 |
IIBR-GC171 | PH IIB - Clear & Grub/Demo - Ramp A | 13-Jun-16 |
IIBR-SP121 | PH IIB - Drainage - Ramp A | 13-Jun-16 |
IBEBM-ST520 | PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 13-Jun-16 |
IBEBM-ST560 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over International DR) | 13-Jun-16 |
IBEBM-ST570 | PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 13-Jun-16 |
IBWBM-ST400 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR) | 13-Jun-16 |
IBWBM-ST490 | PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 13-Jun-16 |
IBWBM-ST530 | PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 13-Jun-16 |
IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening | 20-Jun-16 |
IAEBO-W160 | PH IA - Install Panels (0-32000 SF) - EB Outside Widening | 27-Jun-16 |
IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | 27-Jun-16 |
IIIBWBO-ST3 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR) | 27-Jun-16 |
IAEBO-W170 | PH IA - Install Panels (32000-64000 SF) - EB Outside Widening | 29-Jun-16 |
IAEBO-W180 | PH IA - Install Panels (64000-96000 SF)- EB Outside Widening | 05-Jul-16 |
IIBR-RW141 | PH IIB - Stabilization - Ramp A | 05-Jul-16 |
IIAR-SP100 | PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp O | 06-Jul-16 |
IAEBO-SP100 | PH IA - Jack & Bore 42" (Sta 351+00 near Duke energy access platform) - EB Outside Widening (SR528) | 06-Jul-16 |
IAEBO-W190 | PH IA - Install Panels (96000-128000 SF)- EB Outside Widening | 08-Jul-16 |
IIAR100 | PH IIA - Construct Ramp O Diversion - Ramp O | 11-Jul-16 |
IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 11-Jul-16 |
IAEBO-W200 | PH IA - Install Panels (128000-160000 SF) - EB Outside Widening | 12-Jul-16 |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 13-Jul-16 |
IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | 13-Jul-16 |
IBEBM-ST800 | PH IB - Approach Slabs - EB Median Widening (Bridge over Shingle Creek) | 13-Jul-16 |
IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 13-Jul-16 |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 13-Jul-16 |
IIBR-RW151 | PH IIB - Base - Ramp A | 14-Jul-16 |
IIBEBO-ST1 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over International DR) | 18-Jul-16 |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 18-Jul-16 |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 18-Jul-16 |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 18-Jul-16 |
IBWBM-RW240 | PH IB - Pavement for Permanent Shoulder Construction (Universal-International Drv.) - WB Median Widening | 18-Jul-16 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 18-Jul-16 |
IIIBWBO-ST1 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over International DR) | 18-Jul-16 |
IBEBM-ST720 | PH IB - Curing for End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
IBWBM-ST740 | PH IB - Curing for End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
IAEBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - EB Outside Widening (SR528) | 25-Jul-16 |
IBEBM-ST320 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over International DR) | 25-Jul-16 |
IBWBM-ST270 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over International DR) | 25-Jul-16 |
IIAR-SP110 | PH IIB - Drainage - Ramp O | 26-Jul-16 |
IIBEBO-ST8 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over International DR) | 26-Jul-16 |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 26-Jul-16 |
IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 26-Jul-16 |
PRE-RA-044 | Review and Approve 633 ITS Fiber Optic Cable | 26-Jul-16 |
IBEBM-ST640 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over universal BLVD) | 26-Jul-16 |
IBWBM-ST510 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over universal BLVD) | 26-Jul-16 |
IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | 27-Jul-16 |
IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | 27-Jul-16 |
IBEBM-ST300 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | 27-Jul-16 |
IBWBM-ST220 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR) | 27-Jul-16 |
IIIBWBO-ST9 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over International DR) | 27-Jul-16 |
IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | 28-Jul-16 |
PRE-PS-041 | Prepare and Submit 682 CCTV Camera | 01-Aug-16 |
PRE-PS-045 | Prepare and Submit 660 ITS Vehicle Detection System | 01-Aug-16 |
PRE-PS-046 | Prepare and Submit 684 ITS Managed Ethernet Hub Switch | 01-Aug-16 |
PRE-PS-047 | Prepare and Submit 785 ITS Uninterruptible Power Source (UPS) | 01-Aug-16 |
IIBEBO-ST28 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek) | 01-Aug-16 |
IBEBM-ST440 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | 02-Aug-16 |
IBWBM-ST370 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY) | 02-Aug-16 |
PRE-FA-047 | Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS) | 03-Aug-16 |
PRE-RA-041 | Review and Approve 682 CCTV Camera | 03-Aug-16 |
PRE-RA-045 | Review and Approve 660 ITS Vehicle Detection System | 03-Aug-16 |
PRE-RA-046 | Review and Approve 684 ITS Managed Ethernet Hub Switch | 03-Aug-16 |
PRE-RA-047 | Review and Approve 685 ITS Uninterruptible Power Source (UPS) | 03-Aug-16 |
IBEBM-ST510 | PH IB - End Bent 1 - EB Median Widening (Bridge over John Young PKWY) | 03-Aug-16 |
IBEBM-ST810 | PH IB - Grind and Groove - EB Median Widening (Bridge over Shingle Creek) | 03-Aug-16 |
IBWBM-ST460 | PH IB - End Bent 1 - WB Median Widening (Bridge over John Young PKWY) | 03-Aug-16 |
IBEBM-ST610 | PH IB - Curing for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | 04-Aug-16 |
IBEBM-ST990 | PH IB - Bolt/Pin Temp B/W - EB Median Widening (Bridge over Shingle Creek) | 04-Aug-16 |
IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | 04-Aug-16 |
IBWBM-ST480 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD) | 04-Aug-16 |
IIBEBO-ST6 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR) | 05-Aug-16 |
IBEBM-ST490 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over John Young PKWY) | 05-Aug-16 |
IBWBM-ST420 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over John Young PKWY) | 05-Aug-16 |
PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | 08-Aug-16 |
IBWBM-ST190 | PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 10-Aug-16 |
IIIAWBO-ST35 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over John Young PKWY) | 10-Aug-16 |
IIIAWBO-ST23 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 11-Aug-16 |
IIBEBO-ST27 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 12-Aug-16 |
IIIBWBO-ST6 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over universal BLVD) | 15-Aug-16 |
IBEBM-ST680 | PH IB - End Bent 1 - EB Median Widening (Bridge over universal BLVD) | 18-Aug-16 |
IBWBM-ST540 | PH IB - End Bent 1 - WB Median Widening (Bridge over universal BLVD) | 18-Aug-16 |
IIBEBO-ST9 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over universal BLVD) | 22-Aug-16 |
PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | 22-Aug-16 |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 22-Aug-16 |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 22-Aug-16 |
PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | 22-Aug-16 |
PRE-FA-044 | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable | 22-Aug-16 |
PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | 22-Aug-16 |
PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | 22-Aug-16 |
PRE-PS-042 | Prepare and Submit 781 DMS | 22-Aug-16 |
PRE-RA-042 | Review and Approve 781 DMS | 25-Aug-16 |
IBEBM-ST650 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over universal BLVD) | 02-Sep-16 |
IBWBM-ST520 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over universal BLVD) | 02-Sep-16 |
IBWBM-ST620 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over John Young PKWY) | 06-Sep-16 |
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 07-Sep-16 |
IIAR-TC140 | PH IIA - Temp Striping New Ramp Alignment - Ramp O | 07-Sep-16 |
IIAEBO-TC120 | PH IIA - MOT Shift for Phase IIA - EB Outside Widening | 07-Sep-16 |
IBEBO-GC100 | PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - EB Outside Widening | 08-Sep-16 |
IBWBO-GC100 | PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - WB Outside Widening Area | 08-Sep-16 |
IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | 08-Sep-16 |
IBEBM-ST740 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY) | 12-Sep-16 |
IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | 12-Sep-16 |
IIBR-GC191 | PH IIB - Performance Turf, SOD - Ramp A | 13-Sep-16 |
IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | 14-Sep-16 |
IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | 15-Sep-16 |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 15-Sep-16 |
GC-GCN130 | PH MS - Start Phase IIA Construction | 19-Sep-16 |
IIDEBO-ST150 | PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 21-Sep-16 |
IIIAWBO-ST21 | PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 21-Sep-16 |
IIIAWBO-ST33 | PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Sep-16 |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 26-Sep-16 |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 27-Sep-16 |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 27-Sep-16 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 28-Sep-16 |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 03-Oct-16 |
GC-GCN140 | PH MS - Start Phase II B Construction | 04-Oct-16 |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 04-Oct-16 |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 10-Oct-16 |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 10-Oct-16 |
IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | 10-Oct-16 |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 11-Oct-16 |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 11-Oct-16 |
IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 |
IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 |
IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | 12-Oct-16 |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 13-Oct-16 |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 13-Oct-16 |
IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | 13-Oct-16 |
IIBEBO-ST11 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD) | 17-Oct-16 |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 17-Oct-16 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 17-Oct-16 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 17-Oct-16 |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 17-Oct-16 |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 17-Oct-16 |
PRE-PS-031 | Prepare and Submit 081100 Metal Doors and Frames | 19-Oct-16 |
PRE-PS-032 | Prepare and Submit 099100 Painting Product Data and Sample | 19-Oct-16 |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 21-Oct-16 |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 24-Oct-16 |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 24-Oct-16 |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 24-Oct-16 |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 24-Oct-16 |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 26-Oct-16 |
PRE-RA-031 | Review and Approve 081100 Metal Doors and Frames | 26-Oct-16 |
PRE-RA-032 | Review and Approve 099100 Painting Product Data and Sample | 26-Oct-16 |
IBWBM-RW130 | PH IB - Grade (JYP-Universal) - WB Median Widening | 26-Oct-16 |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 27-Oct-16 |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 27-Oct-16 |
IBWBM-RW140 | PH IB - Stabilization (JYP-Universal) - WB Median Widening | 28-Oct-16 |
IIIBWBO-ST8 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD) | 28-Oct-16 |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 31-Oct-16 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 01-Nov-16 |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 01-Nov-16 |
IBWBM-RW150 | PH IB - Base (JYP-Universal) - WB Median Widening | 03-Nov-16 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 07-Nov-16 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 07-Nov-16 |
IAWBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528) | 10-Nov-16 |
IIBEBO-ST25 | PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 14-Nov-16 |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 15-Nov-16 |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 16-Nov-16 |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 17-Nov-16 |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 18-Nov-16 |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 18-Nov-16 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 21-Nov-16 |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 28-Nov-16 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 02-Dec-16 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 06-Dec-16 |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 06-Dec-16 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 07-Dec-16 |
IIBEBO-ST16 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 08-Dec-16 |
IIIBWBO-ST12 | PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 08-Dec-16 |
IBWBM-RW160 | PH IB - Grade (Universal-International Drv.) - WB Median Widening | 14-Dec-16 |
IBWBM-RW170 | PH IB - Stabilization (Universal-International Drv.) - WB Median Widening | 14-Dec-16 |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 14-Dec-16 |
IBWBM-RW190 | PH IB - Grade (International Drive-I4) - WB Median Widening | 15-Dec-16 |
IBWBM-RW200 | PH IB - Stabilization (International Drv.-I4) - WB Median Widening | 15-Dec-16 |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 15-Dec-16 |
IIBEBO-ST17 | PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLV | 15-Dec-16 |
IIBEBO-ST18 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD) | 15-Dec-16 |
IIIBWBO-ST13 | PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Uni | 15-Dec-16 |
IIIBWBO-ST14 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD) | 16-Dec-16 |
IBR-AP120 | PH IB - Asphalt - Structural - Ramp C (Redundant) | 19-Dec-16 |
IBR-EW110 | PH IB - Embankment - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) | 19-Dec-16 |
IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C (Redundant) | 19-Dec-16 |
IBR-RW120 | PH IB - Stabilization - Ramp C (Redundant) | 19-Dec-16 |
IBR-RW130 | PH IB - Base - Ramp C (Redundant) | 19-Dec-16 |
IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) | 19-Dec-16 |
IIBR-AP160 | PH IIB - Asphalt - Structural - Ramp I4- Interstate | 19-Dec-16 |
IIBR-EW180 | PH IIB - Embankment - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC300 | PH IIB - Demo - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC400 | PH IIB - Guardrail (Roadway) - Ramp I4- Interstate | 19-Dec-16 |
IIBR-RW210 | PH IIB - Stabilization - Ramp I4- Interstate | 19-Dec-16 |
IIBR-RW230 | PH IIB - Base - Ramp I4- Interstate | 19-Dec-16 |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 19-Dec-16 |
IIBR-SP180 | PH IIB - Drainage (Temp) - Ramp I4 Interstate | 19-Dec-16 |
IIBR-SP190 | PH IIB - Drainage (Temp) - Ramp L | 19-Dec-16 |
IIBR-SP200 | PH IIB - Drainage (Temp) - Ramp U | 19-Dec-16 |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 19-Dec-16 |
IIBR-TC360 | PH IIB - Temp Striping New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 |
IIBR-TC370 | PH IIB - MOT Shift New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 19-Dec-16 |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 19-Dec-16 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 19-Dec-16 |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 19-Dec-16 |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 04-Jan-17 |
PRE-PS-038 | Prepare and Submit 238119 Packaged Air Conditioners | 09-Jan-17 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 10-Jan-17 |
IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 10-Jan-17 |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10-Jan-17 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 11-Jan-17 |
IIBEBO-ST260 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 11-Jan-17 |
TF-RA-001 | Review and Approve Precast Erection | 12-Jan-17 |
PRE-RA-022 | Review and Approve 133420 Pre-Engineered Precast Concrete Structure | 12-Jan-17 |
PRE-RA-038 | Review and Approve 238119 Packaged Air Conditioners | 12-Jan-17 |
IBEBM-ST550 | PH IB - Approach Slabs - EB Median Widening (Bridge over International DR) | 12-Jan-17 |
IBWBM-ST390 | PH IB - Approach Slabs - WB Median Widening (Bridge over International DR) | 12-Jan-17 |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 13-Jan-17 |
IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 13-Jan-17 |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 16-Jan-17 |
IIBR-SP140 | PH IIB - Drainage (Temp) - Ramp S-1 | 16-Jan-17 |
IIBR-TC280 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1 | 16-Jan-17 |
IIBR-TC380 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp L | 16-Jan-17 |
IIBR-TC400 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp U | 16-Jan-17 |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 16-Jan-17 |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 16-Jan-17 |
PRE-PS-036 | Prepare and Submit 232000 Piping and Specialties | 16-Jan-17 |
PRE-PS-039 | Prepare and Submit 260536 Cable Trays | 16-Jan-17 |
IBEBO-EW120 | PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside Widening | 16-Jan-17 |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 17-Jan-17 |
PRE-RA-036 | Review and Approve 232000 Piping and Specialties | 18-Jan-17 |
PRE-RA-039 | Review and Approve 260536 Cable Trays | 18-Jan-17 |
IBEBM-RW270 | PH IB - Stabilization (Universal - JYP) - EB Median Widening | 18-Jan-17 |
IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | 18-Jan-17 |
PRE-RA-001 | Review and Approve 506 Bridge Drainage System | 19-Jan-17 |
IBEBM-ST840 | PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD) | 20-Jan-17 |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 20-Jan-17 |
IIIBR120 | PH IIIB - Construct Ramp V Diversion - Ramp V | 23-Jan-17 |
GC-GCN170 | PH MS - Start Phase III B Construction | 23-Jan-17 |
IIBEBO-ST150 | PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 24-Jan-17 |
PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | 25-Jan-17 |
PRE-FA-036 | Fabricate and Deliver 232000 Piping and Specialties | 25-Jan-17 |
IBWBM-ST650 | PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD) | 25-Jan-17 |
IBEBM-ST580 | PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR) | 26-Jan-17 |
IBWBM-ST430 | PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR) | 26-Jan-17 |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 26-Jan-17 |
IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 27-Jan-17 |
TF-FA-001 | Fabricate and Deliver Precast Erection | 30-Jan-17 |
IBEBM-RW230 | PH IB - Grade (International Drive - Universal) - EB Median Widening | 30-Jan-17 |
IBEBM-ST860 | PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD) | 30-Jan-17 |
IIBEBO-ST120 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 30-Jan-17 |
IIBEBO-ST710 | PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 30-Jan-17 |
IIBR-SP160 | PH IIB - Drainage (Temp) - Ramp H | 31-Jan-17 |
IBWBM-ST630 | PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY) | 31-Jan-17 |
IBWBM-ST680 | PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD) | 31-Jan-17 |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 01-Feb-17 |
IBEBM-ST770 | PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY) | 01-Feb-17 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 06-Feb-17 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 06-Feb-17 |
IBEBM-RW220 | PH IB - Grade (I4-International Drive) - EB Median Widening | 06-Feb-17 |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 06-Feb-17 |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 06-Feb-17 |
IBEBM-ST590 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR) | 07-Feb-17 |
IBWBM-ST440 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR) | 07-Feb-17 |
IBEBM-RW260 | PH IB - Stabilization (International Drive - Universal) - EB Median Widening | 08-Feb-17 |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 08-Feb-17 |
IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | 08-Feb-17 |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 09-Feb-17 |
IBEBM-ST870 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD) | 09-Feb-17 |
IBWBM-ST690 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD) | 09-Feb-17 |
IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | 10-Feb-17 |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 13-Feb-17 |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 13-Feb-17 |
IIBEBO-ST280 | PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 13-Feb-17 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 15-Feb-17 |
IBEBM-ST730 | PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY) | 15-Feb-17 |
IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | 15-Feb-17 |
IBEBM-RW250 | PH IB - Stabilization (I4-international Drive) - EB Median Widening | 17-Feb-17 |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-Feb-17 |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 20-Feb-17 |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 20-Feb-17 |
IBEBM-ST600 | PH IB - Grind and Groove - EB Median Widening (Bridge over International DR) | 20-Feb-17 |
IBWBM-ST470 | PH IB - Grind and Groove - WB Median Widening (Bridge over International DR) | 20-Feb-17 |
IBEBM-ST880 | PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD) | 21-Feb-17 |
IBWBM-ST700 | PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD) | 21-Feb-17 |
IIBR-TC300 | PH IIB - Temp Striping New Ramp Alignment - Ramp I-1 | 23-Feb-17 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 24-Feb-17 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 24-Feb-17 |
IIBR-TC220 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp E | 27-Feb-17 |
IIBR-TC310 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp H | 27-Feb-17 |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 27-Feb-17 |
PRE-PS-033 | Prepare and Submit 101400 Signage | 27-Feb-17 |
IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | 27-Feb-17 |
GC-GCN150 | PH MS - Start Phase II C Construction | 28-Feb-17 |
IIBR-TC230 | PH IIB - Temp Striping New Ramp Alignment - Ramp E | 28-Feb-17 |
IIBR-TC320 | PH IIB - Temp Striping New Ramp Alignment - Ramp H | 28-Feb-17 |
IIBR-TC390 | PH IIB - Temp Striping New Ramp Alignment - Ramp L | 28-Feb-17 |
IBEBM-ST790 | PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY) | 28-Feb-17 |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 01-Mar-17 |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 02-Mar-17 |
IBEBM-ST780 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY) | 03-Mar-17 |
IIBR-GC110 | PH IIB - Demo - Ramp E | 06-Mar-17 |
IBWBM-ST640 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY) | 06-Mar-17 |
IIBR-GC240 | PH IIB - Demo - Ramp H | 07-Mar-17 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 07-Mar-17 |
IIBR-TC340 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2 | 09-Mar-17 |
IIBR-TC410 | PH IIB - Temp Striping New Ramp Alignment - Ramp U | 09-Mar-17 |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 09-Mar-17 |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10-Mar-17 |
IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | 13-Mar-17 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 14-Mar-17 |
IIIAWBO-ST230 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 15-Mar-17 |
IIIBR-TC190 | PH IIIB - Temp Striping New Ramp Alignment - Ramp V | 16-Mar-17 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 17-Mar-17 |
IIIAWBO-ST200 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 17-Mar-17 |
TF-CO-002 | Install Upright 1 D.S. | 20-Mar-17 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 20-Mar-17 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 20-Mar-17 |
IIBR-GC310 | PH IIB - Demo - Ramp L | 20-Mar-17 |
IIBR-SP170 | PH IIB - Drainage (Temp) - Ramp R-2 | 20-Mar-17 |
IIBR-TC450 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp D | 20-Mar-17 |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 20-Mar-17 |
PRE-PS-017 | Prepare and Submit 646 Aluminum Pedestal Poles | 20-Mar-17 |
PRE-PS-026 | Prepare and Submit 653 Pedestrian Signals | 20-Mar-17 |
PRE-PS-028 | Prepare and Submit 665 Pedestrian Detector | 20-Mar-17 |
PRE-PS-040 | Prepare and Submit 264113 Lighting Protection System Product Data and Shop Drawing | 20-Mar-17 |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 20-Mar-17 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 20-Mar-17 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 20-Mar-17 |
IIBR-GC130 | PH IIB - Demo - Ramp R-1 | 21-Mar-17 |
IIBR-GC290 | PH IIB - Demo - Ramp R-2 | 21-Mar-17 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 21-Mar-17 |
TF-CO-005 | Install Upright 2 D.S. | 22-Mar-17 |
PRE-RA-017 | Review and Approve 646 Aluminum Pedestal Poles | 23-Mar-17 |
PRE-RA-018 | Review and Approve 650 Traffic Signals | 23-Mar-17 |
PRE-RA-026 | Review and Approve 653 Pedestrian Signals | 23-Mar-17 |
PRE-RA-028 | Review and Approve 665 Pedestrian Detector | 23-Mar-17 |
TF-CO-007 | Install Upright 3 D.S. | 24-Mar-17 |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 27-Mar-17 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 27-Mar-17 |
PRE-RA-035 | Review and Approve 231323 Aboveground Diesel Storage Tank and Piping | 28-Mar-17 |
PRE-RA-040 | Review and Approve 264113 Lighting Protection System Product Data and Shop Drawing | 28-Mar-17 |
IIIBR-GC180 | PH IIIB - Demo - Ramp V | 28-Mar-17 |
IIBR-GC350 | PH IIB - Demo - Ramp U | 29-Mar-17 |
PRE-RA-033 | Review and Approve 101400 Signage | 29-Mar-17 |
IIAEBO-AP100 | PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 29-Mar-17 |
GC-GCN200 | PH MS - Start Phase III A Construction | 30-Mar-17 |
TF-CO-011 | AS Build D.S. | 30-Mar-17 |
IIIBR130 | PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp K | 03-Apr-17 |
IIBR-EW190 | PH IIB - Embankment - Ramp L | 03-Apr-17 |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 03-Apr-17 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 03-Apr-17 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 05-Apr-17 |
IIIAWBO-ST330 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 05-Apr-17 |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 07-Apr-17 |
PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals | 07-Apr-17 |
PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector | 07-Apr-17 |
IIBR-SP120 | PH IIB - Drainage (Temp) - Ramp R-1 | 10-Apr-17 |
IIBR-TC440 | PH IIB - Temp Striping New Ramp Alignment - Ramp D | 10-Apr-17 |
IIBEBO-ST320 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD) | 10-Apr-17 |
IIBR-RW270 | PH IIB - Base - Ramp U | 12-Apr-17 |
IIBEBO-ST130 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR) | 12-Apr-17 |
IIIAWBO-ST290 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Apr-17 |
IIBR-TC250 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp C | 16-Apr-17 |
PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | 19-Apr-17 |
IIIBR-TC180 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp V | 19-Apr-17 |
IIIAWBO-ST340 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 19-Apr-17 |
IIBEBO-ST600 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek) | 20-Apr-17 |
PRE-RA-034 | Review and Approve 231113 Fuel Oil Piping | 21-Apr-17 |
IIBEBO-ST610 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek) | 24-Apr-17 |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 24-Apr-17 |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 24-Apr-17 |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 24-Apr-17 |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 25-Apr-17 |
IIIBR-TC210 | PH IIIB - Temp Striping New Ramp Alignment - Ramp K | 01-May-17 |
IIBEBO-ST430 | PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 01-May-17 |
IIIBWBO-EW100 | PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening Area | 01-May-17 |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 03-May-17 |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 05-May-17 |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 05-May-17 |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 05-May-17 |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 08-May-17 |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 09-May-17 |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 10-May-17 |
IIIAWBO-ST410 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10-May-17 |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 11-May-17 |
IIDEBO-ST340 | PH IID - Curing for End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 12-May-17 |
PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | 15-May-17 |
IIIAWBO-ST420 | PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 15-May-17 |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 16-May-17 |
IIBEBO-ST460 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-May-17 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 18-May-17 |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 18-May-17 |
IIIBR-EW120 | PH IIIB - Embankment - Ramp V | 18-May-17 |
IIBEBO-ST470 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 19-May-17 |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 19-May-17 |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | 22-May-17 |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 22-May-17 |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 22-May-17 |
PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | 22-May-17 |
PRE-RA-037 | Review and Approve 233113 Ductwork Product Data and Shop Drawing | 22-May-17 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 23-May-17 |
IIAR-RW110 | PH IIB - Base - Ramp O | 30-May-17 |
PRE-FA-033 | Fabricate and Deliver 101400 Signage | 30-May-17 |
IIBEBO-ST450 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 31-May-17 |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 31-May-17 |
IIIAWBO-ST520 | PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 31-May-17 |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 02-Jun-17 |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 06-Jun-17 |
IIBEBO-ST420 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 08-Jun-17 |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 09-Jun-17 |
IIIBR-GC190 | PH IIIB - Demo - Ramp K | 12-Jun-17 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 15-Jun-17 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 15-Jun-17 |
IIBEBO-ST360 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 |
IIBEBO-ST730 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 16-Jun-17 |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 16-Jun-17 |
TF-CO-001 | Foundation (FRP SOG) | 19-Jun-17 |
TF-CO-013 | Const. Screen Wall (Con.) | 20-Jun-17 |
PRE-FA-030 | Fabricate and Deliver 042200 Masonry | 20-Jun-17 |
PRE-RA-030 | Review and Approve 042200 Masonry | 20-Jun-17 |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 21-Jun-17 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 21-Jun-17 |
TF-CO-008 | Constr. Pedestal | 26-Jun-17 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 26-Jun-17 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 26-Jun-17 |
TF-CO-004 | Precast Erection | 27-Jun-17 |
TF-CO-006 | FRP Conc. Roof Dec/c | 27-Jun-17 |
TF-CO-009 | Const. Roof System | 27-Jun-17 |
TF-CO-012 | Install Frames & Doors | 27-Jun-17 |
TF-CO-015 | Install HVAC | 27-Jun-17 |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 27-Jun-17 |
IIIBWBO-ST300 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 27-Jun-17 |
IIIBWBO-ST240 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IIIBWBO-ST260 | PH IIIB - Wall Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 05-Jul-17 |
IIIBWBO-ST220 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 05-Jul-17 |
IIIBWBO-ST640 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over universal BLVD) | 05-Jul-17 |
IICR-SP120 | PH IIC - Drainage - Ramp M | 08-Jul-17 |
IIIBWBO-ST330 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 08-Jul-17 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 10-Jul-17 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 10-Jul-17 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 11-Jul-17 |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 12-Jul-17 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 13-Jul-17 |
IIBR-RW250 | PH IIB - Base - Ramp L | 17-Jul-17 |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 17-Jul-17 |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 17-Jul-17 |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 17-Jul-17 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 17-Jul-17 |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 17-Jul-17 |
IIIBR-SP100 | PH IIIB - Drainage (Temp) - Ramp G | 17-Jul-17 |
IIBEBO-ST480 | PH IIB - Set Beams - EB Outside Widening (Bridge over Universal BLVD) | 17-Jul-17 |
IIIBWBO-ST340 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Universal BLVD) | 18-Jul-17 |
IIBEBO-ST500 | PH IIB - Superstructure Deck SIP / Overhangs / Edges - EB Outside Widening (Bridge over Universal BLVD) | 21-Jul-17 |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 21-Jul-17 |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 24-Jul-17 |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 24-Jul-17 |
IIBR-RW170 | PH IIB - Base - Ramp I-1 | 26-Jul-17 |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 28-Jul-17 |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 31-Jul-17 |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 31-Jul-17 |
IIIAWBO-ST570 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 02-Aug-17 |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 07-Aug-17 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 08-Aug-17 |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 10-Aug-17 |
IIBR-RW130 | PH IIB - Base - Ramp E | 10-Aug-17 |
TF-CO-010 | FRP Conc. Pad (Generator) | 14-Aug-17 |
TF-CO-022 | Construct Sidewalk | 14-Aug-17 |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 14-Aug-17 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 14-Aug-17 |
IIBEBO-ST520 | PH IIB - Superstructure Deck Rebar - EB Outside Widening (Bridge over Universal BLVD) | 14-Aug-17 |
IIIAWBO-ST120 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 14-Aug-17 |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 16-Aug-17 |
IIBEBO-ST550 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over universal BLVD) | 16-Aug-17 |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 16-Aug-17 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 16-Aug-17 |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 17-Aug-17 |
IIIAWBO-ST590 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 17-Aug-17 |
IIBR-AP170 | PH IIB - Asphalt - Structural - Ramp L | 21-Aug-17 |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 21-Aug-17 |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 21-Aug-17 |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 21-Aug-17 |
IIIAWBO-ST111 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Aug-17 |
IIIAWBO-ST140 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Aug-17 |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 21-Aug-17 |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 22-Aug-17 |
IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L | 23-Aug-17 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 23-Aug-17 |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 23-Aug-17 |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 23-Aug-17 |
IIBEBO-ST530 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over universal BLVD) | 24-Aug-17 |
IIIAWBO-ST130 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 25-Aug-17 |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 28-Aug-17 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 28-Aug-17 |
IICR-EW120 | PH IIC - Embankment - Ramp M | 28-Aug-17 |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 29-Aug-17 |
GC-GCN180 | PH MS - Start Phase III C Construction | 29-Aug-17 |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 29-Aug-17 |
IIIAWBO-ST170 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 30-Aug-17 |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 01-Sep-17 |
IIIBR-SP120 | PH IIIB - Drainage (Temp) - Ramp V | 17-Sep-17 |
IIIBR-SP130 | PH IIIB - Drainage (Temp) - Ramp K | 17-Sep-17 |
IIIBR-TC160 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp J | 17-Sep-17 |
IIIBR-TC200 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp K | 17-Sep-17 |
IIBR-EW150 | PH IIB - Embankment - Ramp I-1 | 18-Sep-17 |
IIBR-GC140 | PH IIB - Demo - Ramp I-1 | 18-Sep-17 |
IIIAWBO-ST600 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 23-Sep-17 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 25-Sep-17 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 29-Sep-17 |
IIBEBO-ST560 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over universal BLVD) | 30-Sep-17 |
IIIBR-RW140 | PH IIIB - Stabilization - Ramp V | 02-Oct-17 |
IIBR-RW190 | PH IIB - Base - Ramp H | 03-Oct-17 |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 03-Oct-17 |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 04-Oct-17 |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 04-Oct-17 |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 05-Oct-17 |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 05-Oct-17 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 09-Oct-17 |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 10-Oct-17 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 11-Oct-17 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 11-Oct-17 |
IIIAWBO-AP100 | PH IIIA - Mill & Resurface (sacrificial) - WB Outside Widening Area (SR528) | 11-Oct-17 |
IIIAWBO-TC100 | PH IIIA - Install Sign & Traffic Control Devices - WB Outside Widening Area | 11-Oct-17 |
IIIAWBO-TC110 | PH IIIA - Temp Striping for Phase - WB Outside Widening Area (SR528) | 11-Oct-17 |
IIIAWBO-TC120 | PH IIIA - MOT Shift for Phase - WB Outside Widening Area | 11-Oct-17 |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 11-Oct-17 |
IIBR-GC170 | PH IIB - Demo - Ramp C | 12-Oct-17 |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 12-Oct-17 |
IIIBWBO-ST460 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over universal BLVD) | 12-Oct-17 |
IIBR-RW290 | PH IIB - Shoulder Gutter - Ramp C | 15-Oct-17 |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 16-Oct-17 |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 16-Oct-17 |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 16-Oct-17 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 16-Oct-17 |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 16-Oct-17 |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 18-Oct-17 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 20-Oct-17 |
IIIBWBO-ST470 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over universal BLVD) | 20-Oct-17 |
IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V | 23-Oct-17 |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 23-Oct-17 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Oct-17 |
IICR-TC210 | PH IIC - MOT Shift New Ramp Alignment - Ramp U | 24-Oct-17 |
IIICWBO-ST220 | PH IIIA - Demo Bridge Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 25-Oct-17 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 29-Oct-17 |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 30-Oct-17 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 30-Oct-17 |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 31-Oct-17 |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 01-Nov-17 |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 01-Nov-17 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 01-Nov-17 |
IIIBR-RW130 | PH IIIB - Base - Ramp J | 02-Nov-17 |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 02-Nov-17 |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 06-Nov-17 |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 06-Nov-17 |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 06-Nov-17 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 06-Nov-17 |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 07-Nov-17 |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 08-Nov-17 |
IIIBR-TC120 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp G | 08-Nov-17 |
IIIBR-TC130 | PH IIIB - Temp Striping New Ramp Alignment - Ramp G | 09-Nov-17 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 09-Nov-17 |
IIIC-CP10 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 12-Nov-17 |
TF-CO-014 | Pull Wire & Install Light Fixtures | 12-Nov-17 |
TF-CO-018 | Install Lighting | 12-Nov-17 |
TF-CO-019 | Install Security System | 12-Nov-17 |
TF-CO-020 | Install Lightning Protection | 12-Nov-17 |
TF-CO-024 | Wall Treatments (Ply) | 12-Nov-17 |
IIBR-GC390 | PH IIB - Guardrail (Roadway) - Ramp R | 12-Nov-17 |
TF-CO-016 | F+1 Generator | 13-Nov-17 |
TF-CO-017 | F+1 Fuel Tank | 13-Nov-17 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 13-Nov-17 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 13-Nov-17 |
IIIBR-GC140 | PH IIIB - Demo - Ramp J | 13-Nov-17 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 13-Nov-17 |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 13-Nov-17 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 13-Nov-17 |
IIIBWBO-W101 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over Universal BLVD) | 13-Nov-17 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 13-Nov-17 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 13-Nov-17 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 15-Nov-17 |
IIBR-RW160 | PH IIB - Base - Ramp C | 20-Nov-17 |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 27-Nov-17 |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 27-Nov-17 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 27-Nov-17 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 27-Nov-17 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 27-Nov-17 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 29-Nov-17 |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 02-Dec-17 |
TF-CO-023 | Erect Truss | 04-Dec-17 |
TF-CO-025 | Install Equip. Arm Supports | 04-Dec-17 |
TF-CO-029 | Install Conduit/Raceways | 04-Dec-17 |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 04-Dec-17 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 04-Dec-17 |
IIBEBO-ST200 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over International DR) | 05-Dec-17 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 05-Dec-17 |
IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H | 06-Dec-17 |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 06-Dec-17 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 06-Dec-17 |
GC-GCN190 | PH MS - Start Phase II D Construction | 07-Dec-17 |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 07-Dec-17 |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 07-Dec-17 |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 08-Dec-17 |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 11-Dec-17 |
IICR-TC170 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp S-2 | 13-Dec-17 |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Dec-17 |
IICR-TC160 | PH IIC - Temp Striping New Ramp Alignment - Ramp S-2 | 16-Dec-17 |
IICR-GC100 | PH IIC - Demo - Ramp S-2 | 18-Dec-17 |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 18-Dec-17 |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 20-Dec-17 |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 |
IIBR-GC220 | PH IIB - Guardrail (Roadway) - Ramp E | 08-Jan-18 |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 08-Jan-18 |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 08-Jan-18 |
IIIAWBO-ST181 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge over John Young PKWY) | 08-Jan-18 |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 10-Jan-18 |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 10-Jan-18 |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 10-Jan-18 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 11-Jan-18 |
IIIBR-TC170 | PH IIIB - Temp Striping New Ramp Alignment - Ramp J | 14-Jan-18 |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 16-Jan-18 |
IICR-TC1020 | PH IIC - Temp Striping New Ramp Alignment - Ramp M | 18-Jan-18 |
IIIBR-SP160 | PH IIIB - Drainage (Temp) - Ramp Q | 21-Jan-18 |
TF-CO-026 | Cont. Lightning | 22-Jan-18 |
TF-CO-027 | Cont. HVAC | 22-Jan-18 |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 22-Jan-18 |
IIBR-SP210 | PH IIB - Drainage - Ramp D | 23-Jan-18 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 29-Jan-18 |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 29-Jan-18 |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 29-Jan-18 |
IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 31-Jan-18 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 01-Feb-18 |
IICR-GC170 | PH IIC - Demo - Ramp M | 05-Feb-18 |
IIBEBO-ST250 | PH IIB - Set Beams - EB Outside Widening (Bridge over International Drive) | 05-Feb-18 |
IIIAWBO-ST150 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge over John Young PKWY) | 05-Feb-18 |
IIICR-GC110 | PH IIIC - Demo - Ramp N | 06-Feb-18 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 06-Feb-18 |
IIBEBO-ST270 | PH IIB - Superstructure Deck - EB Outside Widening (Bridge over International Drive) | 07-Feb-18 |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 07-Feb-18 |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 08-Feb-18 |
IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 09-Feb-18 |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 12-Feb-18 |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 12-Feb-18 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 15-Feb-18 |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 19-Feb-18 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 20-Feb-18 |
IIIBWBO-ST320 | PH IIIB - Curing for Pier 2, 3, (Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Feb-18 |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 26-Feb-18 |
IIDEBO-ST230 | PH IID - Set Beams - EB Outside Widening (Bridge over John Young PKWY) | 27-Feb-18 |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 28-Feb-18 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 28-Feb-18 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 01-Mar-18 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 01-Mar-18 |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 02-Mar-18 |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 02-Mar-18 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 02-Mar-18 |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 05-Mar-18 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 05-Mar-18 |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 05-Mar-18 |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 05-Mar-18 |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 06-Mar-18 |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 12-Mar-18 |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 14-Mar-18 |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 18-Mar-18 |
IIIBR-TC270 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp Q | 18-Mar-18 |
IIIBR-TC280 | PH IIIB - Temp Striping New Ramp Alignment - Ramp Q | 18-Mar-18 |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 18-Mar-18 |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 19-Mar-18 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 19-Mar-18 |
IIICR-TC140 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp N | 19-Mar-18 |
IIICR-TC150 | PH IIIC - Temp Striping New Ramp Alignment - Ramp N | 19-Mar-18 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 20-Mar-18 |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 21-Mar-18 |
IIBEBO-ST380 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over International DR) | 21-Mar-18 |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 22-Mar-18 |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 22-Mar-18 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Mar-18 |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 27-Mar-18 |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 27-Mar-18 |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 28-Mar-18 |
IIBR-SP100 | PH IIB - Drainage - Ramp B | 29-Mar-18 |
IIBR-EW210 | PH IIB - Embankment - Ramp D | 30-Mar-18 |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 30-Mar-18 |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 30-Mar-18 |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 30-Mar-18 |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 02-Apr-18 |
IIBR-RW320 | PH IIB - Stabilization - Ramp D | 02-Apr-18 |
IIIBR-GC260 | PH IIIB - Guardrail (Roadway) - Ramp K | 02-Apr-18 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 02-Apr-18 |
IICR-RW140 | PH IIC - Base - Ramp M | 03-Apr-18 |
IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J | 03-Apr-18 |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | 04-Apr-18 |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 04-Apr-18 |
GC-GCN160 | PH MS - Start Phase IV Construction | 05-Apr-18 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 05-Apr-18 |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 05-Apr-18 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 06-Apr-18 |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 06-Apr-18 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 09-Apr-18 |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 09-Apr-18 |
IIICR-RW130 | PH IIIC - Base - Ramp N | 09-Apr-18 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 09-Apr-18 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 10-Apr-18 |
IIIAWBO-ST191 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge over John Young PKWY) | 11-Apr-18 |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 12-Apr-18 |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 17-Apr-18 |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 23-Apr-18 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 23-Apr-18 |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 24-Apr-18 |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 25-Apr-18 |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 25-Apr-18 |
IIIBR-GC250 | PH IIIB - Demo - Ramp P | 27-Apr-18 |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 27-Apr-18 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 30-Apr-18 |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 30-Apr-18 |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 01-May-18 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 01-May-18 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 01-May-18 |
IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 03-May-18 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 06-May-18 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 07-May-18 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 07-May-18 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 10-May-18 |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 10-May-18 |
IVR-EC30 | PH IV - Erect Cantilevers (10-15) | 13-May-18 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 14-May-18 |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 17-May-18 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 21-May-18 |
IIIBR-SP150 | PH IIIB - Drainage - Ramp P | 21-May-18 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 21-May-18 |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 22-May-18 |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 22-May-18 |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 23-May-18 |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 23-May-18 |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 24-May-18 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 24-May-18 |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 29-May-18 |
IIICR-RW110 | PH IIIC - Base - Ramp F | 29-May-18 |
IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 29-May-18 |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 02-Jun-18 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 03-Jun-18 |
IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Jun-18 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Jun-18 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 05-Jun-18 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 05-Jun-18 |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 07-Jun-18 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 08-Jun-18 |
IIIBWBO-ST390 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over International Drive) | 02-Jul-18 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 03-Jul-18 |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jul-18 |
IIIBWBO-ST690 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over International Drive) | 08-Jul-18 |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 10-Jul-18 |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 12-Jul-18 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 17-Jul-18 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 17-Jul-18 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 30-Jul-18 |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 31-Jul-18 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 02-Aug-18 |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 13-Aug-18 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 15-Aug-18 |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 20-Aug-18 |
IIBR-GC260 | PH IIB - Guardrail (Roadway) - Ramp I-1 | 20-Aug-18 |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 20-Aug-18 |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 20-Aug-18 |
IVEBM-W180 | PH IV - Median Wall - FFP Stem - Station 259+50 to 311 | 20-Aug-18 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 20-Aug-18 |
IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) | 20-Aug-18 |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 27-Aug-18 |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 29-Aug-18 |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 31-Aug-18 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 31-Aug-18 |
IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express | 05-Sep-18 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 07-Sep-18 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 10-Sep-18 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 10-Sep-18 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 10-Sep-18 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 10-Sep-18 |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 11-Sep-18 |
IIDEBO-ST270 | PH IID - Lighting Conduit - EB Outside Widening (Bridge over John Young PKWY) | 13-Sep-18 |
IIIBWBO-ST530 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over International DR) | 13-Sep-18 |
TF-CO-030 | Pull Wire | 17-Sep-18 |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 17-Sep-18 |
IIBR-TC170 | PH IIB - Temp Striping for New Ramp Alignment - Ramp B | 17-Sep-18 |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 17-Sep-18 |
IIIBWBO-ST540 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over International DR) | 17-Sep-18 |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 24-Sep-18 |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 24-Sep-18 |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 24-Sep-18 |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 26-Sep-18 |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 26-Sep-18 |
IBR-EW100 | PH IB - Embankment - Ramp B/C Gore | 08-Oct-18 |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 08-Oct-18 |
IBR-RW100 | PH IB - Stabilization - Ramp B/C Gore | 15-Oct-18 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 15-Oct-18 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 15-Oct-18 |
TF-CO-031 | Toll Facility Finishes and Punchlist | 19-Oct-18 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 22-Oct-18 |
The following actual finish dates were added in E8P02 Update No 36
Activity ID | Activity Description | Actual Finish |
---|---|---|
GC-GCN100 | PH MS - Construction Mobilization | 03-Sep-15 |
PRE-PS-003 | Prepare and Submit 455 Pile Installation Plan (Structures 750091 & 750218-John Young Parkway) | 26-Sep-15 |
PRE-PS-004 | Prepare and Submit 455 Pile Installation Plan (Structure 750629- Ramp S JYP) | 26-Sep-15 |
PRE-PS-005 | Prepare and Submit 455 Pile Installation Plan (Structure 750630- Ramp T JYP) | 26-Sep-15 |
IBEBM-ST100 | PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek) | 13-Nov-15 |
GC-GCN120 | PH MS - Start Phase IB Construction | 20-Nov-15 |
PRE-RA-013 | Review and Approve 455 Auger Cast Piles (w/noise wall submittal) | 12-Dec-15 |
USV-CO-001 | Verizon | 15-Dec-15 |
UST-CO-001 | TECO | 16-Dec-15 |
IBEBM-ST240 | PH IB - Construct Crane Access - EB Median Widening (Bridge over universal BLVD) | 22-Feb-16 |
IBWBM-ST160 | PH IB - Construct Crane Access - WB Median Widening (Bridge over universal BLVD) | 23-Feb-16 |
IBWBM-GC100 | PH IB - Median Clearing and Grubbing - WB Median Widening | 24-Feb-16 |
IAEBO-GC130 | PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H) | 26-Feb-16 |
IBEBM-ST110 | PH IB - DemoTraffic Rail / End Bents - EB Median Widening (Bridge over Shingle Creek) | 26-Feb-16 |
PRE-PS-007 | Prepare and Submit 400 Concrete Structures (Bearing Pads) | 02-Mar-16 |
IBEBM-ST390 | PH IB - Curing for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | 02-Mar-16 |
IIDEBO-ST100 | PH IID - Construct Crane Access - EB Outside Widening (Bridge over John Young PKWY) | 02-Mar-16 |
IBEBM-ST950 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over John Young PKWY) | 03-Mar-16 |
IBWBM-ST720 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over John Young PKWY) | 03-Mar-16 |
IBWBM-SP140 | PH IB - Drainage for STA 390 to TPK | 04-Mar-16 |
IBWBO-SP130 | PH IB - Jack & Bore JYP to TPK (East of Sta 354+04 to 415+33) | 04-Mar-16 |
PRE-RA-007 | Review and Approve 400 Concrete Structures (Bearing Pads) | 09-Mar-16 |
PRE-FA-00123 | Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 18" (Structures 750089 & 750216) | 10-Mar-16 |
IAEBO-W100 | PH IA - Noise/Sound Wall Prep Work (W-1) - EB Outside Widening | 15-Mar-16 |
IAEBO-W130 | PH IA - Noise/Sound Wall Prep Work (W-2) - EB Outside Widening | 18-Mar-16 |
IBEBM-ST140 | PH IB - Construct Crane Access - EB Median Widening (Bridge over International DR) | 18-Mar-16 |
IBWBM-ST110 | PH IB - Construct Crane Access - WB Median Widening (Bridge over International DR) | 18-Mar-16 |
PRE-PS-050 | Prepare and Submit 400 Concrete Structures (SIP Metal Forms) | 22-Mar-16 |
PRE-RA-050 | Review and Approve 400 Concrete Structures (SIP Metal Forms) | 30-Mar-16 |
IBEBM-ST270 | PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD) | 31-Mar-16 |
IIIAWBO-ST27 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over John Young PKWY) | 06-Apr-16 |
IBWBM-ST130 | PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR) | 13-Apr-16 |
IIIAWBO-ST18 | PH IIIA - Production Pile (H Piles) (1-32) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Apr-16 |
IIBEBO-ST22 | PH IIB - Production Pile (H Piles) (1-31) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 18-Apr-16 |
PRE-FA-0111 | Fabricate and Deliver 455 Temp Sheet Pile/Critical | 18-Apr-16 |
PRE-FA-00145 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 14X89 (Structures 750088 and 750215 I-Drive) | 18-Apr-16 |
USDED-CO-001 | Duke Energy Distribution (A) | 18-Apr-16 |
IBEBM-ST190 | PH IB - Production Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek) | 22-Apr-16 |
PRE-FA-013 | Fabricate and Deliver 455 Auger Cast Piles (w/noise wall submittal) | 29-Apr-16 |
PRE-FA-014 | Fabricate and Deliver 534 Noise and Perimeter Walls | 29-Apr-16 |
PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) | 04-May-16 |
PRE-FA-007 | Fabricate and Deliver 400 Concrete Structures (Bearing Pads) | 06-May-16 |
IBEBM-ST710 | PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD) | 06-May-16 |
IBWBM-ST570 | PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD) | 06-May-16 |
IAEBO-W110 | PH IA - Install Posts (1-101)- EB Outside Widening | 09-May-16 |
IBEBM-ST700 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over universal BLVD) | 10-May-16 |
IBWBM-ST550 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over universal BLVD) | 10-May-16 |
IBEBM-ST230 | PH IB - Production Pile - EB Median Widening (Bridge over International DR) | 11-May-16 |
IBWBM-ST150 | PH IB - Production Pile - WB Median Widening (Bridge over International DR) | 11-May-16 |
IBEBM-ST410 | PH IB - End Bent 3 - EB Median Widening (Bridge over International DR) | 12-May-16 |
IBWBM-ST330 | PH IB - End Bent 3 - WB Median Widening (Bridge over International DR) | 12-May-16 |
PRE-PS-020 | Prepare and Submit 992 Under deck Lighting | 13-May-16 |
IBEBM-ST370 | PH IB - End Bent 1 - EB Median Widening (Bridge over International DR) | 13-May-16 |
IBWBM-ST290 | PH IB - End Bent 1 - WB Median Widening (Bridge over International DR) | 13-May-16 |
IBEBM-ST430 | PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek) | 16-May-16 |
IBEBM-ST330 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR) | 17-May-16 |
IBEBM-ST970 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over universal BLVD) | 17-May-16 |
IBWBM-ST280 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR) | 17-May-16 |
IAEBO-W120 | PH IA - Install Posts (102- 203) - EB Outside Widening | 18-May-16 |
IBEBM-ST200 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over International DR) | 18-May-16 |
IBEBM-ST530 | PH IB - End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | 18-May-16 |
IBWBM-ST140 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over International DR) | 18-May-16 |
IBEBM-ST380 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR) | 19-May-16 |
IBEBM-ST420 | PH IB - Curing for End Bent 3 - EB Median Widening (Bridge over International DR) | 19-May-16 |
IBWBM-ST320 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR) | 19-May-16 |
IBWBM-ST750 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over International DR) | 19-May-16 |
IBEBM-ST980 | PH IB - Curing for End Bent 4 - EB Median Widening (Bridge over Shingle Creek) | 22-May-16 |
PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | 23-May-16 |
PRE-RA-020 | Review and Approve 992 Under deck Lighting | 23-May-16 |
IBWBM-ST760 | PH IB - Curing for End Bent 3 - WB Median Widening (Bridge over universal BLVD) | 23-May-16 |
IAEBO-W140 | PH IA - Install Posts (204-305) - EB Outside Widening | 26-May-16 |
IAEBO-IL100 | PH IA - Temp. ITS Relocate Existing - EB Outside Widening (SR528) | 10-Jun-16 |
IBEBM-ST260 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD) | 10-Jun-16 |
IBEBM-ST850 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD) | 10-Jun-16 |
IBEBM-ST900 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD) | 10-Jun-16 |
IBWBM-ST180 | PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD) | 10-Jun-16 |
IBWBM-ST710 | PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD) | 10-Jun-16 |
IIBEBO-ST3 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over International DR) | 13-Jun-16 |
IIBR-SP121 | PH IIB - Drainage - Ramp A | 13-Jun-16 |
IAEBO-W150 | PH IA - Install Posts (306- 409) - EB Outside Widening | 14-Jun-16 |
IIBR-GC171 | PH IIB - Clear & Grub/Demo - Ramp A | 15-Jun-16 |
IIBR-EW122 | PH IIB - Embankment - Ramp A | 21-Jun-16 |
IBEBM-ST210 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over John Young PKWY) | 21-Jun-16 |
IBEBM-ST560 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over International DR) | 24-Jun-16 |
IBWBM-ST400 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR) | 24-Jun-16 |
IAEBO-W160 | PH IA - Install Panels (0-32000 SF) - EB Outside Widening | 29-Jun-16 |
IBWBM-ST200 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD) | 01-Jul-16 |
IAEBO-W170 | PH IA - Install Panels (32000-64000 SF) - EB Outside Widening | 05-Jul-16 |
IAEBO-W180 | PH IA - Install Panels (64000-96000 SF)- EB Outside Widening | 08-Jul-16 |
IBEBM-W140 | PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528) | 08-Jul-16 |
IBWBM-W140 | PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528) | 08-Jul-16 |
IAEBO-W190 | PH IA - Install Panels (96000-128000 SF)- EB Outside Widening | 12-Jul-16 |
IIIAWBO-ST30 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY) | 12-Jul-16 |
IIAR-SP100 | PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp O | 13-Jul-16 |
IIBR-RW141 | PH IIB - Stabilization - Ramp A | 13-Jul-16 |
IAEBO-SP100 | PH IA - Jack & Bore 42" (Sta 351+00 near Duke energy access platform) - EB Outside Widening (SR528) | 13-Jul-16 |
IBWBM-ST250 | PH IB - Test Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | 13-Jul-16 |
IIBEBO-ST21 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 14-Jul-16 |
IBEBM-ST220 | PH IB - Drive Production Pile (H Piles) - EB Median Widening (Bridge over John Young PKWY) | 15-Jul-16 |
IBWBM-ST310 | PH IB - Production Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | 15-Jul-16 |
IIDEBO-ST120 | PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY) | 15-Jul-16 |
IIBEBO-ST1 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over International DR) | 18-Jul-16 |
IBEBM-TC110 | PH IB - Set Temp Traffic Barriers for Phase IIA - EB Median Widening | 18-Jul-16 |
IBEBM-TC130 | PH IB - Temp Striping for Phase IIA - EB Median Widening | 18-Jul-16 |
IBWBM-RW240 | PH IB - Pavement for Permanent Shoulder Construction (Universal-International Drv.) - WB Median Widening | 18-Jul-16 |
IBWBM-ST300 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over John Young PKWY) | 18-Jul-16 |
IIIBWBO-ST1 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over International DR) | 18-Jul-16 |
IIIBWBO-ST3 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR) | 18-Jul-16 |
IIIAWBO-ST16 | PH IIIA - Test Pile (H Piles) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 18-Jul-16 |
IBEBM-ST520 | PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
IBEBM-ST570 | PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
IBEBM-ST800 | PH IB - Approach Slabs - EB Median Widening (Bridge over Shingle Creek) | 22-Jul-16 |
IBWBM-ST490 | PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
IBWBM-ST530 | PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 22-Jul-16 |
PRE-PS-044 | Prepare and Submit 783 ITS Fiber Optic Cable | 26-Jul-16 |
IBEBM-ST320 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over International DR) | 26-Jul-16 |
IBWBM-ST270 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over International DR) | 26-Jul-16 |
IBEBM-W130 | PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528) | 27-Jul-16 |
IBWBM-W120 | PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528) | 27-Jul-16 |
IIBEBO-ST8 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over International DR) | 27-Jul-16 |
IBEBM-ST640 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over universal BLVD) | 27-Jul-16 |
IBWBM-ST510 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over universal BLVD) | 27-Jul-16 |
IBEBM-ST480 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY) | 28-Jul-16 |
IBWBM-ST450 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY) | 28-Jul-16 |
IBWBO-SP140 | PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50) | 28-Jul-16 |
IIIBWBO-ST9 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over International DR) | 28-Jul-16 |
IAEBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - EB Outside Widening (SR528) | 29-Jul-16 |
IBEBM-ST150 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR) | 29-Jul-16 |
IBEBM-ST280 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD) | 29-Jul-16 |
IBEBM-ST720 | PH IB - Curing for End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 29-Jul-16 |
IBEBM-ST890 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR) | 29-Jul-16 |
IBWBM-ST120 | PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR) | 29-Jul-16 |
IBWBM-ST730 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR) | 29-Jul-16 |
IBWBM-ST740 | PH IB - Curing for End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 29-Jul-16 |
IIIAWBO-ST17 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 01-Aug-16 |
IIBR-RW151 | PH IIB - Base - Ramp A | 03-Aug-16 |
PRE-PS-046 | Prepare and Submit 684 ITS Managed Ethernet Hub Switch | 03-Aug-16 |
PRE-PS-047 | Prepare and Submit 785 ITS Uninterruptible Power Source (UPS) | 03-Aug-16 |
IBEBM-ST300 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | 03-Aug-16 |
IBWBM-ST220 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR) | 03-Aug-16 |
IBEBM-ST810 | PH IB - Grind and Groove - EB Median Widening (Bridge over Shingle Creek) | 04-Aug-16 |
IBEBM-ST510 | PH IB - End Bent 1 - EB Median Widening (Bridge over John Young PKWY) | 05-Aug-16 |
IBWBM-ST460 | PH IB - End Bent 1 - WB Median Widening (Bridge over John Young PKWY) | 05-Aug-16 |
IIBEBO-ST28 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek) | 05-Aug-16 |
IBEBM-ST990 | PH IB - Bolt/Pin Temp B/W - EB Median Widening (Bridge over Shingle Creek) | 08-Aug-16 |
PRE-PS-015 | Prepare and Submit 548 Retaining/MSE Wall Systems | 09-Aug-16 |
IBEBM-ST440 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | 09-Aug-16 |
IBEBM-ST490 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over John Young PKWY) | 09-Aug-16 |
IBWBM-ST370 | PH IB - Curing For Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY) | 09-Aug-16 |
IBWBM-ST420 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over John Young PKWY) | 09-Aug-16 |
IIDEBO-ST170 | PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY) | 10-Aug-16 |
IBEBM-ST610 | PH IB - Curing for Pier 2,(Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | 11-Aug-16 |
IBWBM-ST480 | PH IB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD) | 11-Aug-16 |
IAEBO-W200 | PH IA - Install Panels (128000-160000 SF) - EB Outside Widening | 12-Aug-16 |
IIBEBO-ST6 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR) | 12-Aug-16 |
IBWBM-ST190 | PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 12-Aug-16 |
IBWBM-ST210 | PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 12-Aug-16 |
IIBEBO-ST27 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 12-Aug-16 |
IIIAWBO-ST35 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over John Young PKWY) | 12-Aug-16 |
IIAR100 | PH IIA - Construct Ramp O Diversion - Ramp O | 15-Aug-16 |
IIIAWBO-ST23 | PH IIIA - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 15-Aug-16 |
PRE-FA-047 | Fabricate and Deliver 685 ITS Uninterruptible Power Source (UPS) | 16-Aug-16 |
PRE-RA-046 | Review and Approve 684 ITS Managed Ethernet Hub Switch | 16-Aug-16 |
PRE-RA-047 | Review and Approve 685 ITS Uninterruptible Power Source (UPS) | 16-Aug-16 |
IIIBWBO-ST6 | PH IIIB - Construct Crane Access - WB Outside Widening Area (Bridge over universal BLVD) | 16-Aug-16 |
IBEBM-ST290 | PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD) | 17-Aug-16 |
IBEBO-EW110 | PH IB - Pond Excav/Embank JYP to TPK - EB Outside Widening | 19-Aug-16 |
IIBEBO-ST9 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over universal BLVD) | 22-Aug-16 |
PRE-PS-042 | Prepare and Submit 781 DMS | 25-Aug-16 |
IBEBM-ST680 | PH IB - End Bent 1 - EB Median Widening (Bridge over universal BLVD) | 25-Aug-16 |
IBWBM-ST540 | PH IB - End Bent 1 - WB Median Widening (Bridge over universal BLVD) | 25-Aug-16 |
PRE-RA-015 | Review and Approve 548 Retaining/MSE Wall Systems | 31-Aug-16 |
IIAR-TC140 | PH IIA - Temp Striping New Ramp Alignment - Ramp O | 07-Sep-16 |
IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening | 07-Sep-16 |
IIAEBO-TC120 | PH IIA - MOT Shift for Phase IIA - EB Outside Widening | 07-Sep-16 |
IBEBM-ST650 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over universal BLVD) | 08-Sep-16 |
IBWBM-ST520 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over universal BLVD) | 08-Sep-16 |
IBEBO-GC100 | PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - EB Outside Widening | 09-Sep-16 |
IBWBO-GC100 | PH IB - Remove Existing Overhead Sign (sta 356+25) & Foundation - WB Outside Widening Area | 09-Sep-16 |
IBWBM-ST620 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over John Young PKWY) | 12-Sep-16 |
IIBR-GC191 | PH IIB - Performance Turf, SOD - Ramp A | 13-Sep-16 |
PRE-PS-025 | Prepare and Submit 635 Pull, Splice, & Junction Boxes | 13-Sep-16 |
IBR-IDS10 | PH IB - Install Drilled Shafts (1-13) | 14-Sep-16 |
PRE-PS-021 | Prepare and Submit 05500 Metal Fabrications | 16-Sep-16 |
PRE-RA-021 | Review and Approve 05500 Metal Fabrications | 16-Sep-16 |
IBEBM-ST740 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY) | 16-Sep-16 |
GC-GCN130 | PH MS - Start Phase IIA Construction | 19-Sep-16 |
IBEBO-EW170 | PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside Widening | 19-Sep-16 |
IIIBWBO-ST5 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR) | 20-Sep-16 |
IIDEBO-ST310 | PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 21-Sep-16 |
IIIAWBO-ST690 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 22-Sep-16 |
IIIAWBO-ST710 | PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 22-Sep-16 |
IIDEBO-ST160 | PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP) | 23-Sep-16 |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 27-Sep-16 |
IIDEBO-ST150 | PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 28-Sep-16 |
IIIAWBO-ST21 | PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 28-Sep-16 |
IIIAWBO-ST22 | PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T | 28-Sep-16 |
IIIAWBO-ST33 | PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 28-Sep-16 |
IIIAWBO-ST34 | PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John | 28-Sep-16 |
IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | 29-Sep-16 |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 02-Oct-16 |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 02-Oct-16 |
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 03-Oct-16 |
IIAEBO-TC100 | PH IIA - Install Sign & Traffic Control Devices - EB Outside Widening | 03-Oct-16 |
GC-GCN140 | PH MS - Start Phase II B Construction | 04-Oct-16 |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 11-Oct-16 |
IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 |
IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | 12-Oct-16 |
IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | 12-Oct-16 |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 13-Oct-16 |
IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | 13-Oct-16 |
IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | 14-Oct-16 |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 18-Oct-16 |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 18-Oct-16 |
IIBEBO-ST11 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD) | 18-Oct-16 |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 20-Oct-16 |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 20-Oct-16 |
IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | 24-Oct-16 |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 26-Oct-16 |
PRE-PS-031 | Prepare and Submit 081100 Metal Doors and Frames | 26-Oct-16 |
PRE-PS-032 | Prepare and Submit 099100 Painting Product Data and Sample | 26-Oct-16 |
IBWBM-RW130 | PH IB - Grade (JYP-Universal) - WB Median Widening | 31-Oct-16 |
IIIBWBO-ST8 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD) | 31-Oct-16 |
IBWBM-SP110 | PH IB - Drainage for JYP to STA 390 | 02-Nov-16 |
IBWBM-RW140 | PH IB - Stabilization (JYP-Universal) - WB Median Widening | 03-Nov-16 |
IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | 09-Nov-16 |
IBWBM-RW150 | PH IB - Base (JYP-Universal) - WB Median Widening | 10-Nov-16 |
IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | 10-Nov-16 |
IAWBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528) | 11-Nov-16 |
PRE-RA-031 | Review and Approve 081100 Metal Doors and Frames | 15-Nov-16 |
IIBEBO-ST690 | PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 15-Nov-16 |
PRE-RA-032 | Review and Approve 099100 Painting Product Data and Sample | 16-Nov-16 |
IIBEBO-ST26 | PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ov | 17-Nov-16 |
IIBEBO-ST25 | PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 21-Nov-16 |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 06-Dec-16 |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 08-Dec-16 |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 09-Dec-16 |
IBWBM-RW160 | PH IB - Grade (Universal-International Drv.) - WB Median Widening | 14-Dec-16 |
IBWBM-RW170 | PH IB - Stabilization (Universal-International Drv.) - WB Median Widening | 14-Dec-16 |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 15-Dec-16 |
IBWBM-RW190 | PH IB - Grade (International Drive-I4) - WB Median Widening | 15-Dec-16 |
IBWBM-RW200 | PH IB - Stabilization (International Drv.-I4) - WB Median Widening | 15-Dec-16 |
IIBEBO-ST16 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 15-Dec-16 |
IIIBWBO-ST12 | PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 15-Dec-16 |
IIBEBO-ST17 | PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLV | 16-Dec-16 |
IIBEBO-ST18 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD) | 16-Dec-16 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 16-Dec-16 |
IIIBWBO-ST13 | PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Uni | 16-Dec-16 |
IIIBWBO-ST14 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD) | 16-Dec-16 |
IBR-AP120 | PH IB - Asphalt - Structural - Ramp C (Redundant) | 19-Dec-16 |
IBR-EW110 | PH IB - Embankment - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) | 19-Dec-16 |
IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C (Redundant) | 19-Dec-16 |
IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C (Redundant) | 19-Dec-16 |
IBR-RW120 | PH IB - Stabilization - Ramp C (Redundant) | 19-Dec-16 |
IBR-RW130 | PH IB - Base - Ramp C (Redundant) | 19-Dec-16 |
IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) | 19-Dec-16 |
IIBR-AP160 | PH IIB - Asphalt - Structural - Ramp I4- Interstate | 19-Dec-16 |
IIBR-EW180 | PH IIB - Embankment - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC300 | PH IIB - Demo - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 19-Dec-16 |
IIBR-GC400 | PH IIB - Guardrail (Roadway) - Ramp I4- Interstate | 19-Dec-16 |
IIBR-RW210 | PH IIB - Stabilization - Ramp I4- Interstate | 19-Dec-16 |
IIBR-RW230 | PH IIB - Base - Ramp I4- Interstate | 19-Dec-16 |
IIBR-SP180 | PH IIB - Drainage (Temp) - Ramp I4 Interstate | 19-Dec-16 |
IIBR-SP190 | PH IIB - Drainage (Temp) - Ramp L | 19-Dec-16 |
IIBR-SP200 | PH IIB - Drainage (Temp) - Ramp U | 19-Dec-16 |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 19-Dec-16 |
IIBR-TC360 | PH IIB - Temp Striping New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 |
IIBR-TC370 | PH IIB - MOT Shift New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 19-Dec-16 |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 19-Dec-16 |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 19-Dec-16 |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 10-Jan-17 |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 11-Jan-17 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 11-Jan-17 |
PRE-PS-006 | Prepare and Submit Precast Erection | 12-Jan-17 |
PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | 12-Jan-17 |
PRE-PS-038 | Prepare and Submit 238119 Packaged Air Conditioners | 12-Jan-17 |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 13-Jan-17 |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 16-Jan-17 |
IIBR-SP140 | PH IIB - Drainage (Temp) - Ramp S-1 | 16-Jan-17 |
IIBR-TC280 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1 | 16-Jan-17 |
IIBR-TC380 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp L | 16-Jan-17 |
IIBR-TC400 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp U | 16-Jan-17 |
IBEBO-EW120 | PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside Widening | 16-Jan-17 |
PRE-RA-038 | Review and Approve 238119 Packaged Air Conditioners | 17-Jan-17 |
IBEBM-ST550 | PH IB - Approach Slabs - EB Median Widening (Bridge over International DR) | 17-Jan-17 |
IBWBM-ST390 | PH IB - Approach Slabs - WB Median Widening (Bridge over International DR) | 17-Jan-17 |
IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-Jan-17 |
IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 17-Jan-17 |
IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | 18-Jan-17 |
PRE-PS-036 | Prepare and Submit 232000 Piping and Specialties | 18-Jan-17 |
PRE-PS-039 | Prepare and Submit 260536 Cable Trays | 18-Jan-17 |
IBEBM-RW270 | PH IB - Stabilization (Universal - JYP) - EB Median Widening | 18-Jan-17 |
PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | 19-Jan-17 |
IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | 20-Jan-17 |
IIBEBO-ST260 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 20-Jan-17 |
GC-GCN170 | PH MS - Start Phase III B Construction | 23-Jan-17 |
PRE-RA-001 | Review and Approve 506 Bridge Drainage System | 24-Jan-17 |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 24-Jan-17 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 24-Jan-17 |
PRE-RA-036 | Review and Approve 232000 Piping and Specialties | 25-Jan-17 |
IBEBM-ST840 | PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD) | 25-Jan-17 |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 25-Jan-17 |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 25-Jan-17 |
PRE-FA-036 | Fabricate and Deliver 232000 Piping and Specialties | 26-Jan-17 |
IBEBM-ST580 | PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR) | 26-Jan-17 |
IBWBM-ST430 | PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR) | 26-Jan-17 |
PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | 27-Jan-17 |
PRE-RA-025 | Review and Approve 635 Pull, Splice, & Junction Boxes | 27-Jan-17 |
IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 27-Jan-17 |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 30-Jan-17 |
TF-RA-001 | Review and Approve Precast Erection | 30-Jan-17 |
PRE-RA-022 | Review and Approve 133420 Pre-Engineered Precast Concrete Structure | 30-Jan-17 |
IBEBM-ST860 | PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD) | 30-Jan-17 |
IBWBM-ST650 | PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD) | 30-Jan-17 |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 30-Jan-17 |
IBWBM-ST680 | PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD) | 31-Jan-17 |
IIBEBO-ST150 | PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 31-Jan-17 |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 31-Jan-17 |
IIBR-SP160 | PH IIB - Drainage (Temp) - Ramp H | 01-Feb-17 |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 01-Feb-17 |
IBEBM-ST770 | PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY) | 01-Feb-17 |
IBWBM-ST630 | PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY) | 01-Feb-17 |
IIBEBO-ST120 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 01-Feb-17 |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 01-Feb-17 |
IIIBR120 | PH IIIB - Construct Ramp V Diversion - Ramp V | 02-Feb-17 |
IBEBM-RW230 | PH IB - Grade (International Drive - Universal) - EB Median Widening | 02-Feb-17 |
IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 03-Feb-17 |
IIBEBO-ST710 | PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 06-Feb-17 |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 07-Feb-17 |
IBEBM-RW220 | PH IB - Grade (I4-International Drive) - EB Median Widening | 08-Feb-17 |
IBEBM-RW260 | PH IB - Stabilization (International Drive - Universal) - EB Median Widening | 08-Feb-17 |
IBEBM-ST590 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR) | 08-Feb-17 |
IBWBM-ST440 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR) | 08-Feb-17 |
PRE-RA-039 | Review and Approve 260536 Cable Trays | 09-Feb-17 |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 10-Feb-17 |
IBEBM-ST870 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD) | 10-Feb-17 |
IBWBM-ST690 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD) | 10-Feb-17 |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 11-Feb-17 |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 15-Feb-17 |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 15-Feb-17 |
IBEBM-RW250 | PH IB - Stabilization (I4-international Drive) - EB Median Widening | 17-Feb-17 |
IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | 17-Feb-17 |
IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | 17-Feb-17 |
IIBEBO-ST280 | PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-Feb-17 |
IBEBM-ST600 | PH IB - Grind and Groove - EB Median Widening (Bridge over International DR) | 21-Feb-17 |
IBEBM-ST730 | PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY) | 21-Feb-17 |
IBWBM-ST470 | PH IB - Grind and Groove - WB Median Widening (Bridge over International DR) | 21-Feb-17 |
IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | 21-Feb-17 |
PRE-PS-041 | Prepare and Submit 682 CCTV Camera | 22-Feb-17 |
IBEBM-ST880 | PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD) | 22-Feb-17 |
IBWBM-ST700 | PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD) | 22-Feb-17 |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | 22-Feb-17 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 23-Feb-17 |
IIBR-TC300 | PH IIB - Temp Striping New Ramp Alignment - Ramp I-1 | 23-Feb-17 |
IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | 25-Feb-17 |
IIBR-TC310 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp H | 27-Feb-17 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 28-Feb-17 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 28-Feb-17 |
GC-GCN150 | PH MS - Start Phase II C Construction | 28-Feb-17 |
IIBR-TC220 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp E | 28-Feb-17 |
IIBR-TC230 | PH IIB - Temp Striping New Ramp Alignment - Ramp E | 28-Feb-17 |
IIBR-TC320 | PH IIB - Temp Striping New Ramp Alignment - Ramp H | 28-Feb-17 |
IIBR-TC390 | PH IIB - Temp Striping New Ramp Alignment - Ramp L | 28-Feb-17 |
IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | 28-Feb-17 |
PRE-RA-041 | Review and Approve 682 CCTV Camera | 01-Mar-17 |
IBEBM-ST790 | PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY) | 01-Mar-17 |
IBEBM-ST780 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY) | 04-Mar-17 |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 06-Mar-17 |
IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | 06-Mar-17 |
IIBR-EW110 | PH IIB - Embankment - Ramp E | 07-Mar-17 |
IIBR-GC110 | PH IIB - Demo - Ramp E | 07-Mar-17 |
IIBR-GC240 | PH IIB - Demo - Ramp H | 07-Mar-17 |
PRE-PS-019 | Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead) | 07-Mar-17 |
IBWBM-ST640 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY) | 07-Mar-17 |
IIBR-TC410 | PH IIB - Temp Striping New Ramp Alignment - Ramp U | 09-Mar-17 |
PRE-RA-044 | Review and Approve 633 ITS Fiber Optic Cable | 09-Mar-17 |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 09-Mar-17 |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 11-Mar-17 |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 11-Mar-17 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 13-Mar-17 |
IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | 13-Mar-17 |
IIBR-TC340 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2 | 13-Mar-17 |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 17-Mar-17 |
IIIBR-TC190 | PH IIIB - Temp Striping New Ramp Alignment - Ramp V | 17-Mar-17 |
IIIAWBO-ST230 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 17-Mar-17 |
IIBR-SP170 | PH IIB - Drainage (Temp) - Ramp R-2 | 20-Mar-17 |
IIBR-TC450 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp D | 20-Mar-17 |
IIBR-GC310 | PH IIB - Demo - Ramp L | 21-Mar-17 |
IIBR-GC130 | PH IIB - Demo - Ramp R-1 | 22-Mar-17 |
IIBR-GC290 | PH IIB - Demo - Ramp R-2 | 22-Mar-17 |
TF-CO-002 | Install Upright 1 D.S. | 23-Mar-17 |
PRE-PS-017 | Prepare and Submit 646 Aluminum Pedestal Poles | 23-Mar-17 |
PRE-PS-018 | Prepare and Submit 650 Traffic Signals | 23-Mar-17 |
PRE-PS-026 | Prepare and Submit 653 Pedestrian Signals | 23-Mar-17 |
PRE-PS-028 | Prepare and Submit 665 Pedestrian Detector | 23-Mar-17 |
IIIAWBO-ST200 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 23-Mar-17 |
TF-CO-005 | Install Upright 2 D.S. | 24-Mar-17 |
IIBR-EW200 | PH IIB - Embankment - Ramp U | 24-Mar-17 |
TF-CO-007 | Install Upright 3 D.S. | 28-Mar-17 |
PRE-PS-016 | Prepare and Submit 641 Prestressed Concrete Poles | 28-Mar-17 |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 28-Mar-17 |
PRE-PS-040 | Prepare and Submit 264113 Lighting Protection System Product Data and Shop Drawing | 28-Mar-17 |
PRE-PS-049 | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing | 28-Mar-17 |
PRE-RA-049 | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing | 28-Mar-17 |
PRE-PS-033 | Prepare and Submit 101400 Signage | 29-Mar-17 |
PRE-PS-045 | Prepare and Submit 660 ITS Vehicle Detection System | 29-Mar-17 |
IIIBR-GC180 | PH IIIB - Demo - Ramp V | 29-Mar-17 |
GC-GCN200 | PH MS - Start Phase III A Construction | 30-Mar-17 |
IIBR-GC350 | PH IIB - Demo - Ramp U | 30-Mar-17 |
IIAEBO-AP100 | PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 30-Mar-17 |
TF-CO-011 | AS Build D.S. | 31-Mar-17 |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 31-Mar-17 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 03-Apr-17 |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 05-Apr-17 |
IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 05-Apr-17 |
PRE-RA-017 | Review and Approve 646 Aluminum Pedestal Poles | 06-Apr-17 |
PRE-RA-018 | Review and Approve 650 Traffic Signals | 06-Apr-17 |
PRE-RA-026 | Review and Approve 653 Pedestrian Signals | 06-Apr-17 |
PRE-RA-028 | Review and Approve 665 Pedestrian Detector | 06-Apr-17 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 06-Apr-17 |
IIBR-EW190 | PH IIB - Embankment - Ramp L | 07-Apr-17 |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 07-Apr-17 |
IIBR-TC440 | PH IIB - Temp Striping New Ramp Alignment - Ramp D | 11-Apr-17 |
IIBR-SP120 | PH IIB - Drainage (Temp) - Ramp R-1 | 12-Apr-17 |
IIBEBO-ST320 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD) | 12-Apr-17 |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 13-Apr-17 |
IIIAWBO-ST330 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Apr-17 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 14-Apr-17 |
PRE-RA-033 | Review and Approve 101400 Signage | 14-Apr-17 |
IIBEBO-ST130 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR) | 14-Apr-17 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 14-Apr-17 |
IIBR-TC250 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp C | 16-Apr-17 |
PRE-RA-040 | Review and Approve 264113 Lighting Protection System Product Data and Shop Drawing | 19-Apr-17 |
IIIAWBO-ST290 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 19-Apr-17 |
IIIBR-TC180 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp V | 20-Apr-17 |
IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | 21-Apr-17 |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 21-Apr-17 |
IIBEBO-ST600 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek) | 21-Apr-17 |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 24-Apr-17 |
IIIBR130 | PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp K | 25-Apr-17 |
IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | 25-Apr-17 |
IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | 25-Apr-17 |
PRE-RA-016 | Review and Approve 641 Prestressed Concrete Poles | 25-Apr-17 |
IIBEBO-ST610 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek) | 25-Apr-17 |
IIIAWBO-ST340 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 26-Apr-17 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 27-Apr-17 |
IIAR-EW100 | PH IIB - Embankment - Ramp O | 28-Apr-17 |
PRE-RA-019 | Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead) | 01-May-17 |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 01-May-17 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 01-May-17 |
IIIBR-TC210 | PH IIIB - Temp Striping New Ramp Alignment - Ramp K | 02-May-17 |
IIAR-SP110 | PH IIB - Drainage - Ramp O | 03-May-17 |
IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | 04-May-17 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 04-May-17 |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 04-May-17 |
PRE-RA-034 | Review and Approve 231113 Fuel Oil Piping | 05-May-17 |
PRE-RA-035 | Review and Approve 231323 Aboveground Diesel Storage Tank and Piping | 05-May-17 |
PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals | 08-May-17 |
PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector | 08-May-17 |
PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | 08-May-17 |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 09-May-17 |
IIBEBO-ST430 | PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10-May-17 |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 10-May-17 |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 11-May-17 |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 11-May-17 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 11-May-17 |
IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | 11-May-17 |
IIIAWBO-ST410 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 11-May-17 |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 12-May-17 |
PRE-PS-024 | Prepare and Submit 633 Communication Cable | 15-May-17 |
PRE-RA-042 | Review and Approve 781 DMS | 18-May-17 |
IIBEBO-ST460 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 18-May-17 |
IIDEBO-ST340 | PH IID - Curing for End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 19-May-17 |
IIIBWBO-EW100 | PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening Area | 19-May-17 |
IIBEBO-ST470 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 20-May-17 |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | 22-May-17 |
PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | 22-May-17 |
PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | 22-May-17 |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 22-May-17 |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 22-May-17 |
PRE-RA-037 | Review and Approve 233113 Ductwork Product Data and Shop Drawing | 22-May-17 |
IIIBR-EW120 | PH IIIB - Embankment - Ramp V | 22-May-17 |
IIBR-RW270 | PH IIB - Base - Ramp U | 24-May-17 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 26-May-17 |
IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 26-May-17 |
IIIAWBO-ST420 | PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 30-May-17 |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 31-May-17 |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 02-Jun-17 |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 02-Jun-17 |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 05-Jun-17 |
PRE-FA-033 | Fabricate and Deliver 101400 Signage | 05-Jun-17 |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 07-Jun-17 |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 07-Jun-17 |
IIBEBO-ST450 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 07-Jun-17 |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 08-Jun-17 |
PRE-RA-024 | Review and Approve 633 Communication Cable | 08-Jun-17 |
PRE-RA-045 | Review and Approve 660 ITS Vehicle Detection System | 08-Jun-17 |
IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 09-Jun-17 |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 09-Jun-17 |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 09-Jun-17 |
IIIBR-GC190 | PH IIIB - Demo - Ramp K | 13-Jun-17 |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 |
IIBEBO-ST420 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 16-Jun-17 |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 20-Jun-17 |
IIBEBO-ST360 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 20-Jun-17 |
IIIAWBO-ST520 | PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 21-Jun-17 |
TF-CO-013 | Const. Screen Wall (Con.) | 22-Jun-17 |
PRE-FA-030 | Fabricate and Deliver 042200 Masonry | 22-Jun-17 |
IIBEBO-ST730 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 22-Jun-17 |
TF-FA-001 | Fabricate and Deliver Precast Erection | 27-Jun-17 |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 27-Jun-17 |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 27-Jun-17 |
TF-CO-004 | Precast Erection | 28-Jun-17 |
TF-CO-006 | FRP Conc. Roof Dec/c | 28-Jun-17 |
TF-CO-009 | Const. Roof System | 28-Jun-17 |
TF-CO-012 | Install Frames & Doors | 28-Jun-17 |
TF-CO-015 | Install HVAC | 28-Jun-17 |
PRE-RA-030 | Review and Approve 042200 Masonry | 29-Jun-17 |
TF-CO-001 | Foundation (FRP SOG) | 30-Jun-17 |
TF-CO-008 | Constr. Pedestal | 30-Jun-17 |
IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IIIBWBO-ST300 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 06-Jul-17 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 07-Jul-17 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 07-Jul-17 |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 07-Jul-17 |
IIIBWBO-ST240 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 08-Jul-17 |
IIIBWBO-ST260 | PH IIIB - Wall Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 08-Jul-17 |
IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | 11-Jul-17 |
IIIBWBO-ST220 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 11-Jul-17 |
IIAR-RW110 | PH IIB - Base - Ramp O | 12-Jul-17 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 12-Jul-17 |
IIIBWBO-ST640 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over universal BLVD) | 12-Jul-17 |
IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 13-Jul-17 |
PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | 13-Jul-17 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 14-Jul-17 |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 14-Jul-17 |
IIIBWBO-ST330 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 15-Jul-17 |
USDED-CO-002 | Duke Energy Distribution (B) | 17-Jul-17 |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 18-Jul-17 |
IIIBR-SP100 | PH IIIB - Drainage (Temp) - Ramp G | 18-Jul-17 |
IIBEBO-ST480 | PH IIB - Set Beams - EB Outside Widening (Bridge over Universal BLVD) | 18-Jul-17 |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 19-Jul-17 |
IIIBWBO-ST340 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Universal BLVD) | 19-Jul-17 |
IIBR-RW250 | PH IIB - Base - Ramp L | 21-Jul-17 |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 21-Jul-17 |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 28-Jul-17 |
IIBR-RW170 | PH IIB - Base - Ramp I-1 | 04-Aug-17 |
IIBEBO-ST500 | PH IIB - Superstructure Deck SIP / Overhangs / Edges - EB Outside Widening (Bridge over Universal BLVD) | 07-Aug-17 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 09-Aug-17 |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 10-Aug-17 |
IIIAWBO-ST570 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 11-Aug-17 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 17-Aug-17 |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 17-Aug-17 |
IIBEBO-ST550 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over universal BLVD) | 17-Aug-17 |
TF-CO-010 | FRP Conc. Pad (Generator) | 18-Aug-17 |
TF-CO-022 | Construct Sidewalk | 18-Aug-17 |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 18-Aug-17 |
IIBEBO-ST520 | PH IIB - Superstructure Deck Rebar - EB Outside Widening (Bridge over Universal BLVD) | 18-Aug-17 |
IIIAWBO-ST120 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 18-Aug-17 |
IIIAWBO-ST590 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 18-Aug-17 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 21-Aug-17 |
IIBR-AP170 | PH IIB - Asphalt - Structural - Ramp L | 21-Aug-17 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 21-Aug-17 |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 21-Aug-17 |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 21-Aug-17 |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 21-Aug-17 |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 22-Aug-17 |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 22-Aug-17 |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 23-Aug-17 |
IIIAWBO-ST111 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 23-Aug-17 |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 23-Aug-17 |
IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L | 24-Aug-17 |
IIIAWBO-ST140 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 24-Aug-17 |
IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 25-Aug-17 |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 28-Aug-17 |
GC-GCN180 | PH MS - Start Phase III C Construction | 29-Aug-17 |
IIIAWBO-ST130 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 30-Aug-17 |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 31-Aug-17 |
IIBEBO-ST530 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over universal BLVD) | 31-Aug-17 |
IIIAWBO-ST170 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 06-Sep-17 |
PRE-PS-027 | Prepare and Submit 663 Signal Priority and Preemption Systems | 13-Sep-17 |
IIIBR-SP120 | PH IIIB - Drainage (Temp) - Ramp V | 17-Sep-17 |
IIIBR-SP130 | PH IIIB - Drainage (Temp) - Ramp K | 17-Sep-17 |
IIIBR-TC160 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp J | 17-Sep-17 |
IIIBR-TC200 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp K | 17-Sep-17 |
IIBR-GC140 | PH IIB - Demo - Ramp I-1 | 19-Sep-17 |
IIBR-EW150 | PH IIB - Embankment - Ramp I-1 | 22-Sep-17 |
IIIAWBO-ST600 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 24-Sep-17 |
PRE-RA-027 | Review and Approve 663 Signal Priority and Preemption Systems | 29-Sep-17 |
IIBEBO-ST560 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over universal BLVD) | 01-Oct-17 |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 03-Oct-17 |
IIIBR-RW140 | PH IIIB - Stabilization - Ramp V | 04-Oct-17 |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 05-Oct-17 |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 06-Oct-17 |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 06-Oct-17 |
IIBR-RW130 | PH IIB - Base - Ramp E | 09-Oct-17 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 09-Oct-17 |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 09-Oct-17 |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 09-Oct-17 |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 11-Oct-17 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 12-Oct-17 |
IIIAWBO-AP100 | PH IIIA - Mill & Resurface (sacrificial) - WB Outside Widening Area (SR528) | 12-Oct-17 |
IIIAWBO-TC100 | PH IIIA - Install Sign & Traffic Control Devices - WB Outside Widening Area | 12-Oct-17 |
IIIAWBO-TC110 | PH IIIA - Temp Striping for Phase - WB Outside Widening Area (SR528) | 12-Oct-17 |
IIIAWBO-TC120 | PH IIIA - MOT Shift for Phase - WB Outside Widening Area | 12-Oct-17 |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 12-Oct-17 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 13-Oct-17 |
IIBR-GC170 | PH IIB - Demo - Ramp C | 13-Oct-17 |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 13-Oct-17 |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 13-Oct-17 |
IIIBWBO-ST460 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over universal BLVD) | 13-Oct-17 |
IIBR-RW290 | PH IIB - Shoulder Gutter - Ramp C | 15-Oct-17 |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 16-Oct-17 |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 16-Oct-17 |
IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 16-Oct-17 |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 17-Oct-17 |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 17-Oct-17 |
IIIBWBO-ST470 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over universal BLVD) | 21-Oct-17 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Oct-17 |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 25-Oct-17 |
IICR-TC210 | PH IIC - MOT Shift New Ramp Alignment - Ramp U | 25-Oct-17 |
IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V | 25-Oct-17 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 25-Oct-17 |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 25-Oct-17 |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 27-Oct-17 |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 27-Oct-17 |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 30-Oct-17 |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 31-Oct-17 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 31-Oct-17 |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 02-Nov-17 |
IIICWBO-ST220 | PH IIIA - Demo Bridge Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 02-Nov-17 |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 03-Nov-17 |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 03-Nov-17 |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 04-Nov-17 |
IIIBR-RW130 | PH IIIB - Base - Ramp J | 08-Nov-17 |
IIBR-RW190 | PH IIB - Base - Ramp H | 09-Nov-17 |
IIIBR-TC120 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp G | 09-Nov-17 |
IIIBR-TC130 | PH IIIB - Temp Striping New Ramp Alignment - Ramp G | 10-Nov-17 |
IIIC-CP10 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 12-Nov-17 |
IIBR-GC390 | PH IIB - Guardrail (Roadway) - Ramp R | 12-Nov-17 |
IIIBR-GC140 | PH IIIB - Demo - Ramp J | 15-Nov-17 |
TF-CO-016 | F+1 Generator | 17-Nov-17 |
TF-CO-017 | F+1 Fuel Tank | 17-Nov-17 |
IIIBWBO-W101 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over Universal BLVD) | 17-Nov-17 |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 27-Nov-17 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 30-Nov-17 |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 03-Dec-17 |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 05-Dec-17 |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 06-Dec-17 |
GC-GCN190 | PH MS - Start Phase II D Construction | 07-Dec-17 |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 07-Dec-17 |
IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H | 07-Dec-17 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 07-Dec-17 |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 07-Dec-17 |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 07-Dec-17 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 07-Dec-17 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 07-Dec-17 |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 08-Dec-17 |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 08-Dec-17 |
IIBEBO-ST200 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over International DR) | 08-Dec-17 |
TF-CO-025 | Install Equip. Arm Supports | 11-Dec-17 |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 11-Dec-17 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 12-Dec-17 |
TF-CO-023 | Erect Truss | 13-Dec-17 |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 13-Dec-17 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 14-Dec-17 |
IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | 15-Dec-17 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 16-Dec-17 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 18-Dec-17 |
IICR-TC160 | PH IIC - Temp Striping New Ramp Alignment - Ramp S-2 | 18-Dec-17 |
IICR-TC170 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp S-2 | 18-Dec-17 |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 18-Dec-17 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 18-Dec-17 |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 18-Dec-17 |
IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | 18-Dec-17 |
IICR-GC100 | PH IIC - Demo - Ramp S-2 | 20-Dec-17 |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 20-Dec-17 |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 21-Dec-17 |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 21-Dec-17 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 02-Jan-18 |
PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | 02-Jan-18 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 |
IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | 04-Jan-18 |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 04-Jan-18 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 08-Jan-18 |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 09-Jan-18 |
IIBR-GC220 | PH IIB - Guardrail (Roadway) - Ramp E | 10-Jan-18 |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 12-Jan-18 |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 12-Jan-18 |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 12-Jan-18 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 15-Jan-18 |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 15-Jan-18 |
PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | 15-Jan-18 |
IIIBR-TC170 | PH IIIB - Temp Striping New Ramp Alignment - Ramp J | 15-Jan-18 |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 17-Jan-18 |
IIIAWBO-ST181 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge over John Young PKWY) | 18-Jan-18 |
IICR-TC1020 | PH IIC - Temp Striping New Ramp Alignment - Ramp M | 19-Jan-18 |
TF-CO-014 | Pull Wire & Install Light Fixtures | 22-Jan-18 |
TF-CO-018 | Install Lighting | 22-Jan-18 |
TF-CO-019 | Install Security System | 22-Jan-18 |
TF-CO-020 | Install Lightning Protection | 22-Jan-18 |
TF-CO-024 | Wall Treatments (Ply) | 22-Jan-18 |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 22-Jan-18 |
IBEBO-EW150 | PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside Widening | 22-Jan-18 |
IBEBO-EW160 | PH IB - Pond Excav/Embank Universal to JYP - EB Outside Widening | 22-Jan-18 |
IIIBR-SP160 | PH IIIB - Drainage (Temp) - Ramp Q | 22-Jan-18 |
IIBR-RW160 | PH IIB - Base - Ramp C | 24-Jan-18 |
IIBR-SP210 | PH IIB - Drainage - Ramp D | 26-Jan-18 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 26-Jan-18 |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 31-Jan-18 |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 01-Feb-18 |
IIBEBO-ST250 | PH IIB - Set Beams - EB Outside Widening (Bridge over International Drive) | 06-Feb-18 |
IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 06-Feb-18 |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 07-Feb-18 |
IICR-GC170 | PH IIC - Demo - Ramp M | 07-Feb-18 |
IIIAWBO-ST150 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge over John Young PKWY) | 07-Feb-18 |
IIICR-GC110 | PH IIIC - Demo - Ramp N | 08-Feb-18 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 08-Feb-18 |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 09-Feb-18 |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 09-Feb-18 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 09-Feb-18 |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 12-Feb-18 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 12-Feb-18 |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 16-Feb-18 |
IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 16-Feb-18 |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 19-Feb-18 |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 19-Feb-18 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 19-Feb-18 |
IBEBO-EW130 | PH IB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 20-Feb-18 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 21-Feb-18 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 21-Feb-18 |
IBEBO-EW140 | PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside Widening | 22-Feb-18 |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 22-Feb-18 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Feb-18 |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 23-Feb-18 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 23-Feb-18 |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Feb-18 |
IIIBR-EW140 | PH IIIB - Embankment - Ramp T | 28-Feb-18 |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 28-Feb-18 |
IIIBWBO-ST320 | PH IIIB - Curing for Pier 2, 3, (Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 28-Feb-18 |
IIDEBO-ST230 | PH IID - Set Beams - EB Outside Widening (Bridge over John Young PKWY) | 01-Mar-18 |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 02-Mar-18 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 02-Mar-18 |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 02-Mar-18 |
IIBEBO-ST270 | PH IIB - Superstructure Deck - EB Outside Widening (Bridge over International Drive) | 02-Mar-18 |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 03-Mar-18 |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 09-Mar-18 |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 12-Mar-18 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 14-Mar-18 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 15-Mar-18 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 16-Mar-18 |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 19-Mar-18 |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 19-Mar-18 |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 19-Mar-18 |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 19-Mar-18 |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 19-Mar-18 |
IIIBR-TC270 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp Q | 19-Mar-18 |
IIIBR-TC280 | PH IIIB - Temp Striping New Ramp Alignment - Ramp Q | 19-Mar-18 |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 19-Mar-18 |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 19-Mar-18 |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 20-Mar-18 |
IIICR-TC140 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp N | 20-Mar-18 |
IIICR-TC150 | PH IIIC - Temp Striping New Ramp Alignment - Ramp N | 20-Mar-18 |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 21-Mar-18 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 22-Mar-18 |
IIBEBO-ST380 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over International DR) | 22-Mar-18 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Mar-18 |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 23-Mar-18 |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 23-Mar-18 |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 23-Mar-18 |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 23-Mar-18 |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 24-Mar-18 |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 26-Mar-18 |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 27-Mar-18 |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 28-Mar-18 |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 29-Mar-18 |
IICR-EW120 | PH IIC - Embankment - Ramp M | 30-Mar-18 |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 30-Mar-18 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 30-Mar-18 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 30-Mar-18 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 30-Mar-18 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 01-Apr-18 |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 01-Apr-18 |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 01-Apr-18 |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 01-Apr-18 |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 02-Apr-18 |
IIBR-EW210 | PH IIB - Embankment - Ramp D | 03-Apr-18 |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 03-Apr-18 |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 03-Apr-18 |
IIIBR-GC260 | PH IIIB - Guardrail (Roadway) - Ramp K | 03-Apr-18 |
GC-GCN160 | PH MS - Start Phase IV Construction | 05-Apr-18 |
IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J | 05-Apr-18 |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 06-Apr-18 |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 09-Apr-18 |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 12-Apr-18 |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 12-Apr-18 |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 13-Apr-18 |
IIIBWBO-ST4 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR) | 13-Apr-18 |
IIIAWBO-ST191 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge over John Young PKWY) | 13-Apr-18 |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 13-Apr-18 |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 18-Apr-18 |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 20-Apr-18 |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 25-Apr-18 |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 25-Apr-18 |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 26-Apr-18 |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 26-Apr-18 |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 27-Apr-18 |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 29-Apr-18 |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 30-Apr-18 |
IIIBR-GC250 | PH IIIB - Demo - Ramp P | 30-Apr-18 |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 02-May-18 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 02-May-18 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 04-May-18 |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 05-May-18 |
IIICR-RW130 | PH IIIC - Base - Ramp N | 07-May-18 |
PRE-FA-044 | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable | 07-May-18 |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 08-May-18 |
IICR-RW140 | PH IIC - Base - Ramp M | 09-May-18 |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 10-May-18 |
IICR-SP120 | PH IIC - Drainage - Ramp M | 10-May-18 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 11-May-18 |
TF-CO-027 | Cont. HVAC | 11-May-18 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 11-May-18 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 11-May-18 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 11-May-18 |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 12-May-18 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 12-May-18 |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 14-May-18 |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 14-May-18 |
IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 15-May-18 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 16-May-18 |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 18-May-18 |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 18-May-18 |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 21-May-18 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 21-May-18 |
IIICR-EW100 | PH IIIC - Embankment - Ramp F | 22-May-18 |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 22-May-18 |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 24-May-18 |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 24-May-18 |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 24-May-18 |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 24-May-18 |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 24-May-18 |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 25-May-18 |
IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | 25-May-18 |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 25-May-18 |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 25-May-18 |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 25-May-18 |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 25-May-18 |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 29-May-18 |
IIIBR-SP150 | PH IIIB - Drainage - Ramp P | 30-May-18 |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 31-May-18 |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 31-May-18 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 31-May-18 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 01-Jun-18 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 03-Jun-18 |
IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Jun-18 |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 05-Jun-18 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 05-Jun-18 |
IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 05-Jun-18 |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 06-Jun-18 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 07-Jun-18 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 08-Jun-18 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 08-Jun-18 |
IIICR-RW110 | PH IIIC - Base - Ramp F | 08-Jun-18 |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 12-Jun-18 |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 21-Jun-18 |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 23-Jun-18 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 25-Jun-18 |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 29-Jun-18 |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 29-Jun-18 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 02-Jul-18 |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 03-Jul-18 |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 06-Jul-18 |
IIIBWBO-ST390 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over International Drive) | 07-Jul-18 |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 09-Jul-18 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 11-Jul-18 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 12-Jul-18 |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 13-Jul-18 |
IIIBWBO-ST690 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over International Drive) | 14-Jul-18 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 25-Jul-18 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 03-Aug-18 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 03-Aug-18 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 08-Aug-18 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 10-Aug-18 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 10-Aug-18 |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 17-Aug-18 |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 17-Aug-18 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 17-Aug-18 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 20-Aug-18 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 20-Aug-18 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 20-Aug-18 |
IIBR-GC260 | PH IIB - Guardrail (Roadway) - Ramp I-1 | 21-Aug-18 |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 21-Aug-18 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 22-Aug-18 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 22-Aug-18 |
IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) | 24-Aug-18 |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 27-Aug-18 |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 31-Aug-18 |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 05-Sep-18 |
IVEBM-W180 | PH IV - Median Wall - FFP Stem - Station 259+50 to 311 | 08-Sep-18 |
IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express | 10-Sep-18 |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 10-Sep-18 |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 10-Sep-18 |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 11-Sep-18 |
IIDEBO-ST270 | PH IID - Lighting Conduit - EB Outside Widening (Bridge over John Young PKWY) | 13-Sep-18 |
IIIBWBO-ST530 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over International DR) | 13-Sep-18 |
IIBR-TC170 | PH IIB - Temp Striping for New Ramp Alignment - Ramp B | 17-Sep-18 |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 19-Sep-18 |
IIIBWBO-ST540 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over International DR) | 19-Sep-18 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 27-Sep-18 |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 27-Sep-18 |
IIDEBO-ST290 | PH IID - Grind and Groove - EB Outside Widening (Bridge over John Young PKWY) | 28-Sep-18 |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 28-Sep-18 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 05-Oct-18 |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 05-Oct-18 |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 05-Oct-18 |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 06-Oct-18 |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 10-Oct-18 |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 12-Oct-18 |
IBR-EW100 | PH IB - Embankment - Ramp B/C Gore | 12-Oct-18 |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 12-Oct-18 |
IBR-RW100 | PH IB - Stabilization - Ramp B/C Gore | 16-Oct-18 |
PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | 19-Oct-18 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 19-Oct-18 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 19-Oct-18 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 19-Oct-18 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 19-Oct-18 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 19-Oct-18 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 19-Oct-18 |
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 22-Oct-18 |
This table represents activities with actual start dates bigger than data date in E8P02 Update No 36
Activity ID | Activity Description | Actual Start | Actual Finish |
---|---|---|---|
IVEBM-TC120 | PH IV - TCP Shift to Phase IV - EB traffic to outside at JYP | 22-Oct-18 | 22-Oct-18 |
This table represents activities with no predecessor relationships in E8P02 Update No 36
Activity ID | Activity Description |
---|---|
GC-DP100 | PH MS - NTP |
This table represents activities with no successor relationships in E8P02 Update No 36
Activity ID | Activity Description |
---|---|
GC-DP110 | PH MS - Project Completion |
This table represents activities completed out-of-sequence in E8P02 Update No 36
Activity ID | Activity Description | Act start date | Parent end date |
---|---|---|---|
GC-GCN130 | PH MS - Start Phase IIA Construction | 19-Sep-16 | 21-Oct-18 |
GC-GCN140 | PH MS - Start Phase II B Construction | 04-Oct-16 | 21-Oct-18 |
GC-GCN150 | PH MS - Start Phase II C Construction | 28-Feb-17 | 21-Oct-18 |
GC-GCN160 | PH MS - Start Phase IV Construction | 05-Apr-18 | 22-Oct-18 |
GC-GCN170 | PH MS - Start Phase III B Construction | 23-Jan-17 | 21-Oct-18 |
GC-GCN180 | PH MS - Start Phase III C Construction | 29-Aug-17 | 21-Oct-18 |
GC-GCN190 | PH MS - Start Phase II D Construction | 07-Dec-17 | 21-Oct-18 |
GC-GCN200 | PH MS - Start Phase III A Construction | 30-Mar-17 | 21-Oct-18 |
GC-GCN220 | Written Suspend order - FOC related to pending change | 24-May-18 | 21-Oct-18 |
IAWBO-SP110 | PH IA - Drainage (42") @ JYP Interchange - WB Outside Widening Area (SR528) | 10-Nov-16 | 21-Oct-18 |
IBEBM-AP100 | PH IB - Asphalt - Structural - EB Median Widening (I-4 to I-Drive) | 02-Mar-17 | 21-Oct-18 |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 06-Feb-17 | 21-Oct-18 |
IBEBM-AP120 | PH IB - Asphalt - Structural - EB Median Widening (Univ to JYP) | 23-Jan-17 | 21-Oct-18 |
IBEBM-RW220 | PH IB - Grade (I4-International Drive) - EB Median Widening | 06-Feb-17 | 21-Oct-18 |
IBEBM-RW230 | PH IB - Grade (International Drive - Universal) - EB Median Widening | 30-Jan-17 | 21-Oct-18 |
IBEBM-RW240 | PH IB - Grade (Universal - JYP) - EB Median Widening | 19-Dec-16 | 21-Oct-18 |
IBEBM-RW250 | PH IB - Stabilization (I4-international Drive) - EB Median Widening | 17-Feb-17 | 21-Oct-18 |
IBEBM-RW260 | PH IB - Stabilization (International Drive - Universal) - EB Median Widening | 08-Feb-17 | 21-Oct-18 |
IBEBM-RW270 | PH IB - Stabilization (Universal - JYP) - EB Median Widening | 18-Jan-17 | 21-Oct-18 |
IBEBM-RW290 | PH IB - Base (International Drive - Universal) - EB Median Widening | 08-Feb-17 | 21-Oct-18 |
IBEBM-RW300 | PH IB - Base (Universal - JYP) - EB Median Widening | 18-Jan-17 | 21-Oct-18 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 01-Nov-16 | 21-Oct-18 |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 17-Nov-16 | 21-Oct-18 |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 13-Oct-16 | 21-Oct-18 |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 24-Oct-16 | 21-Oct-18 |
IBEBM-ST550 | PH IB - Approach Slabs - EB Median Widening (Bridge over International DR) | 12-Jan-17 | 21-Oct-18 |
IBEBM-ST580 | PH IB - Lighting Conduit - EB Median Widening (Bridge over International DR) | 26-Jan-17 | 21-Oct-18 |
IBEBM-ST590 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over International DR) | 07-Feb-17 | 21-Oct-18 |
IBEBM-ST600 | PH IB - Grind and Groove - EB Median Widening (Bridge over International DR) | 20-Feb-17 | 21-Oct-18 |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 27-Sep-16 | 21-Oct-18 |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 21-Oct-16 | 21-Oct-18 |
IBEBM-ST730 | PH IB - Approach Slabs - EB Median Widening (Bridge over John Young PKWY) | 15-Feb-17 | 21-Oct-18 |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 11-Oct-16 | 21-Oct-18 |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 24-Oct-16 | 21-Oct-18 |
IBEBM-ST770 | PH IB - Lighting Conduit - EB Median Widening (Bridge over John Young PKWY) | 01-Feb-17 | 21-Oct-18 |
IBEBM-ST780 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over John Young PKWY) | 03-Mar-17 | 21-Oct-18 |
IBEBM-ST790 | PH IB - Grind and Groove - EB Median Widening (Bridge over John Young PKWY) | 28-Feb-17 | 21-Oct-18 |
IBEBM-ST840 | PH IB - Approach Slabs - EB Median Widening (Bridge over universal BLVD) | 20-Jan-17 | 21-Oct-18 |
IBEBM-ST860 | PH IB - Lighting Conduit - EB Median Widening (Bridge over universal BLVD) | 30-Jan-17 | 21-Oct-18 |
IBEBM-ST870 | PH IB - Traffic Railing (32") - EB Median Widening (Bridge over universal BLVD) | 09-Feb-17 | 21-Oct-18 |
IBEBM-ST880 | PH IB - Grind and Groove - EB Median Widening (Bridge over universal BLVD) | 21-Feb-17 | 21-Oct-18 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 23-Aug-17 | 21-Oct-18 |
IBEBO-EW120 | PH IB - Pond Excav/Embank I-4 to Int. Dr. - EB Outside Widening | 16-Jan-17 | 21-Oct-18 |
IBR-AP120 | PH IB - Asphalt - Structural - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-EW100 | PH IB - Embankment - Ramp B/C Gore | 08-Oct-18 | 26-Oct-18 |
IBR-EW110 | PH IB - Embankment - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-GC120 | PH IB - Guardrail (Roadway) - Ramp B/C Gore (Activity Not Req'd) | 19-Dec-16 | 26-Oct-18 |
IBR-GC130 | PH IB - Clear & Grub/Demo - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-GC150 | PH IB - Performance Turf, SOD - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-GC160 | PH IB - Guardrail (Roadway) - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-RW100 | PH IB - Stabilization - Ramp B/C Gore | 15-Oct-18 | 26-Oct-18 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 15-Oct-18 | 26-Oct-18 |
IBR-RW120 | PH IB - Stabilization - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-RW130 | PH IB - Base - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBR-TC100 | PH IB - Set Temp Traffic Barriers - Ramp B/C Gore | 22-May-17 | 21-Oct-18 |
IBR-TC110 | PH IB - Set Temp Traffic Barriers - Ramp C (Redundant) | 19-Dec-16 | 21-Oct-18 |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 16-Nov-16 | 21-Oct-18 |
IBWBM-RW130 | PH IB - Grade (JYP-Universal) - WB Median Widening | 26-Oct-16 | 21-Oct-18 |
IBWBM-RW140 | PH IB - Stabilization (JYP-Universal) - WB Median Widening | 28-Oct-16 | 21-Oct-18 |
IBWBM-RW150 | PH IB - Base (JYP-Universal) - WB Median Widening | 03-Nov-16 | 21-Oct-18 |
IBWBM-RW160 | PH IB - Grade (Universal-International Drv.) - WB Median Widening | 14-Dec-16 | 21-Oct-18 |
IBWBM-RW170 | PH IB - Stabilization (Universal-International Drv.) - WB Median Widening | 14-Dec-16 | 21-Oct-18 |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 14-Dec-16 | 21-Oct-18 |
IBWBM-RW190 | PH IB - Grade (International Drive-I4) - WB Median Widening | 15-Dec-16 | 21-Oct-18 |
IBWBM-RW200 | PH IB - Stabilization (International Drv.-I4) - WB Median Widening | 15-Dec-16 | 21-Oct-18 |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 15-Dec-16 | 21-Oct-18 |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 27-Oct-16 | 21-Oct-18 |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 15-Nov-16 | 21-Oct-18 |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 13-Oct-16 | 21-Oct-18 |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 24-Oct-16 | 21-Oct-18 |
IBWBM-ST390 | PH IB - Approach Slabs - WB Median Widening (Bridge over International DR) | 12-Jan-17 | 21-Oct-18 |
IBWBM-ST430 | PH IB - Lighting Conduit - WB Median Widening (Bridge over International DR) | 26-Jan-17 | 21-Oct-18 |
IBWBM-ST440 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over International DR) | 07-Feb-17 | 21-Oct-18 |
IBWBM-ST470 | PH IB - Grind and Groove - WB Median Widening (Bridge over International DR) | 20-Feb-17 | 21-Oct-18 |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 27-Sep-16 | 21-Oct-18 |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 18-Nov-16 | 21-Oct-18 |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 11-Oct-16 | 21-Oct-18 |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 06-Dec-16 | 21-Oct-18 |
IBWBM-ST610 | PH IB - Approach Slabs - WB Median Widening (Bridge over John Young PKWY) | 15-Feb-17 | 21-Oct-18 |
IBWBM-ST630 | PH IB - Lighting Conduit - WB Median Widening (Bridge over John Young PKWY) | 31-Jan-17 | 21-Oct-18 |
IBWBM-ST640 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over John Young PKWY) | 06-Mar-17 | 21-Oct-18 |
IBWBM-ST650 | PH IB - Approach Slabs - WB Median Widening (Bridge over universal BLVD) | 25-Jan-17 | 21-Oct-18 |
IBWBM-ST670 | PH IB - Grind and Groove - WB Median Widening (Bridge over John Young PKWY) | 27-Feb-17 | 21-Oct-18 |
IBWBM-ST680 | PH IB - Lighting Conduit - WB Median Widening (Bridge over universal BLVD) | 31-Jan-17 | 21-Oct-18 |
IBWBM-ST690 | PH IB - Traffic Railing (32") - WB Median Widening (Bridge over universal BLVD) | 09-Feb-17 | 21-Oct-18 |
IBWBM-ST700 | PH IB - Grind and Groove - WB Median Widening (Bridge over universal BLVD) | 21-Feb-17 | 21-Oct-18 |
IBWBM-TC150 | PH IB - Construct Diversion at I-Drive - WB Median Widening | 08-Feb-17 | 21-Oct-18 |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 24-Oct-16 | 22-Oct-18 |
IIAEBO-AP100 | PH IIA - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 29-Mar-17 | 21-Oct-18 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 26-Jun-17 | 21-Oct-18 |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 30-Apr-18 | 21-Oct-18 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 18-May-17 | 21-Oct-18 |
IIAR-RW110 | PH IIB - Base - Ramp O | 30-May-17 | 21-Oct-18 |
IIAR-TC120 | PH IIB - Construction 12' Widening on I-4 (Ramp C to EB I-4) | 24-Sep-18 | 21-Oct-18 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 14-May-18 | 21-Oct-18 |
IIBEBO-AP100 | PH IIB - Mill & Resurface (sacrificial) - EB Outside Widening (SR528) | 05-Apr-17 | 21-Oct-18 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 29-Jan-18 | 21-Oct-18 |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 04-Aug-17 | 21-Oct-18 |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 28-Jun-17 | 21-Oct-18 |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 22-Jun-17 | 21-Oct-18 |
IIBEBO-AP145 | PH IIB - Mill and resurface - EB Inside (I-4 to I-Drive) | 23-May-18 | 21-Oct-18 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 16-Jun-17 | 21-Oct-18 |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 03-Oct-16 | 21-Oct-18 |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 10-Oct-16 | 21-Oct-18 |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 06-Feb-17 | 21-Oct-18 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 20-Mar-17 | 21-Oct-18 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 07-May-18 | 21-Oct-18 |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 16-Aug-17 | 21-Oct-18 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 04-Dec-17 | 21-Oct-18 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 03-Apr-17 | 21-Oct-18 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 17-Mar-17 | 21-Oct-18 |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 10-Jan-18 | 21-Oct-18 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 10-Jul-17 | 21-Oct-18 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 11-Jul-17 | 21-Oct-18 |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 12-Jul-17 | 21-Oct-18 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 15-Jun-17 | 21-Oct-18 |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 17-Mar-17 | 21-Oct-18 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 01-May-17 | 21-Oct-18 |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 08-Jan-18 | 21-Oct-18 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 07-Nov-16 | 21-Oct-18 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 20-Mar-17 | 21-Oct-18 |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 26-May-17 | 21-Oct-18 |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 08-May-17 | 21-Oct-18 |
IIBEBO-SP150 | PH IIB - Gutter Drainage - STA 326 - 336 (EB Outside) | 05-Apr-17 | 21-Oct-18 |
IIBEBO-SP160 | PH IIB - Gutter Drainage - STA 407 - 412 (EB Outside) | 08-Jan-18 | 21-Oct-18 |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 10-Oct-16 | 21-Oct-18 |
IIBEBO-ST11 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge over universal BLVD) | 17-Oct-16 | 21-Oct-18 |
IIBEBO-ST110 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over Shingle Creek) | 10-Oct-16 | 21-Oct-18 |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 17-Oct-16 | 21-Oct-18 |
IIBEBO-ST120 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 30-Jan-17 | 21-Oct-18 |
IIBEBO-ST130 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over International DR) | 12-Apr-17 | 21-Oct-18 |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 31-Oct-16 | 21-Oct-18 |
IIBEBO-ST140 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over International DR) | 06-Dec-17 | 21-Oct-18 |
IIBEBO-ST150 | PH IIB - End Bent 1 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 24-Jan-17 | 21-Oct-18 |
IIBEBO-ST16 | PH IIB - Curing for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 08-Dec-16 | 21-Oct-18 |
IIBEBO-ST160 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over International DR) | 02-Dec-17 | 21-Oct-18 |
IIBEBO-ST17 | PH IIB - Removal of Concrete Forms Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLV | 15-Dec-16 | 21-Oct-18 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 07-Nov-16 | 21-Oct-18 |
IIBEBO-ST18 | PH IIB - Temp Sheet Pile Removal - EB Outside Widening (Bridge over universal BLVD) | 15-Dec-16 | 21-Oct-18 |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 13-Jan-17 | 21-Oct-18 |
IIBEBO-ST190 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over International DR) | 08-Dec-17 | 21-Oct-18 |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 10-Aug-17 | 21-Oct-18 |
IIBEBO-ST200 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over International DR) | 05-Dec-17 | 21-Oct-18 |
IIBEBO-ST210 | PH IIB - Curing Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 10-Jan-17 | 21-Oct-18 |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10-Jan-17 | 21-Oct-18 |
IIBEBO-ST230 | PH IIB - Removal concrete form for Pier 2, 3, (Pile Cap) - EB Outside Widening (Bridge over Shingle Cr | 20-Jan-17 | 21-Oct-18 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 11-Jan-17 | 21-Oct-18 |
IIBEBO-ST25 | PH IIB - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 14-Nov-16 | 21-Oct-18 |
IIBEBO-ST250 | PH IIB - Set Beams - EB Outside Widening (Bridge over International Drive) | 05-Feb-18 | 21-Oct-18 |
IIBEBO-ST260 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 11-Jan-17 | 21-Oct-18 |
IIBEBO-ST270 | PH IIB - Superstructure Deck - EB Outside Widening (Bridge over International Drive) | 07-Feb-18 | 21-Oct-18 |
IIBEBO-ST280 | PH IIB - Set Beams - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 13-Feb-17 | 21-Oct-18 |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-Feb-17 | 21-Oct-18 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 17-Oct-16 | 21-Oct-18 |
IIBEBO-ST300 | PH IIB - Wall Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 26-Jan-17 | 21-Oct-18 |
IIBEBO-ST310 | PH IIB - End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 13-Jan-17 | 21-Oct-18 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 02-Dec-16 | 21-Oct-18 |
IIBEBO-ST320 | PH IIB - Demo Traffic Rails - EB Outside Widening (Bridge over universal BLVD) | 10-Apr-17 | 21-Oct-18 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 01-Mar-18 | 21-Oct-18 |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 29-Jan-18 | 21-Oct-18 |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10-Mar-17 | 21-Oct-18 |
IIBEBO-ST360 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 | 21-Oct-18 |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 06-Mar-18 | 21-Oct-18 |
IIBEBO-ST380 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over International DR) | 21-Mar-18 | 21-Oct-18 |
IIBEBO-ST390 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over International DR) | 30-Mar-18 | 21-Oct-18 |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 06-Jun-17 | 21-Oct-18 |
IIBEBO-ST410 | PH IIB - Set Beams - EB Outside Widening (Bridge over Shingle Creek) | 06-Feb-17 | 21-Oct-18 |
IIBEBO-ST420 | PH IIB - Wall Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 08-Jun-17 | 21-Oct-18 |
IIBEBO-ST430 | PH IIB - Approach Slabs - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 01-May-17 | 21-Oct-18 |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 18-Dec-17 | 21-Oct-18 |
IIBEBO-ST450 | PH IIB - End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 31-May-17 | 21-Oct-18 |
IIBEBO-ST460 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 17-May-17 | 21-Oct-18 |
IIBEBO-ST470 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 19-May-17 | 21-Oct-18 |
IIBEBO-ST480 | PH IIB - Set Beams - EB Outside Widening (Bridge over Universal BLVD) | 17-Jul-17 | 21-Oct-18 |
IIBEBO-ST490 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over Shingle Creek) | 10-Feb-17 | 21-Oct-18 |
IIBEBO-ST500 | PH IIB - Superstructure Deck SIP / Overhangs / Edges - EB Outside Widening (Bridge over Universal BLVD) | 21-Jul-17 | 21-Oct-18 |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 02-Jun-17 | 21-Oct-18 |
IIBEBO-ST520 | PH IIB - Superstructure Deck Rebar - EB Outside Widening (Bridge over Universal BLVD) | 14-Aug-17 | 21-Oct-18 |
IIBEBO-ST530 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over universal BLVD) | 24-Aug-17 | 21-Oct-18 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 27-Nov-17 | 21-Oct-18 |
IIBEBO-ST550 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over universal BLVD) | 16-Aug-17 | 21-Oct-18 |
IIBEBO-ST560 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over universal BLVD) | 30-Sep-17 | 21-Oct-18 |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 21-Aug-17 | 21-Oct-18 |
IIBEBO-ST580 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over universal BLVD) | 01-Nov-17 | 21-Oct-18 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 27-Mar-17 | 21-Oct-18 |
IIBEBO-ST600 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over Shingle Creek) | 20-Apr-17 | 21-Oct-18 |
IIBEBO-ST610 | PH IIB - Traffic Railing (32") - EB Outside Widening (Bridge over Shingle Creek) | 24-Apr-17 | 21-Oct-18 |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 31-May-17 | 21-Oct-18 |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 24-Apr-17 | 21-Oct-18 |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 24-Apr-17 | 21-Oct-18 |
IIBEBO-ST650 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 | 21-Oct-18 |
IIBEBO-ST660 | PH IIB - Remove Beams - EB Outside Widening (Bridge over Shingle Creek) | 11-Oct-16 | 21-Oct-18 |
IIBEBO-ST670 | PH IIB - Demo Pile Cap - EB Outside Widening (Bridge over Shingle Creek) | 12-Oct-16 | 21-Oct-18 |
IIBEBO-ST680 | PH IIB - Extract Piles - EB Outside Widening (Bridge over Shingle Creek) | 13-Oct-16 | 21-Oct-18 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 24-Feb-17 | 21-Oct-18 |
IIBEBO-ST710 | PH IIB - Curing for End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 30-Jan-17 | 21-Oct-18 |
IIBEBO-ST720 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over International DR) | 11-Dec-17 | 21-Oct-18 |
IIBEBO-ST730 | PH IIB - Curing for End Bent 3 - EB Outside Widening (Bridge over universal BLVD) | 15-Jun-17 | 21-Oct-18 |
IIBEBO-ST740 | PH IIB - Curing for End Bent 4 - EB Outside Widening (Bridge over Shingle Creek) | 27-Jan-17 | 21-Oct-18 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 21-Mar-17 | 21-Oct-18 |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 31-Jul-17 | 21-Oct-18 |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 21-Aug-17 | 21-Oct-18 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 11-Oct-17 | 21-Oct-18 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 08-Aug-17 | 21-Oct-18 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 09-Apr-18 | 21-Oct-18 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 15-Aug-18 | 21-Oct-18 |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 05-Sep-18 | 22-Oct-18 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 11-Oct-17 | 21-Oct-18 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 01-Feb-18 | 21-Oct-18 |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 07-Aug-17 | 21-Oct-18 |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 29-Oct-17 | 21-Oct-18 |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 01-Sep-17 | 21-Oct-18 |
IIBR-AP160 | PH IIB - Asphalt - Structural - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-AP170 | PH IIB - Asphalt - Structural - Ramp L | 21-Aug-17 | 21-Oct-18 |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 11-May-17 | 21-Oct-18 |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 05-Oct-17 | 21-Oct-18 |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 01-Mar-17 | 21-Oct-18 |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 05-May-17 | 21-Oct-18 |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 21-Jun-17 | 21-Oct-18 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 06-Apr-18 | 24-Oct-18 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 20-Mar-17 | 21-Oct-18 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 09-Oct-17 | 21-Oct-18 |
IIBR-EW150 | PH IIB - Embankment - Ramp I-1 | 18-Sep-17 | 21-Oct-18 |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 28-Nov-16 | 21-Oct-18 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 20-Mar-17 | 21-Oct-18 |
IIBR-EW180 | PH IIB - Embankment - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-EW190 | PH IIB - Embankment - Ramp L | 03-Apr-17 | 21-Oct-18 |
IIBR-EW210 | PH IIB - Embankment - Ramp D | 30-Mar-18 | 21-Oct-18 |
IIBR-GC110 | PH IIB - Demo - Ramp E | 06-Mar-17 | 21-Oct-18 |
IIBR-GC130 | PH IIB - Demo - Ramp R-1 | 21-Mar-17 | 21-Oct-18 |
IIBR-GC140 | PH IIB - Demo - Ramp I-1 | 18-Sep-17 | 21-Oct-18 |
IIBR-GC150 | PH IIB - Demo - Ramp S-1 | 16-Jan-17 | 21-Oct-18 |
IIBR-GC170 | PH IIB - Demo - Ramp C | 12-Oct-17 | 21-Oct-18 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 11-Jan-18 | 21-Oct-18 |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 13-Aug-18 | 21-Oct-18 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 31-Aug-18 | 21-Oct-18 |
IIBR-GC220 | PH IIB - Guardrail (Roadway) - Ramp E | 08-Jan-18 | 21-Oct-18 |
IIBR-GC240 | PH IIB - Demo - Ramp H | 07-Mar-17 | 21-Oct-18 |
IIBR-GC260 | PH IIB - Guardrail (Roadway) - Ramp I-1 | 20-Aug-18 | 21-Oct-18 |
IIBR-GC290 | PH IIB - Demo - Ramp R-2 | 21-Mar-17 | 21-Oct-18 |
IIBR-GC300 | PH IIB - Demo - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-GC310 | PH IIB - Demo - Ramp L | 20-Mar-17 | 21-Oct-18 |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 20-Aug-18 | 21-Oct-18 |
IIBR-GC340 | PH IIB - Performance Turf, SOD - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-GC350 | PH IIB - Demo - Ramp U | 29-Mar-17 | 21-Oct-18 |
IIBR-GC390 | PH IIB - Guardrail (Roadway) - Ramp R | 12-Nov-17 | 21-Oct-18 |
IIBR-GC400 | PH IIB - Guardrail (Roadway) - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-GC450 | PH IIB - Performance Turf, SOD - Ramp U | 17-Aug-17 | 21-Oct-18 |
IIBR-IB180 | PH IIB - Install Bores/Boxes/Ped Signals at Ramp R | 07-Nov-17 | 21-Oct-18 |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 03-May-17 | 21-Oct-18 |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 27-Oct-16 | 21-Oct-18 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 07-Mar-17 | 21-Oct-18 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 28-Sep-16 | 21-Oct-18 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 24-Feb-17 | 22-Oct-18 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 13-Jul-17 | 22-Oct-18 |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 06-Nov-17 | 23-Oct-18 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 13-Nov-17 | 21-Oct-18 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 13-Nov-17 | 25-Oct-18 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 20-Feb-18 | 25-Oct-18 |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 20-Mar-17 | 21-Oct-18 |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 31-Jul-17 | 21-Oct-18 |
IIBR-RW130 | PH IIB - Base - Ramp E | 10-Aug-17 | 21-Oct-18 |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 08-Nov-17 | 21-Oct-18 |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 24-Jul-17 | 21-Oct-18 |
IIBR-RW160 | PH IIB - Base - Ramp C | 20-Nov-17 | 21-Oct-18 |
IIBR-RW170 | PH IIB - Base - Ramp I-1 | 26-Jul-17 | 21-Oct-18 |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 14-Aug-17 | 21-Oct-18 |
IIBR-RW190 | PH IIB - Base - Ramp H | 03-Oct-17 | 21-Oct-18 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 14-Aug-17 | 21-Oct-18 |
IIBR-RW210 | PH IIB - Stabilization - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 22-Aug-17 | 21-Oct-18 |
IIBR-RW230 | PH IIB - Base - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 05-Jul-17 | 21-Oct-18 |
IIBR-RW250 | PH IIB - Base - Ramp L | 17-Jul-17 | 21-Oct-18 |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 03-Apr-17 | 21-Oct-18 |
IIBR-RW270 | PH IIB - Base - Ramp U | 12-Apr-17 | 21-Oct-18 |
IIBR-RW290 | PH IIB - Shoulder Gutter - Ramp C | 15-Oct-17 | 21-Oct-18 |
IIBR-RW320 | PH IIB - Stabilization - Ramp D | 02-Apr-18 | 24-Oct-18 |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 22-Jan-18 | 21-Oct-18 |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 19-Dec-16 | 21-Oct-18 |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 27-Mar-17 | 21-Oct-18 |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 25-Apr-17 | 21-Oct-18 |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 16-Oct-17 | 21-Oct-18 |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 16-Oct-17 | 21-Oct-18 |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 10-May-17 | 21-Oct-18 |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 16-May-17 | 21-Oct-18 |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 16-Oct-17 | 21-Oct-18 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 07-Sep-18 | 21-Oct-18 |
IIBR-SP100 | PH IIB - Drainage - Ramp B | 29-Mar-18 | 05-Nov-18 |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 22-May-17 | 21-Oct-18 |
IIBR-SP120 | PH IIB - Drainage (Temp) - Ramp R-1 | 10-Apr-17 | 21-Oct-18 |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 17-Jul-17 | 21-Oct-18 |
IIBR-SP140 | PH IIB - Drainage (Temp) - Ramp S-1 | 16-Jan-17 | 21-Oct-18 |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 06-Nov-17 | 21-Oct-18 |
IIBR-SP160 | PH IIB - Drainage (Temp) - Ramp H | 31-Jan-17 | 21-Oct-18 |
IIBR-SP170 | PH IIB - Drainage (Temp) - Ramp R-2 | 20-Mar-17 | 21-Oct-18 |
IIBR-SP180 | PH IIB - Drainage (Temp) - Ramp I4 Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-SP190 | PH IIB - Drainage (Temp) - Ramp L | 19-Dec-16 | 21-Oct-18 |
IIBR-SP200 | PH IIB - Drainage (Temp) - Ramp U | 19-Dec-16 | 21-Oct-18 |
IIBR-SP210 | PH IIB - Drainage - Ramp D | 23-Jan-18 | 21-Oct-18 |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 12-Jun-17 | 21-Oct-18 |
IIBR-SP250 | PH IIB - Drainage - Ramp R-2 | 17-Apr-17 | 21-Oct-18 |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 17-Sep-18 | 21-Oct-18 |
IIBR-TC170 | PH IIB - Temp Striping for New Ramp Alignment - Ramp B | 17-Sep-18 | 21-Oct-18 |
IIBR-TC220 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp E | 27-Feb-17 | 21-Oct-18 |
IIBR-TC230 | PH IIB - Temp Striping New Ramp Alignment - Ramp E | 28-Feb-17 | 21-Oct-18 |
IIBR-TC250 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp C | 16-Apr-17 | 21-Oct-18 |
IIBR-TC270 | PH IIB - Temp Striping New Ramp Alignment - Ramp C | 10-Oct-17 | 21-Oct-18 |
IIBR-TC280 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I-1 | 16-Jan-17 | 21-Oct-18 |
IIBR-TC290 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-TC300 | PH IIB - Temp Striping New Ramp Alignment - Ramp I-1 | 23-Feb-17 | 21-Oct-18 |
IIBR-TC310 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp H | 27-Feb-17 | 21-Oct-18 |
IIBR-TC320 | PH IIB - Temp Striping New Ramp Alignment - Ramp H | 28-Feb-17 | 21-Oct-18 |
IIBR-TC330 | PH IIB - Temp Striping New Ramp Alignment - Ramp R-2 | 13-Mar-17 | 21-Oct-18 |
IIBR-TC340 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp R-2 | 09-Mar-17 | 21-Oct-18 |
IIBR-TC360 | PH IIB - Temp Striping New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-TC370 | PH IIB - MOT Shift New Ramp Alignment - Ramp I4- Interstate | 19-Dec-16 | 21-Oct-18 |
IIBR-TC380 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp L | 16-Jan-17 | 21-Oct-18 |
IIBR-TC390 | PH IIB - Temp Striping New Ramp Alignment - Ramp L | 28-Feb-17 | 21-Oct-18 |
IIBR-TC400 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp U | 16-Jan-17 | 21-Oct-18 |
IIBR-TC410 | PH IIB - Temp Striping New Ramp Alignment - Ramp U | 09-Mar-17 | 21-Oct-18 |
IIBR-TC440 | PH IIB - Temp Striping New Ramp Alignment - Ramp D | 10-Apr-17 | 21-Oct-18 |
IIBR-TC450 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp D | 20-Mar-17 | 21-Oct-18 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 07-Dec-16 | 21-Oct-18 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 21-Nov-16 | 21-Oct-18 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 06-Feb-17 | 21-Oct-18 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 06-Feb-17 | 21-Oct-18 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 06-Dec-16 | 21-Oct-18 |
IIBR170 | PH IIB - Construct Ramp U Diversion - Ramp U | 04-Jan-17 | 21-Oct-18 |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 19-Mar-18 | 21-Oct-18 |
IICR-AP120 | PH IIC - Asphalt - Structural - Ramp M | 23-May-18 | 21-Oct-18 |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 04-Oct-16 | 21-Oct-18 |
IICR-EW120 | PH IIC - Embankment - Ramp M | 28-Aug-17 | 21-Oct-18 |
IICR-GC100 | PH IIC - Demo - Ramp S-2 | 18-Dec-17 | 21-Oct-18 |
IICR-GC110 | PH IIC - Performance Turf, SOD - Ramp S-2 | 30-Mar-18 | 21-Oct-18 |
IICR-GC120 | PH IIC - Guardrail (Roadway) - Ramp S | 22-Mar-18 | 21-Oct-18 |
IICR-GC170 | PH IIC - Demo - Ramp M | 05-Feb-18 | 21-Oct-18 |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 24-May-18 | 21-Oct-18 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 02-Jan-18 | 21-Oct-18 |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 12-Feb-18 | 21-Oct-18 |
IICR-RW110 | PH IIC - Base - Ramp S-2 | 28-Feb-18 | 21-Oct-18 |
IICR-RW140 | PH IIC - Base - Ramp M | 03-Apr-18 | 21-Oct-18 |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 02-Mar-18 | 21-Oct-18 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 12-Feb-18 | 21-Oct-18 |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 29-Nov-17 | 21-Oct-18 |
IICR-RW350 | PH IIC - Complete Widening - Ramp I-1 | 27-Nov-17 | 02-Nov-18 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 14-Dec-17 | 21-Oct-18 |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 17-Jul-17 | 21-Oct-18 |
IICR-SP120 | PH IIC - Drainage - Ramp M | 08-Jul-17 | 21-Oct-18 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 18-Jul-17 | 21-Oct-18 |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 10-Jan-18 | 21-Oct-18 |
IICR-TC1020 | PH IIC - Temp Striping New Ramp Alignment - Ramp M | 18-Jan-18 | 21-Oct-18 |
IICR-TC120 | PH IIC - MOT Shift New Ramp Alignment - Ramp E | 16-Jan-18 | 21-Oct-18 |
IICR-TC130 | PH IIC - MOT Shift New Ramp Alignment - Ramp O | 17-Jul-17 | 21-Oct-18 |
IICR-TC140 | PH IIC - MOT Shift for New Ramp Alignment - Ramp C | 19-Dec-16 | 21-Oct-18 |
IICR-TC150 | PH IIC - MOT Shift New Ramp Alignment - Ramp I-1 | 12-Oct-17 | 21-Oct-18 |
IICR-TC160 | PH IIC - Temp Striping New Ramp Alignment - Ramp S-2 | 16-Dec-17 | 21-Oct-18 |
IICR-TC170 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp S-2 | 13-Dec-17 | 21-Oct-18 |
IICR-TC180 | PH IIC - MOT Shift New Ramp Alignment - Ramp H | 06-Dec-17 | 21-Oct-18 |
IICR-TC190 | PH IIC - MOT Shift New Ramp Alignment - Ramp R-2 | 07-Dec-17 | 21-Oct-18 |
IICR-TC200 | PH IIC - MOT Shift New Ramp Alignment - Ramp L | 23-Aug-17 | 21-Oct-18 |
IICR-TC210 | PH IIC - MOT Shift New Ramp Alignment - Ramp U | 24-Oct-17 | 21-Oct-18 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 15-Feb-17 | 21-Oct-18 |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 28-Aug-17 | 21-Oct-18 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 22-Jan-18 | 21-Oct-18 |
IIDEBO-ST150 | PH IID - Curing for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 21-Sep-16 | 21-Oct-18 |
IIDEBO-ST180 | PH IID - Demo Traffic Rails - EB Outside Widening (Bridge over John Young PKWY) | 19-Feb-18 | 21-Oct-18 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 17-Jul-18 | 21-Oct-18 |
IIDEBO-ST200 | PH IID - End Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 08-May-17 | 21-Oct-18 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 30-Jul-18 | 21-Oct-18 |
IIDEBO-ST220 | PH IID - End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 09-May-17 | 21-Oct-18 |
IIDEBO-ST230 | PH IID - Set Beams - EB Outside Widening (Bridge over John Young PKWY) | 27-Feb-18 | 21-Oct-18 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 03-Jun-18 | 21-Oct-18 |
IIDEBO-ST250 | PH IID - Approach Slabs - EB Outside Widening (Bridge over John Young PKWY) | 31-Aug-18 | 21-Oct-18 |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 29-Jan-18 | 21-Oct-18 |
IIDEBO-ST270 | PH IID - Lighting Conduit - EB Outside Widening (Bridge over John Young PKWY) | 13-Sep-18 | 21-Oct-18 |
IIDEBO-ST280 | PH IID - Traffic Railing (32") - EB Outside Widening (Bridge over JYP) | 17-Sep-18 | 21-Oct-18 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 20-Mar-18 | 21-Oct-18 |
IIDEBO-ST330 | PH IID - Superstructure Deck Finish Rebar\Set Screed\ Pour - EB Outside Widening (Bridge over John Young PKWY) | 20-Aug-18 | 21-Oct-18 |
IIDEBO-ST340 | PH IID - Curing for End Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 12-May-17 | 21-Oct-18 |
IIDR-TC100 | PH IID - MOT Shift New Ramp Alignment - Ramp S-1 | 18-Mar-18 | 21-Oct-18 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 10-Jan-17 | 21-Oct-18 |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 05-Mar-18 | 22-Oct-18 |
IIIAR120 | PH IIIA - Construct Ramp Diversion P - Ramp P (Tie-in to SC Diversion) | 12-Oct-17 | 21-Oct-18 |
IIIAWBO-AP100 | PH IIIA - Mill & Resurface (sacrificial) - WB Outside Widening Area (SR528) | 11-Oct-17 | 21-Oct-18 |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 24-Apr-17 | 21-Oct-18 |
IIIAWBO-ST111 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Aug-17 | 21-Oct-18 |
IIIAWBO-ST120 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge over John Young PKWY) | 14-Aug-17 | 21-Oct-18 |
IIIAWBO-ST130 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 25-Aug-17 | 21-Oct-18 |
IIIAWBO-ST140 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Aug-17 | 21-Oct-18 |
IIIAWBO-ST150 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge over John Young PKWY) | 05-Feb-18 | 21-Oct-18 |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 07-Feb-18 | 21-Oct-18 |
IIIAWBO-ST170 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge over John Young PKWY) | 30-Aug-17 | 21-Oct-18 |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 12-Apr-18 | 21-Oct-18 |
IIIAWBO-ST181 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge over John Young PKWY) | 08-Jan-18 | 21-Oct-18 |
IIIAWBO-ST191 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge over John Young PKWY) | 11-Apr-18 | 21-Oct-18 |
IIIAWBO-ST200 | PH IIIA - Wall Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 17-Mar-17 | 21-Oct-18 |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 23-Apr-18 | 21-Oct-18 |
IIIAWBO-ST21 | PH IIIA - Curing for Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 21-Sep-16 | 21-Oct-18 |
IIIAWBO-ST211 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge over John Young PKWY) | 10-Jul-18 | 21-Oct-18 |
IIIAWBO-ST230 | PH IIIA - End Bent 1 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 15-Mar-17 | 21-Oct-18 |
IIIAWBO-ST24 | PH IIIA - Construct Crane Access - WB Outside Widening Area (Bridge over Shingle Creek) | 20-Oct-17 | 21-Oct-18 |
IIIAWBO-ST290 | PH IIIA - Wall Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Apr-17 | 21-Oct-18 |
IIIAWBO-ST33 | PH IIIA - Curing of Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 21-Sep-16 | 21-Oct-18 |
IIIAWBO-ST330 | PH IIIA - End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 05-Apr-17 | 21-Oct-18 |
IIIAWBO-ST340 | PH IIIA - Curing for End Bent 5 - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 19-Apr-17 | 21-Oct-18 |
IIIAWBO-ST410 | PH IIIA - Set Beams - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10-May-17 | 21-Oct-18 |
IIIAWBO-ST420 | PH IIIA - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 15-May-17 | 21-Oct-18 |
IIIAWBO-ST520 | PH IIIA - Superstructure Deck Finish Rebar\Set Screed\ Pour - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 31-May-17 | 21-Oct-18 |
IIIAWBO-ST570 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 02-Aug-17 | 21-Oct-18 |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 13-Dec-17 | 21-Oct-18 |
IIIAWBO-ST590 | PH IIIA - Lighting Conduit - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 17-Aug-17 | 21-Oct-18 |
IIIAWBO-ST600 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 23-Sep-17 | 21-Oct-18 |
IIIAWBO-ST620 | PH IIIA - Grind and Groove - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 01-Nov-17 | 21-Oct-18 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 15-Nov-17 | 21-Oct-18 |
IIIAWBO-TC100 | PH IIIA - Install Sign & Traffic Control Devices - WB Outside Widening Area | 11-Oct-17 | 21-Oct-18 |
IIIAWBO-TC110 | PH IIIA - Temp Striping for Phase - WB Outside Widening Area (SR528) | 11-Oct-17 | 21-Oct-18 |
IIIAWBO-TC120 | PH IIIA - MOT Shift for Phase - WB Outside Widening Area | 11-Oct-17 | 21-Oct-18 |
IIIAWBO-TC130 | PH IIIA - Set Temp Traffic Barriers - WB Outside Widening Area | 04-Oct-17 | 21-Oct-18 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 05-Mar-18 | 22-Oct-18 |
IIIBR-AP110 | PH IIIB - Asphalt - Structural - Ramp J | 03-Apr-18 | 22-Oct-18 |
IIIBR-AP120 | PH IIIB - Asphalt - Structural - Ramp V | 23-Oct-17 | 22-Oct-18 |
IIIBR-AP130 | PH IIIB - Asphalt - Structural - Ramp K | 10-Jan-18 | 22-Oct-18 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 20-Aug-18 | 05-Nov-18 |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 31-Jul-18 | 22-Oct-18 |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 29-May-18 | 22-Oct-18 |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 04-Dec-17 | 21-Oct-18 |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 21-Aug-17 | 21-Oct-18 |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 27-Nov-17 | 22-Oct-18 |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 12-Mar-18 | 22-Oct-18 |
IIIBR-EW120 | PH IIIB - Embankment - Ramp V | 18-May-17 | 22-Oct-18 |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 05-Oct-17 | 22-Oct-18 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 10-May-18 | 22-Oct-18 |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 21-Mar-18 | 22-Oct-18 |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 07-Dec-17 | 21-Oct-18 |
IIIBR-GC140 | PH IIIB - Demo - Ramp J | 13-Nov-17 | 22-Oct-18 |
IIIBR-GC150 | PH IIIB - Performance Turf, SOD - Ramp J | 27-Mar-18 | 22-Oct-18 |
IIIBR-GC180 | PH IIIB - Demo - Ramp V | 28-Mar-17 | 22-Oct-18 |
IIIBR-GC190 | PH IIIB - Demo - Ramp K | 12-Jun-17 | 22-Oct-18 |
IIIBR-GC220 | PH IIIB - Performance Turf, SOD - Ramp K | 28-Mar-18 | 22-Oct-18 |
IIIBR-GC250 | PH IIIB - Demo - Ramp P | 27-Apr-18 | 22-Oct-18 |
IIIBR-GC260 | PH IIIB - Guardrail (Roadway) - Ramp K | 02-Apr-18 | 22-Oct-18 |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 12-Jul-18 | 22-Oct-18 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 02-Aug-18 | 22-Oct-18 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 19-Mar-18 | 22-Oct-18 |
IIIBR-GC370 | PH IIIB - Demo - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 15-Oct-18 | 25-Oct-18 |
IIIBR-GC380 | PH IIIB - Base - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 08-Oct-18 | 25-Oct-18 |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 06-Nov-17 | 21-Oct-18 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 14-Mar-17 | 22-Oct-18 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 02-Apr-18 | 21-Oct-18 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 13-Nov-17 | 21-Oct-18 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 10-Jul-17 | 22-Oct-18 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 26-Jun-17 | 22-Oct-18 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 01-May-18 | 01-Nov-18 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 13-Nov-17 | 08-Nov-18 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 01-Mar-18 | 08-Nov-18 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 16-Oct-17 | 23-Oct-18 |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 06-Apr-18 | 22-Oct-18 |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 20-Dec-17 | 22-Oct-18 |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 08-Jan-18 | 22-Oct-18 |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 30-Oct-17 | 22-Oct-18 |
IIIBR-RW130 | PH IIIB - Base - Ramp J | 02-Nov-17 | 22-Oct-18 |
IIIBR-RW140 | PH IIIB - Stabilization - Ramp V | 02-Oct-17 | 22-Oct-18 |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 04-Oct-17 | 22-Oct-18 |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 18-Oct-17 | 22-Oct-18 |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 31-Oct-17 | 22-Oct-18 |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 23-Oct-17 | 22-Oct-18 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 30-Oct-17 | 22-Oct-18 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 08-Jun-18 | 22-Oct-18 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 17-Jul-18 | 22-Oct-18 |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 09-Apr-18 | 22-Oct-18 |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 10-May-18 | 22-Oct-18 |
IIIBR-RW240 | PH IIIB - Median Wall - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 24-Sep-18 | 25-Oct-18 |
IIIBR-RW250 | PH IIIB - Stabilization - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 12-Oct-18 | 25-Oct-18 |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 05-Jun-18 | 05-Nov-18 |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 29-May-18 | 22-Oct-18 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 10-Sep-18 | 21-Oct-18 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 15-Jun-17 | 21-Oct-18 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 13-Nov-17 | 21-Oct-18 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 19-Dec-16 | 21-Oct-18 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 21-May-18 | 21-Oct-18 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 10-Sep-18 | 21-Oct-18 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 17-Oct-16 | 21-Oct-18 |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 17-Oct-16 | 21-Oct-18 |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 17-Oct-16 | 21-Oct-18 |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 13-Nov-17 | 21-Oct-18 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 10-Sep-18 | 21-Oct-18 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 10-Sep-18 | 25-Oct-18 |
IIIBR-SP100 | PH IIIB - Drainage (Temp) - Ramp G | 17-Jul-17 | 22-Oct-18 |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 08-Feb-18 | 21-Oct-18 |
IIIBR-SP120 | PH IIIB - Drainage (Temp) - Ramp V | 17-Sep-17 | 22-Oct-18 |
IIIBR-SP130 | PH IIIB - Drainage (Temp) - Ramp K | 17-Sep-17 | 22-Oct-18 |
IIIBR-SP140 | PH IIIB - Drainage (Temp) - Ramp T | 19-Dec-16 | 22-Oct-18 |
IIIBR-SP150 | PH IIIB - Drainage - Ramp P | 21-May-18 | 22-Oct-18 |
IIIBR-SP160 | PH IIIB - Drainage (Temp) - Ramp Q | 21-Jan-18 | 21-Oct-18 |
IIIBR-SP170 | PH IIIB - Jack & Bore Pressure Testing (1-15) | 30-Apr-18 | 21-Oct-18 |
IIIBR-SP180 | PH IIIB - Jack & Bore Pressure Testing (16-30) | 03-May-18 | 21-Oct-18 |
IIIBR-SP190 | PH IIIB - Jack & Bore Pressure Testing (31-45) | 07-May-18 | 21-Oct-18 |
IIIBR-TC120 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp G | 08-Nov-17 | 21-Oct-18 |
IIIBR-TC130 | PH IIIB - Temp Striping New Ramp Alignment - Ramp G | 09-Nov-17 | 21-Oct-18 |
IIIBR-TC160 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp J | 17-Sep-17 | 21-Oct-18 |
IIIBR-TC170 | PH IIIB - Temp Striping New Ramp Alignment - Ramp J | 14-Jan-18 | 22-Oct-18 |
IIIBR-TC180 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp V | 19-Apr-17 | 22-Oct-18 |
IIIBR-TC190 | PH IIIB - Temp Striping New Ramp Alignment - Ramp V | 16-Mar-17 | 22-Oct-18 |
IIIBR-TC200 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp K | 17-Sep-17 | 22-Oct-18 |
IIIBR-TC210 | PH IIIB - Temp Striping New Ramp Alignment - Ramp K | 01-May-17 | 22-Oct-18 |
IIIBR-TC230 | PH III C - Temp Striping New Ramp Alignment - Ramp T | 11-Sep-18 | 05-Nov-18 |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 25-Apr-18 | 22-Oct-18 |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 25-Apr-18 | 22-Oct-18 |
IIIBR-TC270 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp Q | 18-Mar-18 | 21-Oct-18 |
IIIBR-TC280 | PH IIIB - Temp Striping New Ramp Alignment - Ramp Q | 18-Mar-18 | 21-Oct-18 |
IIIBR-TC290 | PH IIIB - Shift ramp traffic to completed Shingle bridge and Ramp P | 20-Aug-18 | 22-Oct-18 |
IIIBR-TC300 | PH III C - Shift WB traffic to outside - through JYP bridge | 11-Sep-18 | 07-Nov-18 |
IIIBR100 | PH IIIB - Construct Ramp G Diversion/Temp Pavement - Ramp G | 27-Nov-17 | 21-Oct-18 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 28-Aug-17 | 21-Oct-18 |
IIIBR120 | PH IIIB - Construct Ramp V Diversion - Ramp V | 23-Jan-17 | 22-Oct-18 |
IIIBR130 | PH IIIB - Construct Ramp K Diversion/Temp Pavement - Ramp K | 03-Apr-17 | 22-Oct-18 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 15-Feb-18 | 21-Oct-18 |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 29-May-18 | 21-Oct-18 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 06-Dec-17 | 22-Oct-18 |
IIIBWBO-AP110 | PH IIIB - Asphalt - Median Widening STA 2030+00 to STA 217+00 - (Redundant) | 12-Oct-18 | 25-Oct-18 |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 12-Oct-18 | 22-Oct-18 |
IIIBWBO-EW100 | PH IIIB - Surcharge/ Embankment 1 - WB Outside Widening Area | 01-May-17 | 22-Oct-18 |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 19-May-17 | 22-Oct-18 |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 16-Jun-17 | 22-Oct-18 |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 21-Jul-17 | 22-Oct-18 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 13-Nov-17 | 21-Oct-18 |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 19-Sep-16 | 22-Oct-18 |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 29-Aug-17 | 21-Oct-18 |
IIIBWBO-GC120 | PH IIIB - Guardrail (Roadway) - WB Outside Widening ea side of I-Drive Bridge | 08-Oct-18 | 22-Oct-18 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 06-Nov-17 | 21-Oct-18 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 25-Sep-17 | 21-Oct-18 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 09-Nov-17 | 21-Oct-18 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 27-Nov-17 | 22-Oct-18 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 07-May-18 | 21-Oct-18 |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 24-Sep-18 | 22-Oct-18 |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 04-Oct-18 | 22-Oct-18 |
IIIBWBO-SP120 | PH IIIB - Drainage (International - I4)- WB Outside Widening Area (SR528) | 30-Mar-18 | 21-Oct-18 |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 26-Jun-17 | 21-Oct-18 |
IIIBWBO-SP140 | PH IIIB - Gutter Drainage - STA 332 - 329 (WB Outside) | 21-Jun-18 | 22-Oct-18 |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 27-Jul-17 | 21-Oct-18 |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 15-Aug-17 | 22-Oct-18 |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 22-May-18 | 25-Oct-18 |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 23-Aug-17 | 21-Oct-18 |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 01-Nov-16 | 21-Oct-18 |
IIIBWBO-ST12 | PH IIIB - Curing for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 08-Dec-16 | 21-Oct-18 |
IIIBWBO-ST120 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over Shingle Creek) | 29-May-18 | 21-Oct-18 |
IIIBWBO-ST13 | PH IIIB - Removal for Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Uni | 15-Dec-16 | 21-Oct-18 |
IIIBWBO-ST130 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Jun-18 | 21-Oct-18 |
IIIBWBO-ST14 | PH IIIB - Temp Sheet Pile Removal - WB Outside Widening Area (Bridge over universal BLVD) | 16-Dec-16 | 21-Oct-18 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 04-Jun-18 | 21-Oct-18 |
IIIBWBO-ST150 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jul-18 | 21-Oct-18 |
IIIBWBO-ST171 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over International DR) | 21-Aug-17 | 21-Oct-18 |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 27-Jun-17 | 21-Oct-18 |
IIIBWBO-ST190 | PH IIIB - Demo Traffic Rails - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Oct-17 | 21-Oct-18 |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 18-Mar-18 | 21-Oct-18 |
IIIBWBO-ST211 | PH IIIB - Backwall Bent 1 - WB Outside Widening Area (Bridge over International Dr) | 17-May-18 | 21-Oct-18 |
IIIBWBO-ST220 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 05-Jul-17 | 21-Oct-18 |
IIIBWBO-ST240 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 | 21-Oct-18 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 30-Apr-18 | 21-Oct-18 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 29-Nov-17 | 21-Oct-18 |
IIIBWBO-ST260 | PH IIIB - Wall Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 30-Jun-17 | 21-Oct-18 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 05-Dec-17 | 21-Oct-18 |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 03-Jan-18 | 21-Oct-18 |
IIIBWBO-ST280 | PH IIIB - Backwall Bent 3 - WB Outside Widening Area (Bridge over International DR) | 01-May-18 | 21-Oct-18 |
IIIBWBO-ST300 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 27-Jun-17 | 21-Oct-18 |
IIIBWBO-ST310 | PH IIIB - End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 24-Apr-18 | 21-Oct-18 |
IIIBWBO-ST320 | PH IIIB - Curing for Pier 2, 3, (Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 22-Feb-18 | 21-Oct-18 |
IIIBWBO-ST330 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over universal BLVD) | 08-Jul-17 | 21-Oct-18 |
IIIBWBO-ST340 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Universal BLVD) | 18-Jul-17 | 21-Oct-18 |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 24-Jul-17 | 21-Oct-18 |
IIIBWBO-ST360 | PH IIIB - Remove Concrete Forms for Pier 2, 3,(Pile Cap) - WB Outside Widening Area (Bridge over Shingl | 02-Mar-18 | 21-Oct-18 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 28-Feb-18 | 21-Oct-18 |
IIIBWBO-ST380 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over International Drive) | 23-May-18 | 21-Oct-18 |
IIIBWBO-ST390 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over International Drive) | 02-Jul-18 | 21-Oct-18 |
IIIBWBO-ST400 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 26-Feb-18 | 21-Oct-18 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 01-May-18 | 21-Oct-18 |
IIIBWBO-ST430 | PH IIIB - Wall Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 06-Feb-18 | 21-Oct-18 |
IIIBWBO-ST440 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over universal BLVD) | 03-Oct-17 | 21-Oct-18 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 27-Nov-17 | 21-Oct-18 |
IIIBWBO-ST460 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over universal BLVD) | 12-Oct-17 | 21-Oct-18 |
IIIBWBO-ST470 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over universal BLVD) | 20-Oct-17 | 21-Oct-18 |
IIIBWBO-ST480 | PH IIIB - End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 31-Jan-18 | 21-Oct-18 |
IIIBWBO-ST490 | PH IIIB - Approach Slabs - WB Outside Widening Area (Bridge over International DR) | 20-Aug-18 | 21-Oct-18 |
IIIBWBO-ST510 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over universal BLVD) | 02-Nov-17 | 21-Oct-18 |
IIIBWBO-ST520 | PH IIIB - Curing for End Bent 4 - WB Outside Widening Area (Bridge over Shingle Creek) | 09-Feb-18 | 21-Oct-18 |
IIIBWBO-ST530 | PH IIIB - Lighting Conduit - WB Outside Widening Area (Bridge over International DR) | 13-Sep-18 | 21-Oct-18 |
IIIBWBO-ST540 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over International DR) | 17-Sep-18 | 21-Oct-18 |
IIIBWBO-ST550 | PH IIIB - Grind and Groove - WB Outside Widening Area (Bridge over International DR) | 26-Sep-18 | 21-Oct-18 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 02-Mar-18 | 21-Oct-18 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 23-Mar-18 | 21-Oct-18 |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 23-Aug-17 | 21-Oct-18 |
IIIBWBO-ST640 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over universal BLVD) | 05-Jul-17 | 21-Oct-18 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 | 21-Oct-18 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 | 21-Oct-18 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 27-Oct-17 | 21-Oct-18 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 01-Nov-17 | 21-Oct-18 |
IIIBWBO-ST690 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over International Drive) | 08-Jul-18 | 21-Oct-18 |
IIIBWBO-ST700 | PH IIIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - WB Outside Widening Area (Bridge over Shingle Creek) | 03-May-18 | 21-Oct-18 |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 15-Jan-18 | 21-Oct-18 |
IIIBWBO-ST8 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over universal BLVD) | 28-Oct-16 | 21-Oct-18 |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 16-Aug-17 | 21-Oct-18 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 16-Aug-17 | 21-Oct-18 |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 27-Mar-18 | 22-Oct-18 |
IIIBWBO-W101 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over Universal BLVD) | 13-Nov-17 | 21-Oct-18 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 03-Jul-18 | 21-Oct-18 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 05-Jun-18 | 22-Oct-18 |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 04-Apr-18 | 22-Oct-18 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 05-Jun-18 | 22-Oct-18 |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 26-Jul-18 | 22-Oct-18 |
IIIC-CP10 | PH IIIC - Construct Ped. Signalization at Ramps G&F | 12-Nov-17 | 23-Oct-18 |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 07-Jun-18 | 21-Oct-18 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 24-May-18 | 21-Oct-18 |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 12-Feb-18 | 21-Oct-18 |
IIICR-GC110 | PH IIIC - Demo - Ramp N | 06-Feb-18 | 21-Oct-18 |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 02-Jun-18 | 21-Oct-18 |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 22-May-18 | 21-Oct-18 |
IIICR-RW110 | PH IIIC - Base - Ramp F | 29-May-18 | 21-Oct-18 |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 14-Mar-18 | 21-Oct-18 |
IIICR-RW130 | PH IIIC - Base - Ramp N | 09-Apr-18 | 21-Oct-18 |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 22-Mar-18 | 21-Oct-18 |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 28-Jul-17 | 21-Oct-18 |
IIICR-TC120 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp F | 27-Apr-18 | 21-Oct-18 |
IIICR-TC140 | PH IIIC - Set Temp Traffic Barriers (Shoulder) - Ramp N | 19-Mar-18 | 21-Oct-18 |
IIICR-TC150 | PH IIIC - Temp Striping New Ramp Alignment - Ramp N | 19-Mar-18 | 21-Oct-18 |
IIICR100 | PH IIIC - Construct Ramp F Diversion - Ramp F | 02-Apr-18 | 21-Oct-18 |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 29-Aug-17 | 21-Oct-18 |
IIICR130 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp G | 03-May-18 | 23-Oct-18 |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 18-Mar-18 | 22-Oct-18 |
IIICR150 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp N | 02-Jul-18 | 21-Oct-18 |
IIICR160 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp K | 01-Mar-18 | 22-Oct-18 |
IIICR170 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp P | 21-Aug-18 | 22-Oct-18 |
IIICR190 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp Q | 12-Jun-18 | 24-Oct-18 |
IIICR200 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp V | 05-Dec-17 | 22-Oct-18 |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 16-Oct-17 | 21-Oct-18 |
IIICWBO-ST220 | PH IIIA - Demo Bridge Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 25-Oct-17 | 21-Oct-18 |
ITS10-1000 | Issue Identification | 15-May-18 | 21-Oct-18 |
ITS10-1010 | NOI submitted - Potential Delay to Project Schedule | 31-Jul-18 | 21-Oct-18 |
ITS10-1020 | Plan Revision 10 Officially transmitted | 22-Aug-18 | 21-Oct-18 |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 23-Aug-18 | 21-Oct-18 |
ITS10-1040 | Fabrication and Delivery - Conduits | 05-Oct-18 | 21-Oct-18 |
ITS10-1050 | Prepare & Submit - 639 ITS Standby Generator Product Data & Shop Drawings | 20-Aug-18 | 21-Oct-18 |
ITS10-1060 | Review and Approve - 639 ITS Standby Generator Product Data & Shop Drawings | 29-Aug-18 | 21-Oct-18 |
ITS10-1070 | Fabrication & Delivery - ITS Standby Generators | 05-Oct-18 | 21-Oct-18 |
ITS10-1110 | Fabrication and Delivery - Conductors | 05-Oct-18 | 21-Oct-18 |
ITS10-1140 | Fabrication & Delivery - Step Up / Step Down Transformers | 05-Oct-18 | 21-Oct-18 |
IVEBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 EB Express | 08-Oct-18 | 30-Oct-18 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 09-Apr-18 | 30-Oct-18 |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 22-May-18 | 23-Oct-18 |
IVEBM-W170 | PH IV - Median Wall - Excavate - Station 259+50 to 311 | 20-Aug-18 | 30-Oct-18 |
IVEBM-W180 | PH IV - Median Wall - FFP Stem - Station 259+50 to 311 | 20-Aug-18 | 30-Oct-18 |
IVEBM-W190 | PH IV - Median Wall - Rebar/ slip Top - Station 259+50 to 311 | 27-Aug-18 | 30-Oct-18 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 01-Oct-18 | 30-Oct-18 |
IVEBM-W240 | PH IV - Median Wall - FFP Stem Station 311 to 332 | 04-Oct-18 | 30-Oct-18 |
IVEBM-W250 | PH IV - Median Wall - Rebar/ slip Top Station 311 to 332 | 17-Oct-18 | 30-Oct-18 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 04-Oct-18 | 14-Nov-18 |
IVEBM-W270 | PH IV - Median Wall - FFP FOOTER+Stem Station 335 to 352 | 12-Oct-18 | 14-Nov-18 |
IVEBM-W280 | PH IV - Median Wall - Rebar/ slip Top Station 335 to 352 | 19-Oct-18 | 14-Nov-18 |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 05-Mar-18 | 21-Oct-18 |
IVR-EC30 | PH IV - Erect Cantilevers (10-15) | 13-May-18 | 21-Oct-18 |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 17-Apr-18 | 22-Oct-18 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 06-May-18 | 21-Oct-18 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 15-Oct-18 | 21-Oct-18 |
IVWBM-AP110 | PH IV - Asphalt - Structural - Station 259+50 to 311 WB Express | 08-Oct-18 | 30-Oct-18 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 05-Apr-18 | 25-Oct-18 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 21-May-18 | 21-Oct-18 |
IVWBM-RW170 | PH IV - Base - Station 259+50 to 311 WB Express | 24-Sep-18 | 30-Oct-18 |
IVWBM-RW230 | PH IV - Grade for road - Station 259+50 to 311 EB Express | 29-Aug-18 | 30-Oct-18 |
IVWBM-RW240 | PH IV - Stabilization - Station 259+50 to 311 EB Express | 05-Sep-18 | 30-Oct-18 |
IVWBM-RW250 | PH IV - Base - Station 259+50 to 311 EB Express | 24-Sep-18 | 30-Oct-18 |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | 04-Apr-18 | 23-Oct-18 |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 05-Mar-18 | 21-Oct-18 |
PRE-FA-001 | Fabricate and Deliver 506 Bridge Drainage System | 25-Jan-17 | 21-Oct-18 |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 07-Apr-17 | 21-Oct-18 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 17-Jul-17 | 21-Oct-18 |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 09-Mar-17 | 21-Oct-18 |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 17-Jul-17 | 21-Oct-18 |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 20-Mar-17 | 21-Oct-18 |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 27-Feb-17 | 21-Oct-18 |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 22-May-17 | 21-Oct-18 |
PRE-FA-026 | Fabricate and Deliver 653 Pedestrian Signals | 07-Apr-17 | 21-Oct-18 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 29-Sep-17 | 21-Oct-18 |
PRE-FA-028 | Fabricate and Deliver 665 Pedestrian Detector | 07-Apr-17 | 21-Oct-18 |
PRE-FA-029 | Fabricate and Deliver 033000 Cast-In-Place Concrete | 15-May-17 | 21-Oct-18 |
PRE-FA-030 | Fabricate and Deliver 042200 Masonry | 20-Jun-17 | 21-Oct-18 |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 16-Jan-17 | 21-Oct-18 |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 16-Jan-17 | 21-Oct-18 |
PRE-FA-033 | Fabricate and Deliver 101400 Signage | 30-May-17 | 21-Oct-18 |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 05-May-17 | 21-Oct-18 |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 05-May-17 | 21-Oct-18 |
PRE-FA-036 | Fabricate and Deliver 232000 Piping and Specialties | 25-Jan-17 | 21-Oct-18 |
PRE-FA-037 | Fabricate and Deliver 233113 Ductwork Product Data and Shop Drawing | 22-May-17 | 21-Oct-18 |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 17-Jan-17 | 21-Oct-18 |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 09-Feb-17 | 21-Oct-18 |
PRE-FA-040 | Fabricate and Deliver 264113 Lighting Protection System Product Data and Shop Drawing | 19-Apr-17 | 21-Oct-18 |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 18-May-17 | 21-Oct-18 |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 09-Jun-17 | 21-Oct-18 |
PRE-PS-017 | Prepare and Submit 646 Aluminum Pedestal Poles | 20-Mar-17 | 21-Oct-18 |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 18-Nov-16 | 21-Oct-18 |
PRE-PS-026 | Prepare and Submit 653 Pedestrian Signals | 20-Mar-17 | 21-Oct-18 |
PRE-PS-028 | Prepare and Submit 665 Pedestrian Detector | 20-Mar-17 | 21-Oct-18 |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 26-Sep-16 | 21-Oct-18 |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 20-Feb-17 | 21-Oct-18 |
PRE-PS-031 | Prepare and Submit 081100 Metal Doors and Frames | 19-Oct-16 | 21-Oct-18 |
PRE-PS-032 | Prepare and Submit 099100 Painting Product Data and Sample | 19-Oct-16 | 21-Oct-18 |
PRE-PS-033 | Prepare and Submit 101400 Signage | 27-Feb-17 | 21-Oct-18 |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 13-Feb-17 | 21-Oct-18 |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 13-Feb-17 | 21-Oct-18 |
PRE-PS-036 | Prepare and Submit 232000 Piping and Specialties | 16-Jan-17 | 21-Oct-18 |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 20-Feb-17 | 21-Oct-18 |
PRE-PS-038 | Prepare and Submit 238119 Packaged Air Conditioners | 09-Jan-17 | 21-Oct-18 |
PRE-PS-039 | Prepare and Submit 260536 Cable Trays | 16-Jan-17 | 21-Oct-18 |
PRE-PS-040 | Prepare and Submit 264113 Lighting Protection System Product Data and Shop Drawing | 20-Mar-17 | 21-Oct-18 |
PRE-RA-001 | Review and Approve 506 Bridge Drainage System | 19-Jan-17 | 21-Oct-18 |
PRE-RA-017 | Review and Approve 646 Aluminum Pedestal Poles | 23-Mar-17 | 21-Oct-18 |
PRE-RA-018 | Review and Approve 650 Traffic Signals | 23-Mar-17 | 21-Oct-18 |
PRE-RA-022 | Review and Approve 133420 Pre-Engineered Precast Concrete Structure | 12-Jan-17 | 21-Oct-18 |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 01-Feb-17 | 21-Oct-18 |
PRE-RA-026 | Review and Approve 653 Pedestrian Signals | 23-Mar-17 | 21-Oct-18 |
PRE-RA-028 | Review and Approve 665 Pedestrian Detector | 23-Mar-17 | 21-Oct-18 |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 26-Oct-16 | 21-Oct-18 |
PRE-RA-030 | Review and Approve 042200 Masonry | 20-Jun-17 | 21-Oct-18 |
PRE-RA-031 | Review and Approve 081100 Metal Doors and Frames | 26-Oct-16 | 21-Oct-18 |
PRE-RA-032 | Review and Approve 099100 Painting Product Data and Sample | 26-Oct-16 | 21-Oct-18 |
PRE-RA-033 | Review and Approve 101400 Signage | 29-Mar-17 | 21-Oct-18 |
PRE-RA-034 | Review and Approve 231113 Fuel Oil Piping | 21-Apr-17 | 21-Oct-18 |
PRE-RA-035 | Review and Approve 231323 Aboveground Diesel Storage Tank and Piping | 28-Mar-17 | 21-Oct-18 |
PRE-RA-036 | Review and Approve 232000 Piping and Specialties | 18-Jan-17 | 21-Oct-18 |
PRE-RA-037 | Review and Approve 233113 Ductwork Product Data and Shop Drawing | 22-May-17 | 21-Oct-18 |
PRE-RA-038 | Review and Approve 238119 Packaged Air Conditioners | 12-Jan-17 | 21-Oct-18 |
PRE-RA-039 | Review and Approve 260536 Cable Trays | 18-Jan-17 | 21-Oct-18 |
PRE-RA-040 | Review and Approve 264113 Lighting Protection System Product Data and Shop Drawing | 28-Mar-17 | 21-Oct-18 |
TF-CO-001 | Foundation (FRP SOG) | 19-Jun-17 | 21-Oct-18 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 23-May-17 | 21-Oct-18 |
TF-CO-004 | Precast Erection | 27-Jun-17 | 21-Oct-18 |
TF-CO-005 | Install Upright 2 D.S. | 22-Mar-17 | 21-Oct-18 |
TF-CO-006 | FRP Conc. Roof Dec/c | 27-Jun-17 | 21-Oct-18 |
TF-CO-007 | Install Upright 3 D.S. | 24-Mar-17 | 21-Oct-18 |
TF-CO-008 | Constr. Pedestal | 26-Jun-17 | 21-Oct-18 |
TF-CO-009 | Const. Roof System | 27-Jun-17 | 21-Oct-18 |
TF-CO-010 | FRP Conc. Pad (Generator) | 14-Aug-17 | 21-Oct-18 |
TF-CO-011 | AS Build D.S. | 30-Mar-17 | 21-Oct-18 |
TF-CO-012 | Install Frames & Doors | 27-Jun-17 | 21-Oct-18 |
TF-CO-013 | Const. Screen Wall (Con.) | 20-Jun-17 | 21-Oct-18 |
TF-CO-014 | Pull Wire & Install Light Fixtures | 12-Nov-17 | 21-Oct-18 |
TF-CO-015 | Install HVAC | 27-Jun-17 | 21-Oct-18 |
TF-CO-016 | F+1 Generator | 13-Nov-17 | 21-Oct-18 |
TF-CO-017 | F+1 Fuel Tank | 13-Nov-17 | 21-Oct-18 |
TF-CO-018 | Install Lighting | 12-Nov-17 | 21-Oct-18 |
TF-CO-019 | Install Security System | 12-Nov-17 | 21-Oct-18 |
TF-CO-020 | Install Lightning Protection | 12-Nov-17 | 21-Oct-18 |
TF-CO-022 | Construct Sidewalk | 14-Aug-17 | 21-Oct-18 |
TF-CO-023 | Erect Truss | 04-Dec-17 | 21-Oct-18 |
TF-CO-024 | Wall Treatments (Ply) | 12-Nov-17 | 21-Oct-18 |
TF-CO-025 | Install Equip. Arm Supports | 04-Dec-17 | 21-Oct-18 |
TF-CO-026 | Cont. Lightning | 22-Jan-18 | 26-Oct-18 |
TF-CO-027 | Cont. HVAC | 22-Jan-18 | 26-Oct-18 |
TF-CO-029 | Install Conduit/Raceways | 04-Dec-17 | 21-Oct-18 |
TF-CO-030 | Pull Wire | 17-Sep-18 | 29-Oct-18 |
TF-CO-031 | Toll Facility Finishes and Punchlist | 19-Oct-18 | 21-Oct-18 |
TF-FA-001 | Fabricate and Deliver Precast Erection | 30-Jan-17 | 21-Oct-18 |
TF-RA-001 | Review and Approve Precast Erection | 12-Jan-17 | 21-Oct-18 |
We noticed that 418 activities took longer than it was originally anticipated. The following table compares original and actual durations for some of the completed activities. This table should be used as a tool to review the durations for similar activities not yet started.
Activity ID | Activity Description | Original Duration | Actual Duration |
---|---|---|---|
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 5 | 18 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 18 | 56 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 20 | 63 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 20 | 138 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 20 | 25 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 20 | 57 |
IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | 20 | 117 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 20 | 212 |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 20 | 93 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 15 | 194 |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 6 | 28 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 20 | 32 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 20 | 21 |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 20 | 109 |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 12 | 14 |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 18 | 24 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 14 | 101 |
GC-GCN220 | Written Suspend order - FOC related to pending change | 50 | 91 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 4 | 5 |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 3 | 18 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 20 | 31 |
TF-CO-014 | Pull Wire & Install Light Fixtures | 15 | 45 |
TF-CO-018 | Install Lighting | 22 | 45 |
TF-CO-019 | Install Security System | 22 | 45 |
TF-CO-020 | Install Lightning Protection | 10 | 45 |
TF-CO-023 | Erect Truss | 5 | 7 |
TF-CO-024 | Wall Treatments (Ply) | 22 | 45 |
TF-CO-027 | Cont. HVAC | 25 | 80 |
TF-FA-001 | Fabricate and Deliver Precast Erection | 20 | 148 |
IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | 20 | 238 |
IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | 15 | 233 |
IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | 10 | 490 |
IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | 15 | 208 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 4 | 13 |
IIAR-EW100 | PH IIB - Embankment - Ramp O | 20 | 347 |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 1 | 10 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 4 | 6 |
IIAR-RW110 | PH IIB - Base - Ramp O | 8 | 30 |
IIAR-SP110 | PH IIB - Drainage - Ramp O | 20 | 194 |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 3 | 37 |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 11 | 375 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 2 | 63 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 4 | 114 |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 2 | 3 |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 2 | 73 |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 2 | 62 |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 2 | 109 |
IIBR-EW110 | PH IIB - Embankment - Ramp E | 5 | 300 |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 5 | 205 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 5 | 108 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 4 | 47 |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 5 | 86 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 5 | 19 |
IIBR-EW200 | PH IIB - Embankment - Ramp U | 5 | 321 |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 1 | 2 |
IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | 22 | 156 |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 22 | 124 |
IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | 20 | 353 |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 20 | 365 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 20 | 77 |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 20 | 69 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 16 | 91 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 14 | 91 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 10 | 29 |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 2 | 54 |
IIBR-RW130 | PH IIB - Base - Ramp E | 8 | 41 |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 12 | 28 |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 2 | 4 |
IIBR-RW160 | PH IIB - Base - Ramp C | 22 | 42 |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 2 | 53 |
IIBR-RW190 | PH IIB - Base - Ramp H | 8 | 27 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 2 | 3 |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 8 | 37 |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 2 | 7 |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 2 | 4 |
IIBR-RW270 | PH IIB - Base - Ramp U | 8 | 30 |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 14 | 89 |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 20 | 354 |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 20 | 242 |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 20 | 221 |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 14 | 100 |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 7 | 100 |
IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | 18 | 236 |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 19 | 249 |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 18 | 243 |
IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 20 | 305 |
IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 20 | 293 |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 20 | 123 |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 10 | 12 |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 10 | 65 |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 10 | 41 |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 7 | 25 |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 2 | 4 |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 5 | 344 |
IICR-EW120 | PH IIC - Embankment - Ramp M | 5 | 147 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 10 | 43 |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 2 | 14 |
IICR-RW140 | PH IIC - Base - Ramp M | 8 | 26 |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 2 | 22 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 8 | 28 |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 8 | 54 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 8 | 43 |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 5 | 148 |
IICR-SP120 | PH IIC - Drainage - Ramp M | 10 | 212 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 15 | 25 |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 6 | 79 |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 16 | 154 |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 14 | 30 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 2 | 3 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 4 | 7 |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 20 | 235 |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 20 | 233 |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 20 | 219 |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 20 | 443 |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 42 | 634 |
PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | 35 | 325 |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 56 | 59 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 56 | 143 |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 126 | 442 |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 56 | 453 |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 140 | 154 |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 84 | 120 |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 84 | 213 |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 42 | 575 |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 42 | 511 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 30 | 95 |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 56 | 217 |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 42 | 162 |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 70 | 206 |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 84 | 216 |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 42 | 216 |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 42 | 111 |
PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | 42 | 511 |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 56 | 105 |
PRE-FA-044 | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable | 56 | 624 |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 56 | 80 |
PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | 42 | 789 |
PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | 70 | 498 |
PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | 28 | 164 |
PRE-PS-006 | Prepare and Submit Precast Erection | 28 | 223 |
PRE-PS-016 | Prepare and Submit 641 Prestressed Concrete Poles | 28 | 407 |
PRE-PS-018 | Prepare and Submit 650 Traffic Signals | 28 | 402 |
PRE-PS-019 | Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead) | 28 | 421 |
PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | 28 | 223 |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 28 | 75 |
PRE-PS-024 | Prepare and Submit 633 Communication Cable | 28 | 455 |
PRE-PS-027 | Prepare and Submit 663 Signal Priority and Preemption Systems | 28 | 594 |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 28 | 30 |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 28 | 120 |
PRE-PS-033 | Prepare and Submit 101400 Signage | 28 | 30 |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 28 | 67 |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 28 | 43 |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 28 | 91 |
PRE-PS-041 | Prepare and Submit 682 CCTV Camera | 28 | 205 |
PRE-PS-045 | Prepare and Submit 660 ITS Vehicle Detection System | 28 | 240 |
PRE-PS-049 | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing | 28 | 372 |
PRE-RA-016 | Review and Approve 641 Prestressed Concrete Poles | 45 | 434 |
PRE-RA-019 | Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead) | 45 | 469 |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 45 | 110 |
PRE-RA-024 | Review and Approve 633 Communication Cable | 45 | 478 |
PRE-RA-025 | Review and Approve 635 Pull, Splice, & Junction Boxes | 45 | 346 |
PRE-RA-027 | Review and Approve 663 Signal Priority and Preemption Systems | 45 | 591 |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 45 | 224 |
PRE-RA-041 | Review and Approve 682 CCTV Camera | 45 | 210 |
PRE-RA-042 | Review and Approve 781 DMS | 45 | 266 |
PRE-RA-044 | Review and Approve 633 ITS Fiber Optic Cable | 45 | 226 |
PRE-RA-045 | Review and Approve 660 ITS Vehicle Detection System | 45 | 309 |
PRE-RA-049 | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing | 45 | 363 |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 3 | 6 |
IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 222 |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 247 |
IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | 8 | 150 |
IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | 3 | 299 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 193 |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 188 |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 1 | 3 |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 15 | 26 |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 3 | 4 |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 22 | 34 |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 2 | 7 |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 15 | 49 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 15 | 32 |
IBEBO-EW130 | PH IB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 20 | 567 |
IBEBO-EW140 | PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside Widening | 20 | 566 |
IBEBO-EW150 | PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside Widening | 20 | 546 |
IBEBO-EW160 | PH IB - Pond Excav/Embank Universal to JYP - EB Outside Widening | 20 | 538 |
IBEBO-EW170 | PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside Widening | 20 | 171 |
IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | 15 | 343 |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 7 | 76 |
IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 255 |
IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 283 |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 8 | 42 |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 8 | 41 |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 237 |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 226 |
IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | 20 | 149 |
IBWBM-SP110 | PH IB - Drainage for JYP to STA 390 | 20 | 181 |
IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | 20 | 136 |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 2 | 3 |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 15 | 50 |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 3 | 4 |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 22 | 42 |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 2 | 7 |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 15 | 33 |
IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | 3 | 10 |
IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | 20 | 149 |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 20 | 256 |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 20 | 54 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 1 | 7 |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 10 | 77 |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 3 | 162 |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 7 | 157 |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 10 | 23 |
IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | 8 | 187 |
IIBEBO-ST26 | PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ov | 3 | 43 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 22 | 41 |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | 10 | 193 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 20 | 106 |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 15 | 126 |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 15 | 118 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 15 | 82 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 10 | 136 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 22 | 83 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 22 | 37 |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 10 | 14 |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 18 | 46 |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 18 | 22 |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 18 | 237 |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 10 | 391 |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 6 | 18 |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 1 | 2 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 3 | 44 |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 2 | 14 |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 2 | 3 |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 5 | 12 |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 5 | 11 |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 5 | 51 |
IIIBR-EW140 | PH IIIB - Embankment - Ramp T | 5 | 547 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 5 | 21 |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 5 | 48 |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 2 | 7 |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 1 | 27 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 2 | 12 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 2 | 3 |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 6 | 131 |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 25 | 42 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 20 | 470 |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 2 | 47 |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 2 | 4 |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 8 | 9 |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 2 | 8 |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 8 | 42 |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 2 | 173 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 5 | 17 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 10 | 19 |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 2 | 35 |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 8 | 40 |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 8 | 92 |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 5 | 92 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 20 | 241 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 10 | 135 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 20 | 333 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 12 | 30 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 20 | 357 |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 20 | 357 |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 20 | 357 |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 20 | 91 |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 10 | 31 |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 1 | 2 |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 1 | 2 |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 3 | 5 |
IIIBWBO-ST4 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR) | 11 | 491 |
IIIBWBO-ST5 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR) | 20 | 58 |
IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | 3 | 204 |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 2 | 4 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 2 | 6 |
IIICR-EW100 | PH IIIC - Embankment - Ramp F | 5 | 538 |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 5 | 25 |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 2 | 20 |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 2 | 4 |
IIICR-RW110 | PH IIIC - Base - Ramp F | 8 | 9 |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 2 | 17 |
IIICR-RW130 | PH IIIC - Base - Ramp N | 8 | 20 |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 10 | 38 |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 10 | 163 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 20 | 137 |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 4 | 30 |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 20 | 146 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 4 | 69 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 3 | 66 |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 20 | 134 |
IIAEBO-TC100 | PH IIA - Install Sign & Traffic Control Devices - EB Outside Widening | 1 | 260 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 4 | 75 |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 8 | 193 |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 4 | 189 |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 4 | 11 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 20 | 168 |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 15 | 97 |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 20 | 109 |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 5 | 134 |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 10 | 60 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 2 | 5 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 22 | 54 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 22 | 223 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 14 | 178 |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 22 | 76 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 15 | 162 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 8 | 108 |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 7 | 160 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 6 | 18 |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 8 | 40 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 8 | 41 |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 20 | 76 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 20 | 119 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 20 | 189 |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 10 | 226 |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 3 | 154 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 20 | 40 |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 5 | 12 |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 8 | 13 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 4 | 8 |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 15 | 16 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 5 | 9 |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 4 | 39 |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 15 | 18 |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 1 | 9 |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 5 | 7 |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10 | 36 |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 4 | 5 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 5 | 8 |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 1 | 2 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 10 | 14 |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 4 | 7 |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 5 | 13 |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 5 | 13 |
IIBEBO-ST690 | PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 20 | 91 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 15 | 26 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 10 | 27 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 22 | 186 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 16 | 303 |
IIDEBO-ST160 | PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP) | 3 | 5 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 5 | 7 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 5 | 8 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 15 | 25 |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 5 | 9 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 10 | 38 |
IIDEBO-ST310 | PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 20 | 52 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 10 | 37 |
IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 16 | 246 |
IIIAWBO-ST22 | PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T | 3 | 8 |
IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 276 |
IIIAWBO-ST34 | PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John | 3 | 8 |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 18 | 37 |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 2 | 5 |
IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | 7 | 202 |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 20 | 23 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 10 | 48 |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 20 | 36 |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 15 | 63 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 22 | 34 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 7 | 54 |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 15 | 33 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 15 | 48 |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 10 | 17 |
USDED-CO-002 | Duke Energy Distribution (B) | 77 | 595 |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 10 | 52 |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 46 |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 5 | 6 |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 3 | 5 |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10 | 32 |
IIIAWBO-ST690 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10 | 27 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 5 | 14 |
IIIAWBO-ST710 | PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 53 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 10 | 223 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 20 | 222 |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 2 | 6 |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 18 | 19 |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 17 | 24 |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 17 | 22 |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 20 | 654 |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 20 | 531 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 20 | 128 |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 15 | 418 |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 10 | 194 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 20 | 159 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 20 | 152 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 20 | 126 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 10 | 175 |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 10 | 148 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 10 | 76 |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 4 | 9 |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 4 | 6 |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 22 | 509 |
IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | 22 | 450 |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 10 | 136 |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 4 | 110 |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 5 | 200 |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 5 | 86 |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 15 | 30 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 4 |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 2 | 3 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 7 | 16 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 15 | 54 |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 20 | 21 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 8 | 11 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 7 | 11 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 8 | 11 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 4 | 14 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 20 | 30 |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 5 | 143 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 6 | 43 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 2 | 43 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 43 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 43 |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 5 | 8 |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 3 | 40 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 4 | 111 |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 4 | 7 |
We noticed that 551 activities took longer than it was originally anticipated. The following table compares original and actual durations for some of the completed activities. This table should be used as a tool to review the durations for similar activities not yet started.
Activity ID | Activity Description | Original Duration | Actual Duration |
---|---|---|---|
IIAR100 | PH IIA - Construct Ramp O Diversion - Ramp O | 9 | 25 |
IIAR110 | PH IIA - Construct Ramp O Diversion - Ramp O (Tie in to EB) | 5 | 18 |
IIBR100 | PH IIB - Construct Ramp E Diversion - Ramp E | 18 | 56 |
IIBR110 | PH IIB - Construct Ramp I-1 Diversion - Ramp I-1 | 20 | 63 |
IIBR120 | PH IIB - Construct Ramp R-1 Diversion - Ramp R-1 | 20 | 138 |
IIBR140 | PH IIB - Construct Ramp R-2 Diversion - Ramps R-2 | 20 | 25 |
IIBR150 | PH IIB - Construct Ramp H Diversion - Ramp H | 20 | 57 |
IIBR151 | PH IIB - Construct Ramp L Diversion - Ramp L | 20 | 117 |
IICR100 | PH IIC - Construct Ramp S-2 Diversion - Ramp S-2 | 20 | 212 |
IICR120 | PH IIC - Construct Ramp M Diversion - Ramp M | 20 | 93 |
IIIAR100 | PH IIIA - Construct Ramp Diversion P - Ramp P (STA 2013+84 to 2005+50) | 15 | 194 |
IIIAR110 | PH IIIA - Construct Ramp T Diversion - Ramps T | 6 | 28 |
IIIBR110 | PH IIIB - Construct Ramp J Diversion/Temp Pavement - Ramp J | 20 | 32 |
IIIBR140 | PH IIIB - Construct Ramp Q Diversion/Temp Pavement - Ramp Q | 20 | 21 |
IIICR110 | PH IIIC - Construct Ramp N Diversion - Ramp N | 20 | 109 |
IIICR140 | PH IIIC - Remove Diversion / Construct Ramp Shoulder/Gore - Ramp J | 12 | 14 |
IVR-ET50 | PH IV - Erect Trusses (9-17) | 18 | 24 |
IVR-ET60 | PH IV - Erect Trusses (18-24) | 14 | 101 |
GC-GCN220 | Written Suspend order - FOC related to pending change | 50 | 91 |
IAI-TC120 | PH IA - Set Temp Traffic Barriers - Interchanges Roads John Young PKW | 1 | 34 |
IAR-TC130 | PH IA - Set Temp Traffic Barriers for Phase IB - WB Median Widening | 5 | 14 |
IAR-TC140 | PH IA - Set Temp Traffic Barriers for Phase IB - EB Median Widening | 5 | 25 |
IBR-IDS10 | PH IB - Install Drilled Shafts (1-13) | 13 | 135 |
IBR-RW110 | PH IB - Base - Ramp B/C Gore | 4 | 5 |
IIBR-EC10 | PH IIB - Erect Cantilevers (1-3) | 3 | 18 |
TF-CO-003 | Begin Electrical (Stub Outs & Site Electrical) | 20 | 31 |
TF-CO-014 | Pull Wire & Install Light Fixtures | 15 | 45 |
TF-CO-018 | Install Lighting | 22 | 45 |
TF-CO-019 | Install Security System | 22 | 45 |
TF-CO-020 | Install Lightning Protection | 10 | 45 |
TF-CO-023 | Erect Truss | 5 | 7 |
TF-CO-024 | Wall Treatments (Ply) | 22 | 45 |
TF-CO-027 | Cont. HVAC | 25 | 80 |
TF-FA-001 | Fabricate and Deliver Precast Erection | 20 | 148 |
IAEBO-W100 | PH IA - Noise/Sound Wall Prep Work (W-1) - EB Outside Widening | 20 | 50 |
IAEBO-W200 | PH IA - Install Panels (128000-160000 SF) - EB Outside Widening | 20 | 23 |
IBEBM-W100 | PH IB - Median Wall - Grading (JYP to TPK) | 20 | 238 |
IBEBM-W110 | PH IB - Median Wall - FFP Footing/Stem (JYP to TPK) | 15 | 233 |
IBEBM-W130 | PH IB - Wire (mse) Retaining Wall TW 18 - EB Median Widening (SR528) | 16 | 36 |
IBEBM-W140 | PH IB - Wire (mse) Retaining Wall TW 20 - EB Median Widening (SR528) | 16 | 23 |
IBR-IHM300 | PH IB - Install High Mast/Service (1-3) | 10 | 490 |
IBWBM-W100 | PH IB - Median Wall - Construct/ slip Top (JYP to TPK) | 15 | 208 |
IBWBM-W120 | PH IB - Wire (mse) Retaining Wall TW 19 - WB Median Widening (SR528) | 16 | 36 |
IBWBM-W140 | PH IB - Wire (mse) Retaining Wall TW 21 - WB Median Widening (SR528) | 16 | 23 |
IIAR-AP100 | PH IIB - Asphalt - Structural - Ramp O | 4 | 13 |
IIAR-EW100 | PH IIB - Embankment - Ramp O | 20 | 347 |
IIAR-GC100 | PH IIB - Performance Turf, SOD - Ramp O | 1 | 10 |
IIAR-RW100 | PH IIB - Stabilization - Ramp O | 4 | 6 |
IIAR-RW110 | PH IIB - Base - Ramp O | 8 | 30 |
IIAR-SP100 | PH IIA - Jack & Bore (42" (Sta 351+00 near Duke energy access platform) - Ramp O | 3 | 5 |
IIAR-SP110 | PH IIB - Drainage - Ramp O | 20 | 194 |
IIBEBO-ST2 | PH IIB - Test Pile - EB Outside Widening (Bridge over International DR) | 3 | 37 |
IIBEBO-ST4 | PH IIB - Production Pile - EB Outside Widening (Bridge over International DR) | 11 | 375 |
IIBEBO-ST5 | PH IIB - Pier 2, (F/R/P) (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over International DR) | 15 | 39 |
IIBEBO-ST7 | PH IIB- Removal of Concrete Forms for Pier 2, (Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Internatio | 1 | 2 |
IIBR-AP110 | PH IIB - Asphalt - Structural - Ramp E | 2 | 63 |
IIBR-AP120 | PH IIB - Asphalt - Structural - Ramp C | 4 | 114 |
IIBR-AP130 | PH IIB - Asphalt - Structural - Ramp I-1 | 2 | 3 |
IIBR-AP140 | PH IIB - Asphalt - Structural - Ramp H | 2 | 73 |
IIBR-AP150 | PH IIB - Asphalt - Structural - Ramp R-2 | 2 | 62 |
IIBR-AP180 | PH IIB - Asphalt - Structural - Ramp U | 2 | 109 |
IIBR-EW110 | PH IIB - Embankment - Ramp E | 5 | 300 |
IIBR-EW120 | PH IIB - Embankment - Ramp S-1 | 5 | 205 |
IIBR-EW122 | PH IIB - Embankment - Ramp A | 5 | 23 |
IIBR-EW130 | PH IIB - Embankment - Ramp R-1 | 5 | 108 |
IIBR-EW140 | PH IIB - Embankment - Ramp C | 4 | 47 |
IIBR-EW160 | PH IIB - Embankment - Ramp H | 5 | 86 |
IIBR-EW170 | PH IIB - Embankment - Ramp R-2 | 5 | 19 |
IIBR-EW200 | PH IIB - Embankment - Ramp U | 5 | 321 |
IIBR-GC330 | PH IIB - Performance Turf, SOD - Ramp R | 1 | 2 |
IIBR-IDS20 | PH IIB - Install Drilled Shafts (14-35) | 22 | 156 |
IIBR-IDS30 | PH IIB - Install Drilled Shafts (36-57) | 22 | 124 |
IIBR-ITS30 | PH IIB - Install Conduit/Boxes (Univ to JYP) | 20 | 353 |
IIBR-ITS40 | PH IIB - Install Conduit/Boxes (JYP to TPK) | 20 | 365 |
IIBR-ITS50 | PH IIB - Install ITS Poles (1-20) | 20 | 77 |
IIBR-ITS60 | PH IIB - Install ITS Poles (21-41) | 20 | 69 |
IIBR-ITS70 | PH IIB - Install CCTV's (1-8) | 16 | 91 |
IIBR-ITS80 | PH IIB - Install CCTV's (9-16) | 14 | 91 |
IIBR-ITS90 | PH IIB - Install CCTV's (17-22) | 10 | 29 |
IIBR-RW120 | PH IIB - Stabilization - Ramp E | 2 | 54 |
IIBR-RW130 | PH IIB - Base - Ramp E | 8 | 41 |
IIBR-RW140 | PH IIB - Stabilization - Ramp C | 12 | 28 |
IIBR-RW141 | PH IIB - Stabilization - Ramp A | 2 | 6 |
IIBR-RW150 | PH IIB - Stabilization - Ramp I-1 | 2 | 4 |
IIBR-RW151 | PH IIB - Base - Ramp A | 8 | 14 |
IIBR-RW160 | PH IIB - Base - Ramp C | 22 | 42 |
IIBR-RW180 | PH IIB - Stabilization - Ramp H | 2 | 53 |
IIBR-RW190 | PH IIB - Base - Ramp H | 8 | 27 |
IIBR-RW200 | PH IIB - Stabilization - Ramp R-2 | 2 | 3 |
IIBR-RW220 | PH IIB - Base - Ramp R-2 | 8 | 37 |
IIBR-RW240 | PH IIB - Stabilization - Ramp L | 2 | 7 |
IIBR-RW260 | PH IIB - Stabilization - Ramp U | 2 | 4 |
IIBR-RW270 | PH IIB - Base - Ramp U | 8 | 30 |
IIBR-SM380 | PH IIB - Shoulder Mount Light Pole/Service (I-4 to International) (14 EA) | 14 | 89 |
IIBR-SM390 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (A) | 20 | 354 |
IIBR-SM400 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 20 | 242 |
IIBR-SM410 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (C) | 20 | 221 |
IIBR-SM420 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (14 EA) | 14 | 100 |
IIBR-SM430 | PH IIB - Shoulder Mount Light Pole/Service (International to Univ.) (7 EA) | 7 | 100 |
IIBR-SM440 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (A) | 18 | 236 |
IIBR-SM450 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (19 EA) | 19 | 249 |
IIBR-SM460 | PH IIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (18 EA) (B) | 18 | 243 |
IIBR-SM470 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 20 | 305 |
IIBR-SM480 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 20 | 293 |
IIBR-SM490 | PH IIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 20 | 123 |
IIBR-SP110 | PH IIB - Drainage - Ramp E | 10 | 12 |
IIBR-SP130 | PH IIB - Drainage - Ramp I-1 | 10 | 65 |
IIBR-SP150 | PH IIB - Drainage - Ramp C | 10 | 41 |
IIBR-SP240 | PH IIB - Drainage - Ramp R-1 | 7 | 25 |
IICR-AP100 | PH IIC - Asphalt - Structural - Ramp S-2 | 2 | 4 |
IICR-EW100 | PH IIC - Embankment - Ramp S-2 | 5 | 344 |
IICR-EW120 | PH IIC - Embankment - Ramp M | 5 | 147 |
IICR-GC190 | PH IIC - Variable Height Barrier Wall - Ramp S-2 | 10 | 43 |
IICR-RW100 | PH IIC - Stabilization - Ramp S-2 | 2 | 14 |
IICR-RW140 | PH IIC - Base - Ramp M | 8 | 26 |
IICR-RW150 | PH IIC - Stabilization - Ramp M | 2 | 22 |
IICR-RW330 | PH IIC - Complete Widening - Ramp E | 8 | 28 |
IICR-RW340 | PH IIC - Complete Widening - Ramp H | 8 | 54 |
IICR-RW360 | PH IIC - Complete Widening - Ramp L | 8 | 43 |
IICR-SP100 | PH IIC - Drainage - Ramp S-2 | 5 | 148 |
IICR-SP120 | PH IIC - Drainage - Ramp M | 10 | 212 |
IICR-SP130 | PH IIC - Remove Ramp O Diversion - Construct EB Roadway Tie-In | 15 | 25 |
IIIBR-EC20 | PH IIIB - Erect Cantilevers (4-9) | 6 | 79 |
IIIBR-ET40 | PH IIIB - Erect Trusses (1-8) | 16 | 154 |
ITS10-1030 | Plan Revision 10 - Review and Procurement | 14 | 30 |
IVEBM-W230 | PH IV - Median Wall - Excavate - Station 311 to 332 | 2 | 3 |
IVEBM-W260 | PH IV - Median Wall - Excavate - Station 335 to 352 | 4 | 7 |
PRE-FA-007 | Fabricate and Deliver 400 Concrete Structures (Bearing Pads) | 30 | 58 |
PRE-FA-008 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750088 & 750215- I-Drive) | 20 | 235 |
PRE-FA-009 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 45" (Structures 750089, & 750216- Universal/Orangewood) | 20 | 233 |
PRE-FA-010 | Fabricate and Deliver 450 Precast Prestressed Beams TY II (Structures 750631-Shingle Creek) | 20 | 92 |
PRE-FA-011 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750091 & 750218- JYP) | 20 | 219 |
PRE-FA-012 | Fabricate and Deliver 450 Precast Prestressed Florida I Beam 36" (Structures 750629 Ramp S JYP & 750630 Ramp T JYP) | 20 | 443 |
PRE-FA-013 | Fabricate and Deliver 455 Auger Cast Piles (w/noise wall submittal) | 56 | 94 |
PRE-FA-014 | Fabricate and Deliver 534 Noise and Perimeter Walls | 56 | 88 |
PRE-FA-015 | Fabricate and Deliver 548 Retaining/MSE Wall Systems | 42 | 634 |
PRE-FA-016 | Fabricate and Deliver 641 Prestressed Concrete Poles | 35 | 325 |
PRE-FA-017 | Fabricate and Deliver 646 Aluminum Pedestal Poles | 56 | 59 |
PRE-FA-018 | Fabricate and Deliver 650 Traffic Signals | 56 | 143 |
PRE-FA-019 | Fabricate and Deliver 700 Highway Signing (Single, Multi, Panel, and Overhead) | 126 | 442 |
PRE-FA-020 | Fabricate and Deliver 992 Under deck Lighting | 56 | 453 |
PRE-FA-021 | Fabricate and Deliver 05500 Metal Fabrications | 140 | 154 |
PRE-FA-022 | Fabricate and Deliver 133420 Pre-Engineered Precast Concrete Structure | 84 | 120 |
PRE-FA-023 | Fabricate and Deliver 263213 Engine Generator | 84 | 213 |
PRE-FA-024 | Fabricate and Deliver 633 Communication Cable | 42 | 575 |
PRE-FA-025 | Fabricate and Deliver 635 Pull, Splice, & Junction Boxes | 42 | 511 |
PRE-FA-027 | Fabricate and Deliver 663 Signal Priority and Preemption Systems | 30 | 95 |
PRE-FA-031 | Fabricate and Deliver 081100 Metal Doors and Frames | 56 | 217 |
PRE-FA-032 | Fabricate and Deliver 099100 Painting Product Data and Sample | 42 | 162 |
PRE-FA-034 | Fabricate and Deliver 231113 Fuel Oil Piping | 70 | 206 |
PRE-FA-035 | Fabricate and Deliver 231323 Aboveground Diesel Storage Tank and Piping | 84 | 216 |
PRE-FA-038 | Fabricate and Deliver 238119 Packaged Air Conditioners | 42 | 216 |
PRE-FA-039 | Fabricate and Deliver 260536 Cable Trays | 42 | 111 |
PRE-FA-041 | Fabricate and Deliver 682 CCTV Camera | 42 | 511 |
PRE-FA-042 | Fabricate and Deliver 781 DMS | 56 | 105 |
PRE-FA-044 | Fabricate and (Ready to) Deliver 783 ITS Fiber Optic Cable | 56 | 624 |
PRE-FA-045 | Fabricate and Deliver 786 ITS Vehicle Detection System | 56 | 80 |
PRE-FA-046 | Fabricate and Deliver 784 ITS Managed Ethernet Hub Switch | 42 | 789 |
PRE-FA-049 | Fabricate and Deliver 262913 ITS Standby Generator Product Data and Shop Drawing | 70 | 498 |
PRE-FA-050 | Fabricate and Deliver 400 Concrete Structures (SIP Metal Forms) | 42 | 142 |
PRE-PS-001 | Prepare and Submit 506 Bridge Drainage System | 28 | 164 |
PRE-PS-002 | Prepare and Submit 455 Pile Installation Plan (Structures 750089 & 750216-Universal/Orangewood) | 7 | 129 |
PRE-PS-006 | Prepare and Submit Precast Erection | 28 | 223 |
PRE-PS-007 | Prepare and Submit 400 Concrete Structures (Bearing Pads) | 28 | 51 |
PRE-PS-013 | Prepare and Submit 455 Auger Cast Piles (w/noise wall submittal) | 28 | 43 |
PRE-PS-014 | Prepare and Submit 534 Noise and Perimeter Walls | 28 | 48 |
PRE-PS-015 | Prepare and Submit 548 Retaining/MSE Wall Systems | 28 | 114 |
PRE-PS-016 | Prepare and Submit 641 Prestressed Concrete Poles | 28 | 407 |
PRE-PS-018 | Prepare and Submit 650 Traffic Signals | 28 | 402 |
PRE-PS-019 | Prepare and Submit 700 Highway Signing (Single, Multi, Panel, and Overhead) | 28 | 421 |
PRE-PS-021 | Prepare and Submit 05500 Metal Fabrications | 28 | 123 |
PRE-PS-022 | Prepare and Submit 133420 Pre-Engineered Precast Concrete Structure | 28 | 223 |
PRE-PS-023 | Prepare and Submit 263213 Engine Generator | 28 | 75 |
PRE-PS-024 | Prepare and Submit 633 Communication Cable | 28 | 455 |
PRE-PS-025 | Prepare and Submit 635 Pull, Splice, & Junction Boxes | 28 | 239 |
PRE-PS-027 | Prepare and Submit 663 Signal Priority and Preemption Systems | 28 | 594 |
PRE-PS-029 | Prepare and Submit 033000 Cast-In-Place Concrete | 28 | 30 |
PRE-PS-030 | Prepare and Submit 042200 Masonry | 28 | 120 |
PRE-PS-033 | Prepare and Submit 101400 Signage | 28 | 30 |
PRE-PS-034 | Prepare and Submit 231113 Fuel Oil Piping | 28 | 67 |
PRE-PS-035 | Prepare and Submit 231323 Aboveground Diesel Storage Tank and Piping | 28 | 43 |
PRE-PS-037 | Prepare and Submit 233113 Ductwork Product Data and Shop Drawing | 28 | 91 |
PRE-PS-041 | Prepare and Submit 682 CCTV Camera | 28 | 205 |
PRE-PS-044 | Prepare and Submit 783 ITS Fiber Optic Cable | 28 | 169 |
PRE-PS-045 | Prepare and Submit 660 ITS Vehicle Detection System | 28 | 240 |
PRE-PS-049 | Prepare and Submit 639 ITS Standby Generator Product Data and Shop Drawing | 28 | 372 |
PRE-PS-050 | Prepare and Submit 400 Concrete Structures (SIP Metal Forms) | 28 | 184 |
PRE-RA-013 | Review and Approve 455 Auger Cast Piles (w/noise wall submittal) | 45 | 52 |
PRE-RA-014 | Review and Approve 534 Noise and Perimeter Walls | 45 | 97 |
PRE-RA-015 | Review and Approve 548 Retaining/MSE Wall Systems | 45 | 124 |
PRE-RA-016 | Review and Approve 641 Prestressed Concrete Poles | 45 | 434 |
PRE-RA-019 | Review and Approve 700 Highway Signing (Single, Multi, Panel, and Overhead) | 45 | 469 |
PRE-RA-021 | Review and Approve 05500 Metal Fabrications | 45 | 100 |
PRE-RA-023 | Review and Approve 263213 Engine Generator | 45 | 110 |
PRE-RA-024 | Review and Approve 633 Communication Cable | 45 | 478 |
PRE-RA-025 | Review and Approve 635 Pull, Splice, & Junction Boxes | 45 | 346 |
PRE-RA-027 | Review and Approve 663 Signal Priority and Preemption Systems | 45 | 591 |
PRE-RA-029 | Review and Approve 033000 Cast-In-Place Concrete | 45 | 224 |
PRE-RA-041 | Review and Approve 682 CCTV Camera | 45 | 210 |
PRE-RA-042 | Review and Approve 781 DMS | 45 | 266 |
PRE-RA-044 | Review and Approve 633 ITS Fiber Optic Cable | 45 | 226 |
PRE-RA-045 | Review and Approve 660 ITS Vehicle Detection System | 45 | 309 |
PRE-RA-049 | Review and Approve 639 ITS Standby Generator Product Data and Shop Drawing | 45 | 363 |
PRE-RA-050 | Review and Approve 400 Concrete Structures (SIP Metal Forms) | 45 | 121 |
USS-CO-001 | Summit | 22 | 36 |
IAEBO-AP100 | PH IA - Overbuild Shoulder - EB Outside Widening (SR528) | 7 | 25 |
IAEBO-EW100 | PH IA - Embankment(Duke energy access Poles) - EB Outside Widening | 3 | 4 |
IAEBO-GC100 | PH IA - Set Erosion Control Devices - EB Outside Widening | 20 | 55 |
IAEBO-GC110 | PH IA - Clear & Grub - EB Outside Widening | 17 | 77 |
IAEBO-GC130 | PH IA - Clear & Grub - EB Outside Widening (I-4 to Ramp H) | 3 | 4 |
IAEBO-TC110 | PH IA - Temp Striping for Phase IB - EB Outside Widening (SR528) | 5 | 42 |
IAWBO-AP100 | PH IA - Overbuild Shoulder - WB Outside Widening Area (SR528) | 7 | 20 |
IAWBO-GC100 | PH IA - Set Erosion Control Devices - WB Outside Widening Area | 20 | 55 |
IAWBO-GC110 | PH IA - Clear & Grub - WB Outside Widening Area | 20 | 101 |
IAWBO-TC100 | PH IA - Install Advance Sign & Traffic Control Devices - WB Outside Widening Area | 3 | 5 |
IAWBO-TC110 | PH IA - Temp Striping for Phase IB - WB Outside Widening Area (SR528) | 4 | 36 |
IBEBM-AP110 | PH IB - Asphalt - Structural - EB Median Widening (I-Drive to Univ) | 3 | 6 |
IBEBM-GC100 | PH IB - Median Clearing and Grubbing - EB Median Widening | 5 | 78 |
IBEBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 222 |
IBEBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 247 |
IBEBM-RW280 | PH IB - Base (I4-International Drive) - EB Median Widening | 8 | 150 |
IBEBM-RW310 | PH IB - Guard Rail Removal - EB Median Widening | 3 | 299 |
IBEBM-RW320 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 193 |
IBEBM-RW330 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - EB Median Widening | 10 | 188 |
IBEBM-ST100 | PH IB - Construct Crane Access - EB Median Widening (Bridge over Shingle Creek) | 3 | 5 |
IBEBM-ST110 | PH IB - DemoTraffic Rail / End Bents - EB Median Widening (Bridge over Shingle Creek) | 8 | 63 |
IBEBM-ST130 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over John Young PKWY) | 4 | 34 |
IBEBM-ST150 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over International DR) | 2 | 97 |
IBEBM-ST160 | PH IB - Test Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek) | 5 | 31 |
IBEBM-ST190 | PH IB - Production Pile (Concrete) - EB Median Widening (Bridge over Shingle Creek) | 20 | 68 |
IBEBM-ST210 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over John Young PKWY) | 3 | 75 |
IBEBM-ST220 | PH IB - Drive Production Pile (H Piles) - EB Median Widening (Bridge over John Young PKWY) | 20 | 122 |
IBEBM-ST230 | PH IB - Production Pile - EB Median Widening (Bridge over International DR) | 2 | 32 |
IBEBM-ST250 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Median Widening (Bridge over International DR) | 10 | 49 |
IBEBM-ST260 | PH IB - Demo Traffic Rails - EB Median Widening (Bridge over universal BLVD) | 2 | 73 |
IBEBM-ST270 | PH IB - Test Pile - EB Median Widening (Bridge over universal BLVD) | 2 | 15 |
IBEBM-ST280 | PH IB - Temp Sheet Pile - EB Median Widening (Bridge over universal BLVD) | 2 | 36 |
IBEBM-ST290 | PH IB - Production Pile - EB Median Widening (Bridge over universal BLVD) | 2 | 112 |
IBEBM-ST330 | PH IB - Wall Bent 1 - EB Median Widening (Bridge over International DR) | 5 | 21 |
IBEBM-ST340 | PH IB - Rip Rap Under Bridge - EB Median Widening (Bridge over Shingle Creek) | 10 | 44 |
IBEBM-ST350 | PH IB - Pier 2 & 3 (F/R/P)( Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | 15 | 19 |
IBEBM-ST360 | PH IB - Pier 2, 3, 4(F/R/P) ( Pier Cap) - EB Median Widening (Bridge over John Young PKWY) | 22 | 61 |
IBEBM-ST370 | PH IB - End Bent 1 - EB Median Widening (Bridge over International DR) | 5 | 19 |
IBEBM-ST380 | PH IB - Wall Bent 3 - EB Median Widening (Bridge over International DR) | 5 | 8 |
IBEBM-ST400 | PH IB - Remove Concrete Form for Pier 2, 3, (Pile Cap) - EB Median Widening (Bridge over Shingle Creek) | 1 | 3 |
IBEBM-ST430 | PH IB - End Bent 1 - EB Median Widening (Bridge over Shingle Creek) | 10 | 12 |
IBEBM-ST450 | PH IB - Set Beams - EB Median Widening (Bridge over International Drive) | 1 | 3 |
IBEBM-ST460 | PH IB - Superstructure Deck - EB Median Widening (Bridge over International Drive) | 15 | 26 |
IBEBM-ST470 | PH IB - Remove Concrete Forms for Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Median Widening (Bridge over John Young | 3 | 74 |
IBEBM-ST480 | PH IB - Temp Sheet Pile Removal - EB Median Widening (Bridge over John Young PKWY) | 3 | 58 |
IBEBM-ST520 | PH IB - Wall Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 5 | 28 |
IBEBM-ST540 | PH IB - Pier 2,(F/R/P) (Footer, Column & Pier Cap) - EB Median Widening (Bridge over Universal BLVD) | 10 | 39 |
IBEBM-ST570 | PH IB - End Bent 5 - EB Median Widening (Bridge over John Young PKWY) | 8 | 28 |
IBEBM-ST660 | PH IB - Set Beams - EB Median Widening (Bridge over John Young PKWY) | 3 | 4 |
IBEBM-ST670 | PH IB - Superstructure Deck - EB Median Widening (Bridge over John Young PKWY) | 22 | 34 |
IBEBM-ST690 | PH IB - Superstructure Deck- EB Median Widening (Bridge over Shingle Creek) | 22 | 31 |
IBEBM-ST710 | PH IB - End Bent 3 - EB Median Widening (Bridge over universal BLVD) | 5 | 12 |
IBEBM-ST740 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over John Young PKWY) | 3 | 4 |
IBEBM-ST750 | PH IB - Set Beams - EB Median Widening (Bridge over Universal BLVD) | 2 | 7 |
IBEBM-ST760 | PH IB - Superstructure Deck - EB Median Widening Bridge over Universal BLVD) | 15 | 49 |
IBEBM-ST850 | PH IB - Concrete Slope Pavement - EB Median Widening (Bridge over universal BLVD) | 3 | 4 |
IBEBM-ST890 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over International DR) | 5 | 97 |
IBEBM-ST900 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over universal BLVD) | 5 | 73 |
IBEBM-ST950 | PH IB - Demo Bridge Deck - EB Median Widening (Bridge over John Young PKWY) | 12 | 42 |
IBEBM-ST960 | PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column) - EB Median Widening (Bridge over John Young PKWY) | 22 | 89 |
IBEBM-TC210 | PH IB - Construct Diversion at Shingle Creek- EB Median Widening | 22 | 55 |
IBEBM-TC220 | PH IIIA - Construct Diversion at Shingle Creek - WB Median Widening | 15 | 32 |
IBEBO-EW110 | PH IB - Pond Excav/Embank JYP to TPK - EB Outside Widening | 20 | 191 |
IBEBO-EW130 | PH IB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 20 | 567 |
IBEBO-EW140 | PH IB - Pond Excav/Embank Universal to Int. Dr. - WB Outside Widening | 20 | 566 |
IBEBO-EW150 | PH IB - Pond Excav/Embank Universal to Int. Dr. - EB Outside Widening | 20 | 546 |
IBEBO-EW160 | PH IB - Pond Excav/Embank Universal to JYP - EB Outside Widening | 20 | 538 |
IBEBO-EW170 | PH IB - Pond Excav/Embank Int. Dr. to I-4 - WB Outside Widening | 20 | 171 |
IBEBO-SP150 | PH IB - Drainage (Pond 5C @ John Young) - EB Outside Widening (Ponds) | 15 | 343 |
IBWBM-AP100 | PH IB - Asphalt - Structural - WB Median Widening | 7 | 76 |
IBWBM-GC100 | PH IB - Median Clearing and Grubbing - WB Median Widening | 5 | 79 |
IBWBM-RW110 | PH IB - Grade for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 255 |
IBWBM-RW111 | PH IB - Stabilization for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 283 |
IBWBM-RW180 | PH IB - Base (Universal-International Drv.) - WB Median Widening | 8 | 42 |
IBWBM-RW210 | PH IB - Base (International Drv.-I4) - WB Median Widening | 8 | 41 |
IBWBM-RW220 | PH IB - Base for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 237 |
IBWBM-RW230 | PH IB - Pavement for Permanent Shoulder Construction (JYP-TRP) - WB Median Widening | 10 | 226 |
IBWBM-SP100 | PH IB - Drainage for JYP Interchange (Sta 354 +04) | 20 | 149 |
IBWBM-SP110 | PH IB - Drainage for JYP to STA 390 | 20 | 181 |
IBWBM-SP120 | PH IB - Drainage for JYP to Int. Dr. (Sta 354+04 to 234+50) | 20 | 136 |
IBWBM-ST120 | PH IB - Demo Traffic Rail - WB Median Widening (Bridge over International DR) | 2 | 97 |
IBWBM-ST130 | PH IB - Test Pile H-Piles - WB Median Widening (Bridge over International DR) | 1 | 12 |
IBWBM-ST150 | PH IB - Production Pile - WB Median Widening (Bridge over International DR) | 2 | 32 |
IBWBM-ST170 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over International DR) | 10 | 49 |
IBWBM-ST180 | PH IB - Demo Traffic Rail / End Bents - WB Median Widening (Bridge over universal BLVD) | 2 | 73 |
IBWBM-ST190 | PH IB - Test Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 1 | 2 |
IBWBM-ST200 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over universal BLVD) | 2 | 17 |
IBWBM-ST210 | PH IB - Production Pile Concrete - WB Median Widening (Bridge over universal BLVD) | 4 | 109 |
IBWBM-ST240 | PH IB - Demo Traffic Rails - WB Median Widening (Bridge over John Young PKWY) | 4 | 34 |
IBWBM-ST250 | PH IB - Test Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | 5 | 147 |
IBWBM-ST280 | PH IB - Wall Bent 1 - WB Median Widening (Bridge over International DR) | 5 | 21 |
IBWBM-ST290 | PH IB - End Bent 1 - WB Median Widening (Bridge over International DR) | 5 | 19 |
IBWBM-ST300 | PH IB - Temp Sheet Pile - WB Median Widening (Bridge over John Young PKWY) | 3 | 93 |
IBWBM-ST310 | PH IB - Production Pile (H Piles) - WB Median Widening (Bridge over John Young PKWY) | 15 | 122 |
IBWBM-ST320 | PH IB - Wall Bent 3 - WB Median Widening (Bridge over International DR) | 5 | 8 |
IBWBM-ST340 | PH IB - Pier 2, 3, 4(F/R/P) (Footer, Column & Pier Cap) - WB Median Widening (Bridge over John Young PKWY) | 20 | 103 |
IBWBM-ST350 | PH IB - Set Beams - WB Median Widening (Bridge over International Drive) | 2 | 3 |
IBWBM-ST360 | PH IB - Superstructure Deck - WB Median Widening (Bridge over International Drive) | 15 | 50 |
IBWBM-ST380 | PH IB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Median Widening (Bridge over Universal BLVD) | 10 | 38 |
IBWBM-ST400 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over International DR) | 1 | 9 |
IBWBM-ST450 | PH IB - Temp Sheet Pile Removal - WB Median Widening (Bridge over John Young PKWY) | 3 | 58 |
IBWBM-ST490 | PH IB - Wall Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 5 | 28 |
IBWBM-ST530 | PH IB - End Bent 5 - WB Median Widening (Bridge over John Young PKWY) | 8 | 28 |
IBWBM-ST560 | PH IB - Set Beams - WB Median Widening (Bridge over John Young PKWY) | 3 | 4 |
IBWBM-ST570 | PH IB - End Bent 3 - WB Median Widening (Bridge over universal BLVD) | 5 | 12 |
IBWBM-ST580 | PH IB - Superstructure Deck - WB Median Widening (Bridge over John Young PKWY) | 22 | 42 |
IBWBM-ST590 | PH IB - Set Beams - WB Median Widening (Bridge over Universal BLVD) | 2 | 7 |
IBWBM-ST600 | PH IB - Superstructure Deck - WB Median Widening Bridge over Universal BLVD) | 15 | 33 |
IBWBM-ST660 | PH IB - Concrete Slope Pavement - WB Median Widening (Bridge over universal BLVD) | 3 | 10 |
IBWBM-ST710 | PH IB - Demo Bridge Deck- WB Median Widening (Bridge over universal BLVD) | 5 | 57 |
IBWBM-ST720 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over John Young PKWY) | 12 | 42 |
IBWBM-ST730 | PH IB - Demo Bridge Deck - WB Median Widening (Bridge over International DR) | 5 | 97 |
IBWBO-SP100 | PH IB - Jack & Bore JYP Interchange (Sta 354 +04) | 20 | 149 |
IBWBO-SP130 | PH IB - Jack & Bore JYP to TPK (East of Sta 354+04 to 415+33) | 20 | 41 |
IBWBO-SP140 | PH IB - Jack & Bore JYP to Int. Dr. (Sta 354+04 to 234+50) | 20 | 93 |
IBWBO-SP160 | PH IB - Drainage Outfalls (Pond 4A @ John Young) - WB Outside Widening Area (Ponds) | 20 | 256 |
IBWBO-SP190 | PH IB - Drainage Outfalls (Pond 5A @ John Young) - WB Outside Widening Area (Ponds) | 20 | 54 |
IIBEB-TC110 | PH II B - Shift EB traffic to outside across I-Drive | 1 | 7 |
IIBEBO-IE20 | PH IIB - Install 2 Ea Mast Arms at Jyp | 10 | 77 |
IIBEBO-ST10 | PH IIB - Test Pile - EB Outside Widening (Bridge over universal BLVD) | 3 | 162 |
IIBEBO-ST12 | PH IIB - Production Pile - EB Outside Widening (Bridge over universal BLVD) | 7 | 157 |
IIBEBO-ST14 | PH IIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over Universal BLVD) | 10 | 23 |
IIBEBO-ST20 | PH IIB - Test Pile (H Piles) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 5 | 23 |
IIBEBO-ST21 | PH IIB - Temp Sheet Pile - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 6 | 83 |
IIBEBO-ST22 | PH IIB - Production Pile (H Piles) (1-31) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 8 | 49 |
IIBEBO-ST23 | PH IIB - Production Pile (H Piles) (32-62) -EB Outside Widening (Bridge 750629 Ramp S over JYP) | 8 | 187 |
IIBEBO-ST24 | PH IIB - Pier 2, 3, 4 (F/R/P)(Footer, Column) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 22 | 100 |
IIBEBO-ST26 | PH IIB - Remove of Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S ov | 3 | 43 |
IIBEBO-ST28 | PH IIB - Construct Crane Access - EB Outside Widening (Bridge over Shingle Creek) | 2 | 4 |
IIBEBO-ST30 | PH IIB - Production Pile (Concrete) - EB Outside Widening (Bridge over Shingle Creek) | 22 | 41 |
IIBEBO-ST31 | PH IIB - Gravity Wall @ Shingle Creek - EB Outside Widening (Bridge over Shingle Creek) | 10 | 193 |
IIBEBO-ST32 | PH IIB - Rip Rap Under Bridge - EB Outside Widening (Bridge over Shingle Creek) | 20 | 106 |
IIBEBO-W100 | PH IIB - Concrete FACED SHEET Pile Wall Work - Demo Portion of Existing Walls - SE and SW Corners @ I-Drive | 15 | 126 |
IIBEBO-W110 | PH IIB - Concrete FACED SHEET Pile Wall (RW-4A) - SE Corner @ I-Drive | 15 | 118 |
IIBEBO-W120 | PH IIB - Concrete FACED SHEET Pile Wall (RW-3) - SW Corner @ I-Drive | 15 | 82 |
IIBEBO-W130 | PH IIB - Gravity Wall - EB Outside Widening (SR528) | 10 | 136 |
IIBEBO-W140 | PH IIB - MSE Wall RW5 (Level Pads/ Set Panels) - EB Outside Widening (SR528) | 22 | 83 |
IIBEBO-W150 | PH IIB - MSE Wall RW5 (Set coping/ barrier/ moment slab) - EB Outside Widening | 22 | 37 |
IIBEBO-W160 | PH IIIC - MSE Wall RW-1 (Coping/ barrier/ moment slab) - WB Outside | 10 | 14 |
IIBR-EHM340 | PH IIB - Existing High Mast Removal (1-8) | 18 | 46 |
IIBR-EHM350 | PH IIB - Existing High Mast Removal (9-18) | 18 | 22 |
IIBR-EHM360 | PH IIB - Existing High Mast Removal (19-27) | 18 | 237 |
IIBR-IHM310 | PH IIB - Install High Mast/Service (4-6) | 10 | 391 |
IIBR-RES120 | PH IIB - Remove Existing Sign Structures (2-4) | 6 | 18 |
IICR-TC1000 | PH IIC - Set Temp Traffic Barriers (Shoulder) - Ramp M | 1 | 2 |
IIIBR-AP140 | PH III C - Asphalt - Structural - WB outside 337-340 + old Ramp T | 3 | 44 |
IIIBR-AP150 | PH IIIB - Asphalt - Structural - Ramp P to Shingle | 2 | 14 |
IIIBR-AP160 | PH IIIB - Asphalt - Structural - Ramp Q | 2 | 3 |
IIIBR-EW100 | PH IIIB - Embankment - Ramp G | 5 | 12 |
IIIBR-EW110 | PH IIIB - Embankment - Ramp J | 5 | 11 |
IIIBR-EW130 | PH IIIB - Embankment - Ramp K | 5 | 51 |
IIIBR-EW140 | PH IIIB - Embankment - Ramp T | 5 | 547 |
IIIBR-EW150 | PH IIIB - Embankment - Ramp P to Shingle | 5 | 21 |
IIIBR-EW160 | PH IIIB - Embankment - Ramp Q | 5 | 48 |
IIIBR-GC100 | PH IIIB - Demo - Ramp G | 2 | 7 |
IIIBR-GC300 | PH IIIB - Performance Turf, SOD - Ramp P | 1 | 27 |
IIIBR-GC320 | PH IIIB - Guardrail (Roadway) - Ramp P to Shingle | 2 | 12 |
IIIBR-GC340 | PH IIIB - Demo - Ramp Q | 2 | 3 |
IIIBR-IDS40 | PH IIIB - Install Drilled Shafts (58-63) | 6 | 131 |
IIIBR-IDS50 | PH IIIB - Redo/ repair on drilled shafts OHT-11, OHT 16 | 25 | 42 |
IIIBR-ITS80 | PH IIIB - Install Conduit/Boxes (JYP to TPK) | 20 | 470 |
IIIBR-RW100 | PH IIIB - Stabilization - Ramp G | 2 | 47 |
IIIBR-RW120 | PH IIIB - Stabilization - Ramp J | 2 | 4 |
IIIBR-RW150 | PH IIIB - Base - Ramp V | 8 | 9 |
IIIBR-RW160 | PH IIIB - Stabilization - Ramp K | 2 | 8 |
IIIBR-RW170 | PH IIIB - Base - Ramp K | 8 | 42 |
IIIBR-RW180 | PH IIIB - Stabilization - Ramp T | 2 | 173 |
IIIBR-RW200 | PH IIIB - Stabilization - Ramp P to Shingle | 5 | 17 |
IIIBR-RW210 | PH IIIB - Base - Ramp P to Shingle | 10 | 19 |
IIIBR-RW220 | PH IIIB - Stabilization - Ramp Q | 2 | 35 |
IIIBR-RW230 | PH IIIB - Base - Ramp Q | 8 | 40 |
IIIBR-RW260 | PH III C - Base - WB outside 337-340 + old Ramp T | 8 | 92 |
IIIBR-RW270 | PH III C - Stabilization - WB outside 337-340 + old Ramp T | 5 | 92 |
IIIBR-SM530 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) | 20 | 241 |
IIIBR-SM550 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (10 EA) | 10 | 135 |
IIIBR-SM570 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (20 EA) | 20 | 333 |
IIIBR-SM590 | PH IIIB - Shoulder Mount Light Pole/Service (Univ. to JYP) (12 EA) | 12 | 30 |
IIIBR-SM600 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (A) | 20 | 357 |
IIIBR-SM610 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (B) | 20 | 357 |
IIIBR-SM620 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (C) | 20 | 357 |
IIIBR-SM630 | PH IIIB - Shoulder Mount Light Pole/Service (JYP to TPK) (20 EA) (D) | 20 | 91 |
IIIBR-SP110 | PH IIIB - Drainage - Ramp J | 10 | 31 |
IIIBR-TC250 | PH IIIB - Set Temp Traffic Barriers (Shoulder) - Ramp P | 1 | 2 |
IIIBR-TC260 | PH IIIB - Temp Striping New Ramp Alignment - Ramp P | 1 | 2 |
IIIBWBO-ST2 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over International DR) | 3 | 5 |
IIIBWBO-ST3 | PH IIIB - Temp Sheet Pile - WB Outside Widening Area (Bridge over International DR) | 3 | 14 |
IIIBWBO-ST4 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over International DR) | 11 | 491 |
IIIBWBO-ST5 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over International DR) | 20 | 58 |
IIIBWBO-ST7 | PH IIIB - Test Pile - WB Outside Widening Area (Bridge over universal BLVD) | 3 | 204 |
IIICR-AP100 | PH IIIC - Asphalt - Structural - Ramp F | 2 | 4 |
IIICR-AP110 | PH IIIC - Asphalt - Structural - Ramp N | 2 | 6 |
IIICR-EW100 | PH IIIC - Embankment - Ramp F | 5 | 538 |
IIICR-EW110 | PH IIIC - Embankment - Ramp N | 5 | 25 |
IIICR-GC160 | PH IIIC - Guardrail (Roadway) - Ramp N | 2 | 20 |
IIICR-RW100 | PH IIIC - Stabilization - Ramp F | 2 | 4 |
IIICR-RW110 | PH IIIC - Base - Ramp F | 8 | 9 |
IIICR-RW120 | PH IIIC - Stabilization - Ramp N | 2 | 17 |
IIICR-RW130 | PH IIIC - Base - Ramp N | 8 | 20 |
IIICR-SP100 | PH IIIC - Drainage - Ramp F | 10 | 38 |
IIICR-SP110 | PH IIIC - Drainage - Ramp N | 10 | 163 |
IVEBM-SP100 | PH IV - Drainage - Median Widening (West of 311) | 20 | 137 |
IVEBM-TC100 | PH IV - Shift EB traffic to outside I-Drive through Station 312 | 4 | 30 |
IVEBO-SS100 | PH IV - Install OT Structures - East of JYP | 20 | 146 |
IVWBM-RW120 | PH IV - Grade for road - Station 259+50 to 311 WB Express | 4 | 69 |
IVWBM-RW160 | PH IV - Stabilization - Station 259+50 to 311 WB Express | 3 | 66 |
IVWBM-SP100 | PH IV - Drainage - Median Widening (East of 311) | 20 | 134 |
PRE-FA-0111 | Fabricate and Deliver 455 Temp Sheet Pile/Critical | 14 | 83 |
IIAEBO-TC100 | PH IIA - Install Sign & Traffic Control Devices - EB Outside Widening | 1 | 260 |
IIBEBO-AP110 | PH IIB - Asphalt - Structural - EB Outside Widening (I-4 to I-Drive) | 4 | 75 |
IIBEBO-AP120 | PH IIB - Asphalt - Structural - EB Outside Widening (I-Drive to Univ) | 8 | 193 |
IIBEBO-AP130 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 291 to 320 | 4 | 189 |
IIBEBO-AP140 | PH IIB - Asphalt - Structural - EB Outside Widening (Univ to JYP) - STA 320 to 332 | 4 | 11 |
IIBEBO-EW100 | PH IIB - Embankment (I4-Int. Drive) - EB Outside Widening | 20 | 168 |
IIBEBO-EW101 | PH IIB - Embankment (Int. Drive - Universal) - EB Outside Widening | 15 | 97 |
IIBEBO-EW102 | PH IIB - Embankment (Universal - JYP) - EB Outside Widening | 20 | 109 |
IIBEBO-EW112 | PH IIB - Embankment (Int. Drive - Universal) - at Toll Facility | 5 | 134 |
IIBEBO-GC100 | PH IIB - MISC. Demo - EB Outside Widening | 10 | 60 |
IIBEBO-GC120 | PH IIB - Guardrail (Roadway) - EB Outside Widening | 2 | 5 |
IIBEBO-RW110 | PH IIB - Stabilization (I4-Int. Drive) - EB Outside Widening | 22 | 54 |
IIBEBO-RW111 | PH IIB - Stabilization (Int. Drive - Universal) - EB Outside Widening | 22 | 223 |
IIBEBO-RW112 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 291 to 320) | 14 | 178 |
IIBEBO-RW120 | PH IIB - Base (I4-Int. Drive) - EB Outside Widening | 22 | 76 |
IIBEBO-RW130 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - LR | 15 | 162 |
IIBEBO-RW140 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 291 to 304) | 8 | 108 |
IIBEBO-RW150 | PH IIB - Base (Int. Drive - Universal)- EB Outside Widening - RCA | 7 | 160 |
IIBEBO-RW160 | PH IIB - Base (Universal - JYP) - EB Outside Widening - RCA | 6 | 18 |
IIBEBO-RW170 | PH IIB - Stabilization (Universal - JYP) - EB Outside Widening - (STA 320 to 332) | 8 | 40 |
IIBEBO-RW180 | PH IIB - Base (Universal - JYP) - EB Outside Widening - LR - (STA 320 to 332) | 8 | 41 |
IIBEBO-SP100 | PH IIB - Drainage (I4-Int. Drive) - EB Outside Widening (SR528) | 20 | 76 |
IIBEBO-SP110 | PH IIB - Drainage (Int. Drive - Universal) - EB Outside Widening (SR528) | 20 | 119 |
IIBEBO-SP120 | PH IIB - Drainage (Universal - JYP) - EB Outside Widening (SR528) | 20 | 189 |
IIBEBO-SP130 | PH IIB - Gutter Drainage - STA 228 - 248 (EB Outside) | 10 | 226 |
IIBEBO-SP140 | PH IIB - Gutter Drainage - STA 280 - 299 (EB Outside) | 3 | 154 |
IIBEBO-ST170 | PH IIB - Pier 2, 3, (F/R/P)(Pile Cap) - EB Outside Widening (Bridge over Shingle Creek) | 20 | 40 |
IIBEBO-ST180 | PH IIB - Wall Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 5 | 12 |
IIBEBO-ST220 | PH IIB - End Bent 5 - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 8 | 13 |
IIBEBO-ST240 | PH IIB - Wall Bent 1 - EB Outside Widening (Bridge over Shingle Creek) | 4 | 8 |
IIBEBO-ST290 | PH IIB - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 15 | 16 |
IIBEBO-ST330 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over International DR) | 5 | 9 |
IIBEBO-ST340 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over International DR) | 4 | 39 |
IIBEBO-ST350 | PH IIB - Superstructure Deck Finish Rebar\Set screed\Pouring - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 15 | 18 |
IIBEBO-ST370 | PH IIB - Lighting Conduit - EB Outside Widening (Bridge over International DR) | 1 | 9 |
IIBEBO-ST400 | PH IIB - End Bent 1 - EB Outside Widening (Bridge over universal BLVD) | 5 | 7 |
IIBEBO-ST440 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 10 | 36 |
IIBEBO-ST510 | PH IIB - Grind and Groove - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 4 | 5 |
IIBEBO-ST540 | PH IIB - Concrete Slope Pavement - EB Outside Widening (Bridge over universal BLVD) | 5 | 8 |
IIBEBO-ST570 | PH IIB - Superstructure Deck Pour - EB Outside Widening (Bridge over Universal BLVD) | 1 | 2 |
IIBEBO-ST590 | PH IIB - Approach Slabs - EB Outside Widening (Bridge over Shingle Creek) | 10 | 14 |
IIBEBO-ST620 | PH IIB - Grind and Groove - EB Outside Widening (Bridge over Shingle Creek) | 4 | 7 |
IIBEBO-ST630 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over International DR) | 5 | 13 |
IIBEBO-ST640 | PH IIB - Demo Bridge Deck - EB Outside Widening (Bridge over universal BLVD) | 5 | 13 |
IIBEBO-ST690 | PH IIB - Pier 2, 3, 4 (F/R/P)(Pier Cap) - EB Outside Widening (Bridge 750629 Ramp S over JYP) | 20 | 91 |
IIBEBO-ST700 | PH IIB - Superstructure Deck (Finish Rebar\Set Screed\Pour) - EB Outside Widening (Bridge over Shingle Creek) | 15 | 26 |
IIBEBO-TC130 | PH IIB - Set Temp Traffic Barriers - EB Outside Widening | 10 | 27 |
IIDEBO-RW150 | PH IID - Construct EB Outside Widening STA 346 to STA 369 | 22 | 186 |
IIDEBO-ST120 | PH IID - Temp Sheet Pile - EB Outside Widening (Bridge over John Young PKWY) | 3 | 83 |
IIDEBO-ST130 | PH IID - Production Pile (H Piles) - EB Outside Widening (Bridge over John Young PKWY) | 16 | 303 |
IIDEBO-ST140 | PH IID - Pier 2, 3, 4 (F/R/P) (Footer & Column) - EB Outside Widening (Bridge over John Young PKWY) | 22 | 100 |
IIDEBO-ST160 | PH IID - Remove Concrete form for Pier 2, 3, 4(Footer, Column & Pier Cap) - EB Outside Widening (Bridge over JYP) | 3 | 5 |
IIDEBO-ST170 | PH IID - Temp Sheet Pile Removal - EB Outside Widening (Bridge over John Young PKWY) | 6 | 67 |
IIDEBO-ST190 | PH II D - Wall Bent 1 - EB Outside Widening (Bridge over John Young PKWY) | 5 | 7 |
IIDEBO-ST210 | PH II D - Wall Bent 5 - EB Outside Widening (Bridge over John Young PKWY) | 5 | 8 |
IIDEBO-ST240 | PH II D - Superstructure Deck SIP & Start Rebar - EB Outside Widening (Bridge over John Young PKWY) | 15 | 25 |
IIDEBO-ST260 | PH IID - Concrete Slope Pavement - EB Outside Widening (Bridge over John Young PKWY) | 5 | 9 |
IIDEBO-ST300 | PH II D - Demo Bridge Deck remove slabs - EB Outside Widening (Bridge over John Young PKWY) | 10 | 38 |
IIDEBO-ST310 | PH IID - Pier 2, 3, 4 (F/R/P) ( Pier Cap) - EB Outside Widening (Bridge over John Young PKWY) | 20 | 52 |
IIDEBO-ST320 | PH IID - Demo Bridge Deck hand demo - EB Outside Widening (Bridge over John Young PKWY) | 10 | 37 |
IIIAWBO-ST16 | PH IIIA - Test Pile (H Piles) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 5 | 155 |
IIIAWBO-ST17 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 3 | 60 |
IIIAWBO-ST19 | PH IIIA - Production Pile (H Piles) (33-65) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 16 | 246 |
IIIAWBO-ST20 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 20 | 67 |
IIIAWBO-ST22 | PH IIIA - Remove Concrete Form Pier 2, 3, 4 (Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T | 3 | 8 |
IIIAWBO-ST30 | PH IIIA - Temp Sheet Pile - WB Outside Widening Area (Bridge over John Young PKWY) | 5 | 32 |
IIIAWBO-ST31 | PH IIIA - Production Pile (H Piles) - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 276 |
IIIAWBO-ST32 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Footer, Column) - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 51 |
IIIAWBO-ST34 | PH IIIA - Remove Concrete Form for Pier 2, 3, 4(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over John | 3 | 8 |
IIIBR-RES130 | PH IIIB - Remove Existing Sign Structures (5-13) I-4 to Universal | 18 | 37 |
IIIBWB-TC100 | PH IIIB - Shift WB traffic to EB and Ramp F traffic to inside WB | 2 | 5 |
IIIBWBO-ST10 | PH IIIB - Production Pile - WB Outside Widening Area (Bridge over universal BLVD) | 7 | 202 |
IIIBWBO-ST11 | PH IIIB - Pier 2, (F/R/P)(Footer, Column & Pier Cap) - WB Outside Widening Area (Bridge over Universal BLVD) | 20 | 23 |
IIIBWBO-ST26 | PH IIIB - Production Pile (11-30)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 10 | 48 |
IIIBWBO-ST28 | PH IIIB - Rip Rap Under Bridge - WB Outside Widening Area (Bridge over Shingle Creek) | 20 | 36 |
IIIBWBO-W100 | PH IIIB - Concrete faced sheet pile Wall - Demo Portion of Existing Walls - NE and NW Corners @ I-Drive | 15 | 63 |
IIIBWBO-W110 | PH IIIB - MSE Wall RW-1 (Leveling Pad/ Set Panels) - WB Outside | 22 | 34 |
IIIBWBO-W111 | PH IIIB - Gravity Wall - WB Outside Widening Area (Bridge over International DR) | 7 | 54 |
IIIBWBO-W120 | PH IIIB - Concrete FACED SHEET Pile Wall (RW-4B) - NE Corner @ I-Drive | 15 | 33 |
IIIBWBO-W130 | PH IIIB - Sheet Pile Wall (RW-2) - Drive sheets place walers, deadman | 15 | 48 |
IIIBWBO-W140 | PH IIIB - Concrete facing on Wall (RW-2) - NW Corner @ I-Drive | 10 | 17 |
PRE-FA-00123 | Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 18" (Structures 750089 & 750216) | 20 | 24 |
PRE-FA-00132 | Fabricate and Deliver 455 Structure Foundations Prestressed Concrete Piling 24" (Structure 750631-Shingle Creek) | 20 | 26 |
PRE-FA-00145 | Fabricate and Deliver 455 Structure Foundations Steel Pile HP 14X89 (Structures 750088 and 750215 I-Drive) | 14 | 63 |
USDED-CO-001 | Duke Energy Distribution (A) | 6 | 139 |
USDED-CO-002 | Duke Energy Distribution (B) | 77 | 595 |
IIIAWBO-SP100 | PH IIIA - Jack & Bore - WB Outside Widening Area (SR528) | 10 | 52 |
IIIAWBO-ST160 | PH IIIA - Superstructure Deck - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 46 |
IIIAWBO-ST171 | PH IIIA - Approach Slabs - WB Outside Widening Area (Bridge over John Young PKWY) | 5 | 6 |
IIIAWBO-ST201 | PH IIIA - Traffic Railing (32") - WB Outside Widening Area (Bridge over John Young PKWY) | 3 | 5 |
IIIAWBO-ST580 | PH IIIA - Concrete Slope Pavement - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10 | 32 |
IIIAWBO-ST690 | PH IIIA - Pier 2, 3, 4 (F/R/P)(Pier Cap) - WB Outside Widening Area (Bridge 750630 Ramp T over JYP) | 10 | 27 |
IIIAWBO-ST700 | PH IIIA - Production Pile (1-10)(Concrete) - WB Outside Widening Area (Bridge over Shingle Creek) | 5 | 14 |
IIIAWBO-ST710 | PH IIIA - Pier 2, 3, 4 (F/R/P) (Pier Cap) - WB Outside Widening Area (Bridge over John Young PKWY) | 22 | 53 |
IIIBR-ITS1010 | PH IIIB - Install Conduit/Boxes ( International to Univ) | 10 | 223 |
IIIBWBO-AP100 | PH IIIB - Asphalt - Structural - WB Outside JYP to I-Drive | 20 | 222 |
IIIBWBO-AP120 | PH IIIB - Asphalt - Structural - (At Wall RW-1) WB Outside Widening | 2 | 6 |
IIIBWBO-EW101 | PH IIIB - Surcharge/ Embankment 2 - WB Outside Widening Area | 18 | 19 |
IIIBWBO-EW102 | PH IIIB - Surcharge/ Embankment 3 - WB Outside Widening Area | 17 | 24 |
IIIBWBO-EW103 | PH IIIB - Surcharge/ Embankment 4 - WB Outside Widening Area | 17 | 22 |
IIIBWBO-EW110 | PH IIIB - Embankment (JYP-Universal) - WB Outside Widening Area | 20 | 654 |
IIIBWBO-EW120 | PH IIIB - Embankment (Universal - International) - WB Outside Widening Area | 20 | 531 |
IIIBWBO-EW130 | PH IIIB - Embankment (I-4 to STa 227) - WB Outside Widening Area | 20 | 128 |
IIIBWBO-EW140 | PH IIIB - Pond Excav/Embank JYP to Universal - WB Outside Widening | 15 | 418 |
IIIBWBO-GC100 | PH IIIB - MISC. Demo - WB Outside Widening Area | 10 | 194 |
IIIBWBO-RW100 | PH IIIB - Stabilization (Shingle - Universal) - WB Outside Widening Area | 20 | 159 |
IIIBWBO-RW110 | PH IIIB - Stabilization (Ramp G - International) - WB Outside Widening Area | 20 | 152 |
IIIBWBO-RW120 | PH IIIB - Stabilization ( I4 to Sta 227) - WB Outside Widening Area | 20 | 126 |
IIIBWBO-RW140 | PH IIIB - Base (Shingle - Universal) - WB Outside Widening Area | 10 | 175 |
IIIBWBO-RW150 | PH IIIB - Base (Ramp G - International) - WB Outside Widening Area | 10 | 148 |
IIIBWBO-RW160 | PH IIIB - Base (I4 to Sta 227) - WB Outside Widening Area | 10 | 76 |
IIIBWBO-RW170 | PH IIIB - Stabilization (At RW-1) - WB Outside Widening | 4 | 9 |
IIIBWBO-RW180 | PH IIIB - Base (At Wall RW-1) - WB Outside Widening Area | 4 | 6 |
IIIBWBO-SP100 | PH IIIB - Drainage (Shingle - Universal) - WB Outside Widening Area (SR528) | 22 | 509 |
IIIBWBO-SP110 | PH IIIB - Drainage (Universal - International) - WB Outside Widening Area (SR528) | 22 | 450 |
IIIBWBO-SP130 | PH IIIB - Gutter Drainage - STA 352 - 342 (WB Outside) | 10 | 136 |
IIIBWBO-SP150 | PH IIIB - Gutter Drainage - STA 301 - 280 (WB Outside) | 4 | 110 |
IIIBWBO-SP160 | PH IIIB - Gutter Drainage - STA 248 - 236 (WB Outside) | 5 | 200 |
IIIBWBO-SP170 | PH III C - Shoulder Gutter - STA 341 - 355 (WB Outside) | 5 | 86 |
IIIBWBO-ST100 | PH IIIB - Superstructure Deck Finish Rebar\Set Screed\Pour - WB Outside Widening Area (Bridge over Universal BLVD) | 15 | 30 |
IIIBWBO-ST140 | PH IIIB - Traffic Railing (32") - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 4 |
IIIBWBO-ST180 | PH IIIB - Demo Traffic Rail - WB Outside Widening Area (Bridge over universal BLVD) | 2 | 3 |
IIIBWBO-ST250 | PH IIIB - End Bent 1 - WB Outside Widening Area (Bridge over International DR) | 7 | 16 |
IIIBWBO-ST270 | PH IIIB - Pier 2, 3, (F/R/P) ( Pile Cap) - WB Outside Widening Area (Bridge over Shingle Creek) | 15 | 54 |
IIIBWBO-ST350 | PH IIIB - Superstructure Deck SIB & Start Rebar - WB Outside Widening (Area Bridge over Universal BLVD) | 20 | 21 |
IIIBWBO-ST370 | PH IIIB - Wall Bent 1 - WB Outside Widening Area (Bridge over Shingle Creek) | 8 | 11 |
IIIBWBO-ST410 | PH IIIB - Curing for End Bent 3 - WB Outside Widening Area (Bridge over International DR) | 7 | 11 |
IIIBWBO-ST450 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over universal BLVD) | 8 | 11 |
IIIBWBO-ST560 | PH IIIB - Set Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 4 | 14 |
IIIBWBO-ST610 | PH IIIB - Superstructure Deck SIP & Start Rebar - WB Outside Widening Area (Bridge over Shingle Creek) | 20 | 30 |
IIIBWBO-ST631 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over International DR) | 5 | 143 |
IIIBWBO-ST650 | PH IIIB - Demo Bridge Deck - WB Outside Widening Area (Bridge over Shingle Creek) | 6 | 43 |
IIIBWBO-ST660 | PH IIIB - Remove Beams - WB Outside Widening Area (Bridge over Shingle Creek) | 2 | 43 |
IIIBWBO-ST670 | PH IIIB - Demo Pile Cap - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 43 |
IIIBWBO-ST680 | PH IIIB - Extract Pile - WB Outside Widening Area (Bridge over Shingle Creek) | 3 | 43 |
IIIBWBO-ST750 | PH IIIB - Gravity Wall @ Shingle Creek - WB Outside Widening (Bridge over Shingle Creek) | 5 | 8 |
IIIBWBO-TC110 | PH IIIB - Set Temp Traffic Barriers - WB Outside Widening Area | 3 | 40 |
IIIBWBO-TC120 | PH IIIB - Temp Striping for Phase - WB Outside Widening Area | 4 | 111 |
IIICWBO-ST100 | PH IIIA - Demo Bridge - WB Outside Widening Area (Bridge over John Young PKWY) | 4 | 7 |
The following 97 activities should have started during this schedule period but have not as of October 21, 2018 data date.
Activity ID | Activity Description | Planned Start Date | Total Float |
---|---|---|---|
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 05-Dec-16 | -13 |
IIBR-GC100 | PH IIB - Demo - Ramp B | 09-Dec-16 | -39 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | 06-Jan-17 | -39 |
IIBR-RW100 | PH IIB - Stabilization - Ramp B | 08-Feb-17 | -39 |
IIBR-RW110 | PH IIB - Base - Ramp B | 16-Feb-17 | -39 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 27-Feb-17 | -3 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | 16-Mar-17 | -39 |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | 30-Mar-17 | -39 |
IIBR-GC160 | PH IIB - Guardrail (Roadway) - Ramp B | 05-Apr-17 | -39 |
IIBR-GC120 | PH IIB - Performance Turf, SOD - Ramp B | 17-Apr-17 | -39 |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 18-Apr-17 | -39 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 03-May-17 | -22 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | 05-Jun-17 | -34 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 08-Jun-17 | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 12-Jun-17 | -22 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | 25-Sep-17 | -9 |
TF-CO-021 | Install Bollards | 29-Sep-17 | -26 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 05-Oct-17 | -9 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 09-Oct-17 | -15 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 19-Oct-17 | -33 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 20-Oct-17 | -7 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 21-Nov-17 | -35 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 21-Nov-17 | -33 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 28-Nov-17 | -3 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | 29-Nov-17 | -26 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 04-Dec-17 | -32 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 21-Dec-17 | -35 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 01-Feb-18 | -73 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 15-Feb-18 | -73 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | 22-Feb-18 | -36 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 22-Feb-18 | -12 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 22-Feb-18 | -41 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 28-Feb-18 | -35 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 01-Mar-18 | -73 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 07-Mar-18 | -30 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | 08-Mar-18 | -36 |
IVEBM-W150 | PH IV - Median Wall - FFP Stem Station 207 to 217 | 09-Mar-18 | -30 |
TF-CO-032 | Toll Facility CO | 09-Mar-18 | -26 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | 15-Mar-18 | -73 |
NA-GC100 | TEC Install and Test | 16-Mar-18 | -34 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | 22-Mar-18 | -36 |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | 23-Mar-18 | -30 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 29-Mar-18 | -73 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | 30-Mar-18 | -30 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | 30-Mar-18 | -29 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 04-Apr-18 | -30 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 04-Apr-18 | -29 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 05-Apr-18 | -36 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | 06-Apr-18 | -21 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 06-Apr-18 | -30 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | 19-Apr-18 | -36 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 26-Apr-18 | -130 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 07-May-18 | -41 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 21-May-18 | -41 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 05-Jun-18 | -41 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 13-Jun-18 | -25 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 13-Jun-18 | -41 |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | 20-Jun-18 | -25 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | 20-Jun-18 | -41 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | 26-Jun-18 | -25 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 26-Jun-18 | -41 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 09-Jul-18 | -41 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 10-Jul-18 | -25 |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | 13-Jul-18 | -41 |
GC-GCN210 | PH MS - Punch List/Acceptance | 14-Jul-18 | -190 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | 16-Jul-18 | -25 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 17-Jul-18 | -36 |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | 17-Jul-18 | -25 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 18-Jul-18 | -42 |
IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | 26-Jul-18 | -31 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 27-Jul-18 | -31 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 26-Sep-16 | 0 |
IIBR-RW310 | PH IIB - Base - Ramp D | 15-Dec-16 | 1 |
IIBR-AP151 | PH IIB - Asphalt - Structural - Ramp D | 23-Dec-16 | 1 |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 27-Dec-16 | 1 |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | 10-Jan-17 | 2 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 01-Feb-17 | 0 |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 14-Feb-17 | 21 |
IIBR-GC430 | PH IIB - Guardrail (Roadway) - Ramp L | 13-Mar-17 | 4 |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 15-Mar-17 | 4 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 20-Mar-17 | 11 |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 19-Apr-17 | 2 |
IIBR-GC360 | PH IIB - Guardrail (Roadway) - Ramp H | 20-Apr-17 | 4 |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 24-Apr-17 | 4 |
IIIBR-GC120 | PH IIIB - Guardrail (Roadway) - Ramp G | 07-Jul-17 | 3 |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 11-Jul-17 | 3 |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 13-Sep-17 | 2 |
IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q | 13-Sep-17 | 1 |
IIIBR-GC160 | PH IIIB - Guardrail (Roadway) - Ramp J | 15-Sep-17 | 5 |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 15-Sep-17 | 1 |
USDET-CO-002 | Duke Energy Transmission Phase 4 | 18-Sep-17 | 46 |
IIIBR-GC230 | PH IIIB - Guardrail (Roadway) - Ramp V | 11-Oct-17 | 10 |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 13-Oct-17 | 10 |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 17-Nov-17 | 12 |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 06-Dec-17 | 4 |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 07-Dec-17 | 6 |
IVR-RES140 | PH IV - Remove Existing Sign Structures (14-16) | 22-Feb-18 | 2 |
The following 96 activities should have started during this schedule period but have not as of October 21, 2018 data date.
Activity ID | Activity Description | Planned Start Date | Total Float |
---|---|---|---|
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 05-Dec-16 | -13 |
IIBR-GC100 | PH IIB - Demo - Ramp B | 09-Dec-16 | -39 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | 06-Jan-17 | -39 |
IIBR-RW100 | PH IIB - Stabilization - Ramp B | 08-Feb-17 | -39 |
IIBR-RW110 | PH IIB - Base - Ramp B | 16-Feb-17 | -39 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 27-Feb-17 | -3 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | 16-Mar-17 | -39 |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | 30-Mar-17 | -39 |
IIBR-GC160 | PH IIB - Guardrail (Roadway) - Ramp B | 05-Apr-17 | -39 |
IIBR-GC120 | PH IIB - Performance Turf, SOD - Ramp B | 17-Apr-17 | -39 |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 18-Apr-17 | -39 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 03-May-17 | -22 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | 05-Jun-17 | -34 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 08-Jun-17 | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 12-Jun-17 | -22 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | 25-Sep-17 | -9 |
TF-CO-021 | Install Bollards | 29-Sep-17 | -26 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 05-Oct-17 | -9 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 09-Oct-17 | -15 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 19-Oct-17 | -33 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 20-Oct-17 | -7 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 21-Nov-17 | -35 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 21-Nov-17 | -33 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 28-Nov-17 | -3 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | 29-Nov-17 | -26 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 04-Dec-17 | -32 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 21-Dec-17 | -35 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 01-Feb-18 | -73 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 15-Feb-18 | -73 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | 22-Feb-18 | -36 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 22-Feb-18 | -12 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 22-Feb-18 | -41 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 28-Feb-18 | -35 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 01-Mar-18 | -73 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 07-Mar-18 | -30 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | 08-Mar-18 | -36 |
IVEBM-W150 | PH IV - Median Wall - FFP Stem Station 207 to 217 | 09-Mar-18 | -30 |
TF-CO-032 | Toll Facility CO | 09-Mar-18 | -26 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | 15-Mar-18 | -73 |
NA-GC100 | TEC Install and Test | 16-Mar-18 | -34 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | 22-Mar-18 | -36 |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | 23-Mar-18 | -30 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 29-Mar-18 | -73 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | 30-Mar-18 | -30 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | 30-Mar-18 | -29 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 04-Apr-18 | -30 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 04-Apr-18 | -29 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 05-Apr-18 | -36 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | 06-Apr-18 | -21 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 06-Apr-18 | -30 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | 19-Apr-18 | -36 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 26-Apr-18 | -130 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 07-May-18 | -41 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 21-May-18 | -41 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 05-Jun-18 | -41 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 13-Jun-18 | -25 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 13-Jun-18 | -41 |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | 20-Jun-18 | -25 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | 20-Jun-18 | -41 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | 26-Jun-18 | -25 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 26-Jun-18 | -41 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 09-Jul-18 | -41 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 10-Jul-18 | -25 |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | 13-Jul-18 | -41 |
GC-GCN210 | PH MS - Punch List/Acceptance | 14-Jul-18 | -190 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | 16-Jul-18 | -25 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 17-Jul-18 | -36 |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | 17-Jul-18 | -25 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 18-Jul-18 | -42 |
IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | 26-Jul-18 | -31 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 27-Jul-18 | -31 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 26-Sep-16 | 0 |
IIBR-RW310 | PH IIB - Base - Ramp D | 15-Dec-16 | 1 |
IIBR-AP151 | PH IIB - Asphalt - Structural - Ramp D | 23-Dec-16 | 1 |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 27-Dec-16 | 1 |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | 10-Jan-17 | 2 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 01-Feb-17 | 0 |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 14-Feb-17 | 21 |
IIBR-GC430 | PH IIB - Guardrail (Roadway) - Ramp L | 13-Mar-17 | 4 |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 15-Mar-17 | 4 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 20-Mar-17 | 11 |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 19-Apr-17 | 2 |
IIBR-GC360 | PH IIB - Guardrail (Roadway) - Ramp H | 20-Apr-17 | 4 |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 24-Apr-17 | 4 |
IIIBR-GC120 | PH IIIB - Guardrail (Roadway) - Ramp G | 07-Jul-17 | 3 |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 11-Jul-17 | 3 |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 13-Sep-17 | 2 |
IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q | 13-Sep-17 | 1 |
IIIBR-GC160 | PH IIIB - Guardrail (Roadway) - Ramp J | 15-Sep-17 | 5 |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 15-Sep-17 | 1 |
IIIBR-GC230 | PH IIIB - Guardrail (Roadway) - Ramp V | 11-Oct-17 | 10 |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 13-Oct-17 | 10 |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 17-Nov-17 | 12 |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 06-Dec-17 | 4 |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 07-Dec-17 | 6 |
IVR-RES140 | PH IV - Remove Existing Sign Structures (14-16) | 22-Feb-18 | 2 |
The following 137 activities should have completed during this schedule period but have not as of October 21, 2018 data date.
Activity ID | Activity Description | Planned Finish Date | Total Float |
---|---|---|---|
IBWBO-EW100 | PH IB - Pond Excav/Embank JYP to TPK - WB Outside Widening | 13-Oct-16 | -36 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 14-Oct-16 | -73 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 19-Oct-16 | -16 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 02-Nov-16 | -16 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 14-Nov-16 | -73 |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 09-Dec-16 | -39 |
IIBR-GC100 | PH IIB - Demo - Ramp B | 21-Dec-16 | -39 |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 04-Jan-17 | -13 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 04-Jan-17 | -16 |
IIBR-SP100 | PH IIB - Drainage - Ramp B | 06-Jan-17 | -39 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 27-Jan-17 | -72 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | 08-Feb-17 | -39 |
IIBR-RW100 | PH IIB - Stabilization - Ramp B | 16-Feb-17 | -39 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 16-Feb-17 | -36 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 02-Mar-17 | -3 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 08-Mar-17 | -41 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 13-Mar-17 | -3 |
IIBR-RW110 | PH IIB - Base - Ramp B | 16-Mar-17 | -39 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 21-Mar-17 | -34 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 24-Mar-17 | -72 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | 30-Mar-17 | -39 |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | 05-Apr-17 | -39 |
IIBR-GC160 | PH IIB - Guardrail (Roadway) - Ramp B | 17-Apr-17 | -39 |
IIBR-GC120 | PH IIB - Performance Turf, SOD - Ramp B | 18-Apr-17 | -39 |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 19-Apr-17 | -39 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 04-May-17 | -22 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 16-May-17 | -32 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 06-Jun-17 | -22 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | 07-Jun-17 | -34 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 12-Jun-17 | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 13-Jun-17 | -22 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 15-Jun-17 | -32 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 03-Jul-17 | -73 |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 03-Jul-17 | -36 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 06-Jul-17 | -36 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 12-Jul-17 | -11 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | 04-Oct-17 | -9 |
TF-CO-021 | Install Bollards | 06-Oct-17 | -26 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 12-Oct-17 | -15 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 19-Oct-17 | -33 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 20-Oct-17 | -34 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 23-Oct-17 | -7 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 25-Oct-17 | -53 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 26-Oct-17 | -9 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 20-Nov-17 | -35 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 27-Nov-17 | -53 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 28-Nov-17 | -33 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 06-Dec-17 | -32 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 11-Dec-17 | -3 |
TF-CO-029 | Install Conduit/Raceways | 12-Dec-17 | -18 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 20-Dec-17 | -35 |
TF-CO-026 | Cont. Lightning | 02-Jan-18 | -23 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 02-Jan-18 | -53 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | 05-Jan-18 | -26 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 16-Jan-18 | -3 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 22-Jan-18 | -35 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 31-Jan-18 | -53 |
TF-CO-030 | Pull Wire | 07-Feb-18 | -23 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 13-Feb-18 | -3 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 14-Feb-18 | -73 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 22-Feb-18 | -12 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 22-Feb-18 | -41 |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | 27-Feb-18 | -30 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 28-Feb-18 | -73 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 06-Mar-18 | -35 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 06-Mar-18 | -30 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | 07-Mar-18 | -36 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 08-Mar-18 | -30 |
TF-CO-031 | Toll Facility Finishes and Punchlist | 09-Mar-18 | -26 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 14-Mar-18 | -73 |
TF-CO-032 | Toll Facility CO | 16-Mar-18 | -26 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | 21-Mar-18 | -36 |
IVEBM-W150 | PH IV - Median Wall - FFP Stem Station 207 to 217 | 22-Mar-18 | -30 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | 28-Mar-18 | -73 |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | 29-Mar-18 | -30 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | 03-Apr-18 | -30 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | 03-Apr-18 | -29 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | 04-Apr-18 | -36 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 05-Apr-18 | -30 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 05-Apr-18 | -29 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | 12-Apr-18 | -21 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 12-Apr-18 | -30 |
NA-GC100 | TEC Install and Test | 16-Apr-18 | -34 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 18-Apr-18 | -36 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | 24-Apr-18 | -36 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 25-Apr-18 | -73 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 18-May-18 | -41 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 04-Jun-18 | -41 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 07-Jun-18 | -130 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 12-Jun-18 | -41 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 19-Jun-18 | -25 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 19-Jun-18 | -41 |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | 25-Jun-18 | -25 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | 25-Jun-18 | -41 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 06-Jul-18 | -41 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | 09-Jul-18 | -25 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 12-Jul-18 | -41 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 13-Jul-18 | -25 |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | 16-Jul-18 | -41 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | 17-Jul-18 | -25 |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | 17-Jul-18 | -25 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 25-Jul-18 | -42 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 26-Jul-18 | -36 |
IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | 01-Aug-18 | -31 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 02-Aug-18 | -31 |
GC-GCN210 | PH MS - Punch List/Acceptance | 12-Aug-18 | -190 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 14-Oct-16 | 0 |
IIBR-RW310 | PH IIB - Base - Ramp D | 20-Dec-16 | 1 |
IIBR-RW320 | PH IIB - Stabilization - Ramp D | 23-Dec-16 | 1 |
IIBR-AP151 | PH IIB - Asphalt - Structural - Ramp D | 27-Dec-16 | 1 |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 28-Dec-16 | 1 |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | 17-Jan-17 | 2 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 06-Feb-17 | 0 |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 20-Feb-17 | 21 |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 21-Feb-17 | 7 |
IIBR-GC430 | PH IIB - Guardrail (Roadway) - Ramp L | 15-Mar-17 | 4 |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 16-Mar-17 | 4 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 22-Mar-17 | 11 |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 19-Apr-17 | 2 |
IIBR-GC360 | PH IIB - Guardrail (Roadway) - Ramp H | 21-Apr-17 | 4 |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 24-Apr-17 | 2 |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 24-Apr-17 | 4 |
IIIBR-GC120 | PH IIIB - Guardrail (Roadway) - Ramp G | 10-Jul-17 | 3 |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 11-Jul-17 | 3 |
IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q | 14-Sep-17 | 1 |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 15-Sep-17 | 1 |
IIIBR-GC160 | PH IIIB - Guardrail (Roadway) - Ramp J | 18-Sep-17 | 5 |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 19-Sep-17 | 2 |
USDET-CO-002 | Duke Energy Transmission Phase 4 | 02-Oct-17 | 46 |
IIIBR-GC230 | PH IIIB - Guardrail (Roadway) - Ramp V | 12-Oct-17 | 10 |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 13-Oct-17 | 10 |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 22-Nov-17 | 12 |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 07-Dec-17 | 4 |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 07-Dec-17 | 6 |
IVR-EC30 | PH IV - Erect Cantilevers (10-15) | 01-Mar-18 | 7 |
IVR-RES140 | PH IV - Remove Existing Sign Structures (14-16) | 01-Mar-18 | 2 |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 22-Mar-18 | 3 |
The following 136 activities should have completed during this schedule period but have not as of October 21, 2018 data date.
Activity ID | Activity Description | Planned Finish Date | Total Float |
---|---|---|---|
IBWBO-EW100 | PH IB - Pond Excav/Embank JYP to TPK - WB Outside Widening | 13-Oct-16 | -36 |
IIBR-ITS10 | PH IIB - Install Conduit/Boxes (I-4 to International) | 14-Oct-16 | -73 |
IIBR-IHM320 | PH IIB - Install High Mast/Service (7-9) | 19-Oct-16 | -16 |
IIIBR-IHM330 | PH IIIB - Install High Mast/Service (10-13) | 02-Nov-16 | -16 |
IIBR-ITS20 | PH IIB - Install Conduit/Boxes ( International to Univ) | 14-Nov-16 | -73 |
IIBR-TC160 | PH IIB - Set Temp Traffic Barriers (Shoulder) - Ramp B | 09-Dec-16 | -39 |
IIBR-GC100 | PH IIB - Demo - Ramp B | 21-Dec-16 | -39 |
IIAR-TC130 | PH IIB - Construct variable Widening on I-4 (Ramp B to WB I-4) | 04-Jan-17 | -13 |
IIBR-EHM370 | PH IIB - Existing High Mast Removal (28-33) | 04-Jan-17 | -16 |
IIBR-SP100 | PH IIB - Drainage - Ramp B | 06-Jan-17 | -39 |
IIIBR-ITS1000 | PH IIIB - Install Conduit/Boxes (I-4 to International) | 27-Jan-17 | -72 |
IIBR-EW100 | PH IIB - Embankment - Ramp B | 08-Feb-17 | -39 |
IIBR-RW100 | PH IIB - Stabilization - Ramp B | 16-Feb-17 | -39 |
IIBR-GC190 | PH IIB - Performance Turf, SOD - Ramp E | 16-Feb-17 | -36 |
IIBR-GC210 | PH IIB - Performance Turf, SOD - Ramp I-1 | 02-Mar-17 | -3 |
IIIBR-SM510 | PH IIIB - Shoulder Mount Light Pole/Service (I-4 to International) (15) | 08-Mar-17 | -41 |
IIBR-CP10 | PH IIB - Construct Ped Signalization at Ramp I | 13-Mar-17 | -3 |
IIBR-RW110 | PH IIB - Base - Ramp B | 16-Mar-17 | -39 |
IIIBR-SM520 | PH IIIB - WB Shoulder Mount Light Pole/Service (I-4 to International) (9) | 21-Mar-17 | -34 |
IIIBR-ITS1020 | PH IIIB - Install Conduit/Boxes (Univ to JYP) | 24-Mar-17 | -72 |
IIBR-RW280 | PH IIB - Shoulder Gutter - Ramp B | 30-Mar-17 | -39 |
IIBR-AP100 | PH IIB - Asphalt - Structural - Ramp B | 05-Apr-17 | -39 |
IIBR-GC160 | PH IIB - Guardrail (Roadway) - Ramp B | 17-Apr-17 | -39 |
IIBR-GC120 | PH IIB - Performance Turf, SOD - Ramp B | 18-Apr-17 | -39 |
IIBR-TC420 | PH IIB - MOT Shift for Final Alignment - Ramp B | 19-Apr-17 | -39 |
IIIBR-GC210 | PH III C - Demo - old temp Ramp T gore | 04-May-17 | -22 |
IIIBR-SM540 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (20 EA) (B) | 16-May-17 | -32 |
IIIBR-RW190 | PH IIIB - Base - Ramp T | 06-Jun-17 | -22 |
IIIBWBO-ST500 | PH IIIB - Concrete Slope Pavement - WB Outside Widening Area (Bridge over International DR) | 07-Jun-17 | -34 |
IIIBR-GC290 | PH IIIB - Guardrail (Roadway) - Ramp T | 12-Jun-17 | -22 |
IIIBR-GC280 | PH IIIB - Performance Turf, SOD - Ramp T | 13-Jun-17 | -22 |
IIIBR-SM560 | PH IIIB - Shoulder Mount Light Pole/Service (International to Univ.) (11 EA) | 15-Jun-17 | -32 |
IIIBR-ITS90 | PH IIIB - Install ITS Cabinets/Hardware | 03-Jul-17 | -73 |
IIIBR-RW110 | PH IIIB - Base - Ramp G | 03-Jul-17 | -36 |
IIIBR-AP100 | PH IIIB - Asphalt - Structural - Ramp G | 06-Jul-17 | -36 |
IIBR-SM500 | PH IIB - Bridge Mount Light Poles/Service (1-10) | 12-Jul-17 | -11 |
IVR-SM660 | PH IV - Install Underdeck Lighting/Service (2 EA, OCCC Flyover) | 04-Oct-17 | -9 |
TF-CO-021 | Install Bollards | 06-Oct-17 | -26 |
IIBEBM-GC110 | PH IV - Rumble Strips - EB Median | 12-Oct-17 | -15 |
IIICR-TC130 | PH IIIC - Temp Striping New Ramp Alignment - Ramp F | 19-Oct-17 | -33 |
IIBEBO-GC110 | PH IIB - Performance Turf, SOD - EB Outside Widening | 20-Oct-17 | -34 |
IIICR-GC100 | PH IIIC - Demo - Old Ramp F | 23-Oct-17 | -7 |
IIIBR-ITS100 | PH IIIB - Install Vehicle Detection Systems (1-11) | 25-Oct-17 | -53 |
IVR-SM670 | PH IV - Install Underdeck Lighting/Service (4 EA, I-Drive) | 26-Oct-17 | -9 |
IVR-SM680 | PH IV - Install Underdeck Lighting/Service (4 EA, Universal) | 20-Nov-17 | -35 |
IIIBR-ITS110 | PH IIIB - Install Vehicle Detection Systems (12-22) | 27-Nov-17 | -53 |
IIIBWBO-GC110 | PH IIIB - Performance Turf, SOD - WB Outside Widening Area | 28-Nov-17 | -33 |
IIICR-GC140 | PH IIIC - Guardrail (Roadway) - Ramp F | 06-Dec-17 | -32 |
IIIBR-CP10 | PH IIIB - Construct Ped Signalization at Ramp K | 11-Dec-17 | -3 |
TF-CO-029 | Install Conduit/Raceways | 12-Dec-17 | -18 |
IVR-SM690 | PH IV - Install Underdeck Lighting/Service (8 EA, JYP) | 20-Dec-17 | -35 |
TF-CO-026 | Cont. Lightning | 02-Jan-18 | -23 |
IIIBR-ITS130 | PH IIIB - Install Digital Message Signs (1-12) | 02-Jan-18 | -53 |
TF-CO-028 | F+1 Tolling Cabinets + Frames | 05-Jan-18 | -26 |
IIIBR-SM640 | PH IIIB - Shoulder Mount Light Pole/Service (WB around JYP) (9 EA) | 16-Jan-18 | -3 |
IVR-SM700 | PH IV - Install Underdeck Lighting/Service (4 EA, Consulate Drive) | 22-Jan-18 | -35 |
IIIBR-ITS140 | PH IIIB - Install Digital Message Signs (13-23) | 31-Jan-18 | -53 |
TF-CO-030 | Pull Wire | 07-Feb-18 | -23 |
IIIBR-SM650 | PH IIIB - Bridge Mount Light Poles/Service (11-21) | 13-Feb-18 | -3 |
IIIBR-ITS150 | PH IIIB - Pull FOC (I-4 to International) | 14-Feb-18 | -73 |
IVEBO-TC100 | PH IV - Reconfigure & Remove MOT Devices - EB Outside Widening | 22-Feb-18 | -12 |
IVWBO-TC100 | PH IV - Shift WB traffic to outside over new WB I-Drive Bridge | 22-Feb-18 | -41 |
IVWBM-TC100 | PH IV - Set Temp Traffic Barriers - WB Median Widening | 27-Feb-18 | -30 |
IIIBR-ITS160 | PH IIIB - Pull FOC (International to Univ) | 28-Feb-18 | -73 |
IVEBM-GC100 | PH IV - Demo Temporary pavement - EB Express | 06-Mar-18 | -35 |
IVWBM-GC100 | PH IV - Demo Temporary - WB Express | 06-Mar-18 | -30 |
IVR-IPM70 | PH IV - Install Post Mount Signs (1-70) | 07-Mar-18 | -36 |
IVEBM-W140 | PH IV - Median Wall - Excavate - Station 207 to 217 | 08-Mar-18 | -30 |
TF-CO-031 | Toll Facility Finishes and Punchlist | 09-Mar-18 | -26 |
IIIBR-ITS170 | PH IIIB - Pull FOC (UNIV to JYP) | 14-Mar-18 | -73 |
TF-CO-032 | Toll Facility CO | 16-Mar-18 | -26 |
IVR-IPM80 | PH IV - Install Post Mount Signs (71-145) | 21-Mar-18 | -36 |
IVEBM-W150 | PH IV - Median Wall - FFP Stem Station 207 to 217 | 22-Mar-18 | -30 |
IIIBR-ITS180 | PH IIIB - Pull FOC (JYP to TPK) | 28-Mar-18 | -73 |
IVEBM-W160 | PH IV - Median Wall - Rebar/ slip Top Station 207 to 217 | 29-Mar-18 | -30 |
IVWBM-RW110 | PH IV - Grade for road - Station 207 to 217 WB Express | 03-Apr-18 | -30 |
IVWBM-RW200 | PH IV - Grade for road - Station 207 to 217 EB Express | 03-Apr-18 | -29 |
IVR-IPM90 | PH IV - Install Post Mount Signs (146-230) | 04-Apr-18 | -36 |
IVWBM-RW180 | PH IV - Stabilization for road - Station 207 to 217 WB Express | 05-Apr-18 | -30 |
IVWBM-RW210 | PH IV - Stabilization - Station 207 to 217 EB Express | 05-Apr-18 | -29 |
IVWBM-RW190 | PH IV - Base for road - Station 207 to 217 WB Express | 12-Apr-18 | -21 |
IVWBM-RW220 | PH IV - Base - Station 207 to 217 EB Express | 12-Apr-18 | -30 |
NA-GC100 | TEC Install and Test | 16-Apr-18 | -34 |
IVR-IPM100 | PH IV - Install Post Mount Signs (231-349) | 18-Apr-18 | -36 |
IIIBR-IBM110 | PH IIIB - Install Bridge Mount Signs | 24-Apr-18 | -36 |
IIIBR-ITS190 | PH IIIB - Splice/Terminate FOC | 25-Apr-18 | -73 |
IVEBM-W200 | PH IV - Median Wall - Excavate - Station 217 to 259+50 | 18-May-18 | -41 |
IVEBM-W210 | PH IV - Median Wall - FFP Stem - Station 217 to 259+50 | 04-Jun-18 | -41 |
NA-GC110 | PH PW - ITS Testing and Commissioning - Critical Areas | 07-Jun-18 | -130 |
IVEBM-W220 | PH IV - Median Wall - Rebar/ slip Top - Station 217 to 259+50 | 12-Jun-18 | -41 |
IVWBM-RW130 | PH IV - Grade for road Station 217 to 259+50 WB Express | 19-Jun-18 | -25 |
IVWBM-RW260 | PH IV - Subgrade Station 217 to 259+50 EB Express | 19-Jun-18 | -41 |
IVWBM-RW140 | PH IV - Stabilization - Station 217 to 259+50 WB Express | 25-Jun-18 | -25 |
IVWBM-RW270 | PH IV - Stabilization for Station 217 to 259+50 EB Express | 25-Jun-18 | -41 |
IVWBM-RW280 | PH IV - Base - Station 217 to 259+50 EB Express | 06-Jul-18 | -41 |
IVWBM-RW150 | PH IV - Base - Station 217 to 259+50 WB Express | 09-Jul-18 | -25 |
IVEBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 EB Express | 12-Jul-18 | -41 |
IVWBM-AP100 | PH IV - Asphalt - Structural - Station 207 to 259+50 WB Express | 13-Jul-18 | -25 |
IVEBM-TC110 | PH IV - Remove Temp Barrier - EB Median Widening | 16-Jul-18 | -41 |
IVWBM-TC110 | PH IV - Remove Temp barrier - WB Median Widening | 17-Jul-18 | -25 |
IVWBM-TC120 | PH IV - MOT Shift for Phase - WB Median Widening | 17-Jul-18 | -25 |
IVWBO-AP100 | PH IV - Asphalt - Friction - WB Outside Incl Ramp B,C | 25-Jul-18 | -42 |
IVEBO-AP100 | PH IV - Asphalt - Friction - EB Outside to JYP incl Ramp A,D | 26-Jul-18 | -36 |
IVWBO-PM110 | PH IV - Pavement Markings (Final) - WB Outside Widening Area | 01-Aug-18 | -31 |
IVEBO-PM110 | PH IV - Pavement Markings (Final) - EB Outside Widening | 02-Aug-18 | -31 |
GC-GCN210 | PH MS - Punch List/Acceptance | 12-Aug-18 | -190 |
IBR-GC100 | PH IB - Clear & Grub/Demo - Ramp B/C Gore | 14-Oct-16 | 0 |
IIBR-RW310 | PH IIB - Base - Ramp D | 20-Dec-16 | 1 |
IIBR-RW320 | PH IIB - Stabilization - Ramp D | 23-Dec-16 | 1 |
IIBR-AP151 | PH IIB - Asphalt - Structural - Ramp D | 27-Dec-16 | 1 |
IIBR-GC470 | PH IIB - Performance Turf, SOD - Ramp D | 28-Dec-16 | 1 |
IBR-AP110 | PH IB - Asphalt - Structural - Ramp B/C Gore | 17-Jan-17 | 2 |
IBR-GC110 | PH IB - Performance Turf, SOD - Ramp B/C Gore | 06-Feb-17 | 0 |
IIBR-IB10 | PH IIB - Install Bores/Loops/Boxes at Ramp E | 20-Feb-17 | 21 |
IICR-GC180 | PH IIC - Guardrail (Roadway) - Ramp M | 21-Feb-17 | 7 |
IIBR-GC430 | PH IIB - Guardrail (Roadway) - Ramp L | 15-Mar-17 | 4 |
IIBR-GC370 | PH IIB - Performance Turf, SOD - Ramp L | 16-Mar-17 | 4 |
IIBR-GC460 | PH IIB - Guardrail (Roadway) - Ramp U | 22-Mar-17 | 11 |
IIBR-GC200 | PH IIB - Grade ditch and SOD - Ramp C | 19-Apr-17 | 2 |
IIBR-GC360 | PH IIB - Guardrail (Roadway) - Ramp H | 21-Apr-17 | 4 |
IIBR-TC430 | PH IIB - MOT Shift for Final Alignment - Ramp C | 24-Apr-17 | 2 |
IIBR-GC320 | PH IIB - Performance Turf, SOD - Ramp H | 24-Apr-17 | 4 |
IIIBR-GC120 | PH IIIB - Guardrail (Roadway) - Ramp G | 10-Jul-17 | 3 |
IIIBR-GC110 | PH IIIB - Performance Turf, SOD - Ramp G | 11-Jul-17 | 3 |
IIIBR-GC360 | PH IIIB - Guardrail (Roadway) - Ramp Q | 14-Sep-17 | 1 |
IIIBR-GC350 | PH IIIB - Performance Turf, SOD - Ramp Q | 15-Sep-17 | 1 |
IIIBR-GC160 | PH IIIB - Guardrail (Roadway) - Ramp J | 18-Sep-17 | 5 |
IIIBR-CP170 | PH IIIB - Construct Ped Signalization at Ramp Q | 19-Sep-17 | 2 |
IIIBR-GC230 | PH IIIB - Guardrail (Roadway) - Ramp V | 12-Oct-17 | 10 |
IIIBR-GC200 | PH IIIB - Performance Turf, SOD - Ramp V | 13-Oct-17 | 10 |
IIIBWBM-GC110 | PH IIIB - Rumble Strip (Widening) - WB Median Widening | 22-Nov-17 | 12 |
IIICR-GC120 | PH IIIC - Performance Turf, SOD - Ramp F | 07-Dec-17 | 4 |
IIICR-GC130 | PH IIIC - Performance Turf, SOD - Ramp N | 07-Dec-17 | 6 |
IVR-EC30 | PH IV - Erect Cantilevers (10-15) | 01-Mar-18 | 7 |
IVR-RES140 | PH IV - Remove Existing Sign Structures (14-16) | 01-Mar-18 | 2 |
IVWBO-SS100 | PH IV - Install Overhead Signs Structures - WB Outside Widening Area | 22-Mar-18 | 3 |
The numbers in this report should not be relied upon, excercise caution and double-check the values.
This table represents monthly costs in E8P02 Update No 36
Month | Actual | Actual Cumul | Remaining Early | Remaining Early Cumul | Remaining Late | Remaining Late Cumul | |
---|---|---|---|---|---|---|---|
Aug-2015 | $5,906,772.92 | $5,906,772.92 | 0 | 0 | 0 | 0 | |
Sep-2015 | $2,471,526.40 | $8,378,299.32 | 0 | 0 | 0 | 0 | |
Oct-2015 | $4,010,141.75 | $12,388,441.07 | 0 | 0 | 0 | 0 | |
Nov-2015 | $1,370,791.46 | $13,759,232.53 | 0 | 0 | 0 | 0 | |
Dec-2015 | $1,087,352.39 | $14,846,584.93 | 0 | 0 | 0 | 0 | |
Jan-2016 | $665,835.32 | $15,512,420.25 | 0 | 0 | 0 | 0 | |
Feb-2016 | $1,013,974.26 | $16,526,394.50 | 0 | 0 | 0 | 0 | |
Mar-2016 | $635,461.93 | $17,161,856.43 | 0 | 0 | 0 | 0 | |
Apr-2016 | $695,096.93 | $17,856,953.36 | 0 | 0 | 0 | 0 | |
May-2016 | $1,841,865.56 | $19,698,818.92 | 0 | 0 | 0 | 0 | |
Jun-2016 | $2,133,459.20 | $21,832,278.12 | 0 | 0 | 0 | 0 | |
Jul-2016 | $2,666,571.77 | $24,498,849.89 | 0 | 0 | 0 | 0 | |
Aug-2016 | $1,556,235.15 | $26,055,085.04 | 0 | 0 | 0 | 0 | |
Sep-2016 | $1,375,097.31 | $27,430,182.35 | 0 | 0 | 0 | 0 | |
Oct-2016 | $1,187,196.19 | $28,617,378.54 | 0 | 0 | 0 | 0 | |
Nov-2016 | $1,080,977.50 | $29,698,356.04 | 0 | 0 | 0 | 0 | |
Dec-2016 | $3,493,958.18 | $33,192,314.22 | 0 | 0 | 0 | 0 | |
Jan-2017 | $2,518,687.26 | $35,711,001.48 | 0 | 0 | 0 | 0 | |
Feb-2017 | $2,206,879.69 | $37,917,881.17 | 0 | 0 | 0 | 0 | |
Mar-2017 | $2,866,857.38 | $40,784,738.55 | 0 | 0 | 0 | 0 | |
Apr-2017 | $1,820,613.08 | $42,605,351.63 | 0 | 0 | 0 | 0 | |
May-2017 | $1,500,322.86 | $44,105,674.49 | 0 | 0 | 0 | 0 | |
Jun-2017 | $1,810,796.01 | $45,916,470.50 | 0 | 0 | 0 | 0 | |
Jul-2017 | $1,537,190.48 | $47,453,660.98 | 0 | 0 | 0 | 0 | |
Aug-2017 | $2,251,744.38 | $49,705,405.36 | 0 | 0 | 0 | 0 | |
Sep-2017 | $1,742,718.15 | $51,448,123.50 | 0 | 0 | 0 | 0 | |
Oct-2017 | $2,515,027.06 | $53,963,150.56 | 0 | 0 | 0 | 0 | |
Nov-2017 | $2,682,347.93 | $56,645,498.49 | 0 | 0 | 0 | 0 | |
Dec-2017 | $2,525,253.10 | $59,170,751.60 | 0 | 0 | 0 | 0 | |
Jan-2018 | $2,699,943.26 | $61,870,694.86 | 0 | 0 | 0 | 0 | |
Feb-2018 | $2,229,196.52 | $64,099,891.38 | 0 | 0 | 0 | 0 | |
Mar-2018 | $2,788,612.63 | $66,888,504.01 | 0 | 0 | 0 | 0 | |
Apr-2018 | $2,425,962.04 | $69,314,466.05 | 0 | 0 | 0 | 0 | |
May-2018 | $2,718,592.52 | $72,033,058.57 | 0 | 0 | 0 | 0 | |
Jun-2018 | $1,373,138.22 | $73,406,196.80 | 0 | 0 | 0 | 0 | |
Jul-2018 | $1,138,335.30 | $74,544,532.10 | 0 | 0 | $564,508.81 | $564,508.81 | |
Aug-2018 | $1,493,678.52 | $76,038,210.61 | 0 | 0 | $1,079,669.61 | $1,644,178.42 | |
Sep-2018 | $1,370,812.93 | $77,409,023.54 | 0 | 0 | $2,109,514.81 | $3,753,693.23 | |
Oct-2018 | $2,073,235.13 | $79,482,258.67 | $4,777,943.78 | $4,777,943.78 | $5,262,603.90 | $9,016,297.13 | |
Nov-2018 | 0 | 0 | $3,228,161.84 | $8,006,105.62 | $3,985,463.06 | $13,001,760.18 | |
Dec-2018 | 0 | 0 | $2,770,242.78 | $10,776,348.40 | $517,954.15 | $13,519,714.33 | |
Jan-2019 | 0 | 0 | $2,028,299.43 | $12,804,647.83 | 0 | $13,519,714.33 | |
Feb-2019 | 0 | 0 | $76,163.63 | $12,880,811.46 | 0 | $13,519,714.33 | |
Mar-2019 | 0 | 0 | 0 | $12,880,811.46 | 0 | $13,519,714.33 | |
Apr-2019 | 0 | 0 | $3,793.00 | $12,884,604.46 | 0 | $13,519,714.33 | |
May-2019 | 0 | 0 | $36,505.54 | $12,921,110.00 | 0 | $13,519,714.33 | |
Jun-2019 | 0 | 0 | $404,873.56 | $13,325,983.56 | 0 | $13,519,714.33 | |
Jul-2019 | 0 | 0 | 0 | $13,325,983.56 | 0 | $13,519,714.33 |
The numbers in this report should not be relied upon, excercise caution and double-check the values.
This chart represents monthly costs in E8P02 Update No 36